BLD-Final | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Jim Sly
|
|
|
Please call on advance so I can let you in! Phone #: ###-#### Inspection requested via web by Andy Thompson
|
DOC - Permit Finaled | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | FAIL |
Jim Sly
|
|
|
Complete yesterday Phone #: ###-#### Inspection requested via web by Andy Thompson Handrails......
|
Zoning Approval | 5/2/2016 | 5/2/2016 | 5/2/2016 | | DONE |
Andrea Tuning
|
|
|
|
Place hold on job | 3/7/2016 | | 4/29/2016 | | DONE |
Christina Prado
|
|
|
Ok for CO issuance per attached ACHD Letter 4/29/16///No CO is to be issued without approval from ACHD, see Christina with questions
|
BLD-Energy code compliance | 1/19/2016 | 1/19/2016 | 1/19/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PASS |
Jim Sly
|
|
|
Andy Phone #: ###-####
|
BLD-Wall Bracing | 12/15/2015 | 12/15/2015 | 12/15/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Conference | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | DONE |
Jim Sly
|
|
|
Please call 20 min before so I can meet you out there. Thanks! -Andy Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Foundation | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | PART |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 9/18/2015 | 9/18/2015 | 9/18/2015 | P | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 9/15/2015 | 9/16/2015 | 9/16/2015 | P | NR |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
OVERRIDE | | | 9/14/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/14/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 9/14/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (LEG) Tisha | 8/13/2015 | | 9/14/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 9/2; building, planning
|
Routing - PLAN CHECK | 9/10/2015 | | 9/14/2015 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/14/2015 | | DONE |
|
|
|
all requirments met
|
Routing - PLANNING | 9/10/2015 | | 9/10/2015 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 9/10/2015 | | DONE |
|
|
|
|
1st review completed | | | 9/2/2015 | | FAIL |
|
|
|
plan check & planning
|
Routing - PLAN CHECK | 8/13/2015 | | 9/2/2015 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 8/13/2015 | | 8/14/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/13/2015 | | 8/14/2015 | | FAIL |
Andrea Tuning
|
|
|
A common wall agreement is required.
|
Routing - PUBLIC WORKS | 8/13/2015 | | 8/14/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 8/13/2015 | | 8/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 8/13/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/13/2015 | | DONE |
|
|
|
|
Telephone call | | | 8/12/2015 | | DONE |
|
|
|
called Andy to remind him that I need the building section before I can start the reviewing process. He said he'd get his designer to get it to me. BRD15-02742, BRD15-02737 & BRD15-02736 re the other 3 permits that we need the building sections for
|
Intake Approval | | | 8/6/2015 | | FAIL |
|
|
|
Missing Res Check, Foundation Plan, Wall Bracing, Cross Section, Floor Framing and Pony/Cripple Walls
|
Application received | | | 8/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 4 2015 11:48AM
|