Third Notice | | 3/2/2016 | 3/3/2016 | | DONE |
|
|
|
This permit finaled on the web by Admin Assistant
|
Second Notice | | 1/21/2016 | 2/26/2016 | | DONE |
|
|
|
|
First Notice | | 12/14/2015 | 1/11/2016 | | DONE |
|
|
|
Mailed 1-12-16
|
BLD-Final | 12/4/2015 | 12/4/2015 | 12/4/2015 | P | PASS |
Dave Hannah
|
|
|
would like call ahead; Lloyd Phone #: ###-####
|
Permanent Occupancy | | | 12/4/2015 | | DONE |
|
|
|
|
BLD-Final | 12/1/2015 | 12/3/2015 | 12/3/2015 | P | NR |
Dave Hannah
|
|
|
Lloyd-please call 30 minutes prior to meet Phone #: ###-#### needs to change lock on int door
|
FIRE-Final Inspection | 12/1/2015 | 12/2/2015 | 12/2/2015 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no modifications to the fire alarm system. Life fire safety inspection passed/complete
|
BLD-Framing/Rough-in | 10/20/2015 | 10/21/2015 | 10/22/2015 | P | PASS |
Dave Hannah
|
|
|
Call 30 mins before // Lloyd Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/5/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/2015 | | DONE |
|
|
|
|
Plan assigned to (JG) | 8/5/2015 | 8/5/2015 | 8/12/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 8/11 Foothills Psychiatry
|
Routing - PLAN CHECK | 8/12/2015 | | 8/12/2015 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/12/2015 | | DONE |
Christina Prado
|
|
|
All requirements met////Needs GC Form & Revised certificate of value
|
1st review completed | | | 8/7/2015 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/5/2015 | | 8/7/2015 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - PUBLIC WORKS | 8/6/2015 | | 8/6/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 8/5/2015 | | 8/5/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 8/5/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 8/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 4 2015 3:37PM
|