Second Notice | | 9/26/2016 | 9/29/2016 | | DONE |
|
|
|
This permit finaled on the web by Kim Anderson
|
First Notice | 9/1/2016 | 9/1/2016 | 9/16/2016 | | DONE |
Jim Storey
|
|
|
Mailed 9-19-16
|
BLD-Final | 8/31/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Jim Storey
|
|
|
would like call ahead; Caleb Phone #: ###-####
|
DOC - Permit Finaled | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications required, no fire alarm modifications required, equipment is unoccupied and located on the roof, fire extinguisher located inside cabinet, final life fire safety inspection passed/complete.
|
Zoning Approval | 9/1/2016 | 9/1/2016 | 9/1/2016 | | DONE |
David Moser
|
|
|
|
BLD-Aging Inspection | 8/29/2016 | 8/29/2016 | 8/29/2016 | | PEND |
Tony Young
|
|
|
|
Issue PAID IN FULL permit | | | 10/14/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/14/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/6/2015 | 8/6/2015 | 10/13/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing Off Site - STRUCTURAL | 9/21/2015 | | 10/13/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2015 | | DONE |
|
|
|
***STILL NEEDS ACHD*** Needs; GC Form, Revised Cert of Value, & ACHD
|
Routing - PLANNING | 9/17/2015 | | 9/17/2015 | | PASS |
David Moser
|
|
|
|
Routing - FIRE | 8/6/2015 | 8/6/2015 | 8/11/2015 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
1st review completed | | | 8/11/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/6/2015 | | 8/11/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 8/6/2015 | | 8/7/2015 | | FAIL |
David Moser
|
|
|
Need to provide screening for the equipment cabinets since the design has change from the approved plans (CAA14-00239).
|
Routing - Addressing | 8/6/2015 | | 8/7/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/6/2015 | | 8/7/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 8/6/2015 | | 8/7/2015 | | CANC |
Evan Jenkins
|
|
|
No ESC Permit Required: No Earth Disturbance
|
Routing - Design Review | 8/6/2015 | | 8/7/2015 | | FAIL |
Josh Wilson
|
|
|
Roof mounted equipment has increased in height to project above parapet. Screen wall will be required.
|
Intake Approval | | | 8/6/2015 | | PASS |
|
|
|
|
Intake Approval | | | 8/4/2015 | | FAIL |
|
|
|
PLease provide a completed submittal checklist with all required items. I was also looking through the engineering and noticed ther were no calculations provided. Please provide all calculations to support your conclusions.
|
Application received | | | 8/3/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2015 9:18AM
|