Print Statement | | | 2/16/2017 | | DONE |
|
|
|
2nd late notice since 7/28/16
|
Print Statement | | | 12/1/2016 | | DONE |
|
|
|
sent 1st notice that we have not recieved payment on FNL values
|
Meeting | | | 8/29/2016 | | DONE |
|
|
|
Sent notice back, again, since no one would return my call. Asked them to fill out the individual plumbing values as well as the mechanical value
|
Telephone call | | | 8/26/2016 | | DONE |
|
|
|
Left a message asking to have someone call me back so we can go over the final values given for the mechanical and the two plumbing permits.
|
Meeting | | | 8/18/2016 | | DONE |
|
|
|
Sent notice back since no one would return my call. Asked them to fill out the individual plumbing values as well as the mechanical value
|
Telephone call | | | 8/16/2016 | | DONE |
|
|
|
Left a message asking them to call me back so that I can put in the correct final values in for the two plumbing permits and the one mechanical permit.
|
Telephone call | | | 8/4/2016 | | DONE |
|
|
|
Left a message for Scott asking him to give me a call back. Gave a full totoal on final for plumbing and there are two permits by two different companies
|
Telephone call | | | 7/29/2016 | | DONE |
|
|
|
Left a message for Scott asking him to give me a call back. Gave a full totoal on final for plumbing and there are two permits by two different companies
|
Print Statement | | | 7/28/2016 | | DONE |
|
|
|
|
Second Notice | | 6/20/2016 | 7/14/2016 | | DONE |
|
|
|
Mailed 7-15-16
|
First Notice | | 5/14/2016 | 6/10/2016 | | DONE |
|
|
|
Mailed 6-13-16
|
Permanent Occupancy | | | 5/4/2016 | | DONE |
|
|
|
|
BLD-Final | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Jim Storey
|
|
|
would like call ahead; Scott Phone #: ###-#### pending plm sign off
|
FIRE-Final Inspection | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | PASS |
Jim Page
|
|
|
No fire alarms, one fire sprinkler located in compressed gas closet (Not associated with an FIR permit, sprinkler head is supplied by domestic water) fire extinguishers in place with current inspection tags. Thumb-turn deadbolt hardware on interior records room door will be removed. Final life fire safety inspection passed/complete.
|
Zoning Approval | 4/29/2016 | 4/29/2016 | 4/29/2016 | | DONE |
Andrea Tuning
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/28/2016 | | DONE |
|
|
|
plan mod fees paid
|
OVERRIDE | | | 4/6/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 4/1/2016 | 4/1/2016 | 4/6/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
RELOCATION OF DRINKING FOUNTAIN. Plan Mod. All Valley Pet Clinci
|
Routing - PLAN CHECK | 4/1/2016 | | 4/6/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2016 | | DONE |
|
|
|
plan mod fees due- DO NOT RE-ISSUE
|
Plan Modification Accepted | | | 4/1/2016 | | DONE |
Christina Prado
|
|
|
As requested by Arch firm to update location of drinking fountain
|
BLD-Footing | 1/29/2016 | 2/1/2016 | 2/1/2016 | P | PART |
Jim Storey
|
|
|
Early PM // Scott Phone #: ###-#### mti pending report
|
BLD-Framing/Rough-in | 1/25/2016 | 1/26/2016 | 1/26/2016 | A | FAIL |
Jim Storey
|
|
|
Scott Phone #: ###-#### need engineer to addres se1 ft hds nailling holes/ ceilling supports through out
|
Issue PAID IN FULL permit | | | 10/7/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/7/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/6/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 8/6/2015 | 8/6/2015 | 10/6/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
resubmittal recieved 1st review completed 9/2Level 3 TI - ePlanReview - All Valley Pet Clinic
|
Routing - PLAN CHECK | 10/6/2015 | | 10/6/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
called and spoke with Jim Story on door hardware 10/6/15
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/6/2015 | | DONE |
|
|
|
ALL REQUIRMENTS MET 10-7-15 //CEV need RP, GC and rev cert of val
|
Routing - PLAN CHECK | 9/29/2015 | | 9/29/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 9/14/2015 | 9/14/2015 | 9/16/2015 | | PASS |
Katie Marron
|
|
|
Previous correction item resolved. Updated report attached to case.
|
Routing - PLAN CHECK | 9/14/2015 | | 9/14/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
need exit door hardware specifications/ drinking fountain hi/low
|
1st review completed | | | 8/27/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/6/2015 | | 8/27/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 8/6/2015 | 8/6/2015 | 8/11/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to case and emailed to architect.
|
Routing - MECHANICAL | 8/6/2015 | | 8/7/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/6/2015 | | 8/7/2015 | | PASS |
Brent Moore
|
|
|
Brent Moore - CUP15-00027
|
Routing - Design Review | 8/6/2015 | | 8/7/2015 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - CZC15-00199
|
Routing PW Sewer Rating | 8/7/2015 | | 8/7/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLUMBING | 8/6/2015 | | 8/7/2015 | | PASS |
Bill VanDegrift
|
|
|
May require additional backflow protection on installed equipment
|
Routing - Addressing | 8/6/2015 | | 8/7/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/6/2015 | | 8/7/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 8/6/2015 | | 8/7/2015 | | PASS |
Evan Jenkins
|
|
|
Waiver Request Approved
(ALL VALLEY PET CLINIC) Remodel to convert an existing assembly restaurant to a new animal veterinary clinic within an existing 5,585 sq. ft. building per approved plans. Work to include interior demolition work, some new interior structural work (pad footings, columns beams, headers) new interior walls and doors, interior finish, suspended ceiling work, three new skylights, paint exterior, add flashing cap to entry archways, some new roofing, plumbing work, mechanical work and electrical work
|
Intake Approval | | | 8/6/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Pending Assignment by JCB | 8/6/2015 | | 8/6/2015 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 8/6/2015 | | DONE |
Jason Blais
|
|
|
No ACHD impact fees per email from ACHD uploaded into the ePlanReview system.
|
Intake Approval | | | 8/5/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please re up load all drawings to read left to right.
Please make sure to name them exactly the same in order for them to version over top of the original submittal.
Please make sure all drawings are a min. 18'x24' in size
|
Intake Approval | | | 8/5/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
There are 4 drawings that failed to upload, scroll down to yellow ! mark. The file names are to long. Please upload with new shorter file names. I will delete the old names once you have uploaded new files.
|
Application received | | | 7/31/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 31 2015 4:23PM
|