BLD-Final | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Dave Hannah
|
|
|
Nate Phone #: ###-####
|
DOC - Permit Finaled | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Dave Hannah
|
|
|
|
Case Summary (BLD) | | | 6/7/2016 | | DONE |
|
|
|
|
BLD-Final | 6/3/2016 | 6/6/2016 | 6/6/2016 | A | FAIL |
Phil Shearer
|
|
|
Nate Phone #: ###-####. Handrail to high
|
BLD-Energy code compliance | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Dave Hannah
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 1/21/2016 | 1/22/2016 | 1/22/2016 | A | PASS |
Dave Hannah
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 1/19/2016 | 1/20/2016 | 1/20/2016 | A | PEND |
Dave Hannah
|
|
|
Nate Phone #: ###-#### needs truss engineering and air seal package.
|
Plan Modification Accepted | | | 1/19/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/19/2016 | | 1/19/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Framing/Rough-in | 1/13/2016 | 1/13/2016 | 1/13/2016 | P | NR |
Mike Jordan
|
|
|
Nate Phone #: ###-####. Needs mech. rough in inspection.
|
BLD-Wall Bracing | 12/29/2015 | 12/29/2015 | 12/30/2015 | P | PASS |
Dave Hannah
|
|
|
shear // nate Phone #: ###-#### ok to cover ext but needs to install several more holddowns on inside also ext fire treaded wood 4ft each way of prop line ok.
|
BLD-Foundation | 10/1/2015 | 10/1/2015 | 10/1/2015 | P | PASS |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 9/29/2015 | 9/30/2015 | 9/30/2015 | P | PASS |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 9/28/2015 | 9/29/2015 | 9/29/2015 | P | CANC |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 9/29/2015 | 9/29/2015 | 9/29/2015 | P | PASS |
Dave Hannah
|
|
|
garage ftg.
|
BLD-Footing | 9/28/2015 | 9/28/2015 | 9/28/2015 | P | PASS |
Mike Jordan
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 9/28/2015 | 9/28/2015 | 9/28/2015 | P | CANC |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
OVERRIDE | | | 9/10/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/10/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 9/10/2015 | | DONE |
Christina Prado
|
|
|
|
Place hold on job | 9/3/2015 | | 9/10/2015 | | DONE |
Christina Prado
|
|
|
DO NOT ISSUE WITHOUT BLD15-02674 AND BLD15-02675
|
Permit Ready to Issue | | | 9/10/2015 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/2/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 8/28/2015 | 8/28/2015 | 9/2/2015 | | DONE |
Brian McGowan
|
|
|
due 8/27 ePlan
|
1st review completed | | | 9/2/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/2/2015 | | 9/2/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
Permit Ready to Issue | | | 9/2/2015 | | DONE |
|
|
|
ALL REQUIREMENTS MET
|
Routing - PLAN CHECK | 8/6/2015 | | 9/2/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 8/6/2015 | | 9/2/2015 | | PASS |
Todd Tucker
|
|
|
|
Plan assigned to (LEG) Tisha | 8/6/2015 | | 8/28/2015 | | DEFR |
Tisha Gallop
|
|
|
8/27 ePlan L2 Townhouse (Bld15-02673 in ePlan)
|
Route to Impact Fee Review | 8/6/2015 | 8/9/2015 | 8/11/2015 | | PASS |
Stephanie Jensen
|
|
|
|
Routing - MECHANICAL | 8/6/2015 | | 8/7/2015 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 8/6/2015 | | 8/6/2015 | | PASS |
Emily Dixon
|
|
|
Address corrected to 2805 W Pleasanton Ave.
|
Routing - PUBLIC WORKS | 8/6/2015 | | 8/6/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 8/6/2015 | | PASS |
|
|
|
|
Intake Approval | | | 8/4/2015 | | FAIL |
Christina Prado
|
|
|
Need structural calcs, manual Js and res check uploaded. This is a submittal for three permits on one plan set, please update all three
|
Application received | | | 7/29/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2015 10:50PM
|