Second Notice | | 2/21/2016 | 2/26/2016 | | DONE |
|
|
|
This permit finaled on the web by Tara May
|
First Notice | | 2/5/2016 | 2/11/2016 | | DONE |
|
|
|
mailed 2-12-16
|
Permanent Occupancy | | | 1/26/2016 | | DONE |
|
|
|
|
Temporary Occupancy | 12/1/2015 | 2/29/2016 | 12/1/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 11/19/2015 | 11/20/2015 | 11/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson perm final ok pending pw sign off
|
FIRE-Final Inspection | 11/19/2015 | 11/20/2015 | 11/20/2015 | A | PASS |
Jim Page
|
|
|
FIR permit inspection for fire sprinklers complete, FIR permit inspection for fire alarms complete. Life fire safety inspection passed/complete.
|
FIRE-Alarm Testing | 11/19/2015 | 11/19/2015 | 11/19/2015 | A | CANC |
Jim Page
|
|
|
Spoke to point of contact, Scott phone number ###-####, informed him that core/shell FIR permits for alarms and fire sprinklers need to be completed before final inspection. FIR permits for fire alarms and fire sprinklers need to be complete for tenant space before final life fire safety inspection can be completed. This inspection cancelled and will be scheduled for a later date.
|
FIRE-Final Inspection | 11/19/2015 | 11/19/2015 | 11/19/2015 | A | CANC |
Jim Page
|
|
|
Spoke to point of contact, Scott phone number ###-####, informed him that core/shell FIR permits for alarms and fire sprinklers need to be completed before final inspection. FIR permits for fire alarms and fire sprinklers need to be complete for tenant space before final life fire safety inspection can be completed. This inspection cancelled and will be scheduled for a later date.
|
PubWorks Temp Occupancy Appr | 11/19/2015 | 11/19/2015 | 11/19/2015 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 11/19/2015 | 11/19/2015 | 11/19/2015 | | PASS |
Josh Wilson
|
|
|
|
BLD-Conference | 11/18/2015 | 11/18/2015 | 11/18/2015 | P | DONE |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
Print Occupancy Form | | | 11/16/2015 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 11/6/2015 | 11/6/2015 | 11/6/2015 | P | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
Override - Parcel Holds | 11/6/2015 | 1/1/1900 | 11/6/2015 | | |
|
|
|
does not apply to this permit
|
BLD-Ceiling Grid Inspection | 10/30/2015 | 10/30/2015 | 11/2/2015 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Ceiling Grid Inspection | 11/2/2015 | 11/2/2015 | 11/2/2015 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Ceiling Grid Inspection | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 10/7/2015 | 10/8/2015 | 10/8/2015 | P | PASS |
Dave Hannah
|
|
|
This is for the restrooms and hallway hard lids and soffit framing. Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 9/30/2015 | 10/2/2015 | 10/6/2015 | P | PASS |
Dave Hannah
|
|
|
interior partial framing. Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PART |
Jim Sly
|
|
|
Scott Phone #: ###-#### Exterior pop out wall for menu board at front entry.......OK.
|
OVERRIDE | | | 9/14/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 8/7/2015 | 8/7/2015 | 9/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - Cafe Zupas
|
Issue PAID IN FULL permit | | | 9/14/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/14/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/10/2015 | | 9/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/14/2015 | | DONE |
|
|
|
***all requirments met 9-14-15//CEV NEED RP, GC form, and Certificate of Value
|
1st review completed | | | 9/3/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/7/2015 | | 9/3/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing Off Site - C.D.H | 8/7/2015 | | 8/27/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Environmental | 8/10/2015 | | 8/14/2015 | | PASS |
Rick Christenson
|
|
|
Need verification on size of grease interceptor and verifiy working condition.
|
Routing - MECHANICAL | 8/7/2015 | | 8/14/2015 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 8/7/2015 | 8/7/2015 | 8/12/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments and conditions of approval to plans.
|
Plan Reviewer's activity | | | 8/11/2015 | | DONE |
Jason Blais
|
|
|
No ACHD impact fees or inspection required per email from Austin Miller at ACHD:
Jamin and Lou,
Thank you for your help. With regard to the Café Zupas TI at 111 S. Broadway, there is No Impact Fee Due and an ACHD inspection is not required.
Thank you,
Austin Miller
Ada County Highway District
Planner I, Development Services
3775 Adams Street, Garden City, ID 83714
Phone: ###-####
E-mail: Amiller@achdidaho.org
|
Routing - Addressing | 8/7/2015 | | 8/11/2015 | | PASS |
Emily Dixon
|
|
|
Address corrected to 133 S Broadway Ave.
|
Routing - PUBLIC WORKS | 8/7/2015 | | 8/10/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLUMBING | 8/7/2015 | | 8/10/2015 | | PASS |
Bill VanDegrift
|
|
|
1) vent over length trap arms
2) use island sink venting not AAV
3) additional cross connection protection may be required
4) use trap primers not proseal etc.
5) mixing valves at hand sinks and public lavs must be ASSE 1070
6) RP required upstream of the filtered water systems
|
Routing PW Sewer Rating | 8/10/2015 | | 8/10/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 8/7/2015 | | 8/10/2015 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. Need to designate RP on permit.
|
Routing - Design Review | 8/7/2015 | | 8/10/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00244
|
Plan Reviewer's activity | | | 8/7/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to have him contact ACHD to determine if any additional impact fees are due. Written verification from ACHD shall be provided to our Permit Counter prior to the building permit being issued.
|
Intake Approval | | | 8/7/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Pending Assignment by JCB | 8/7/2015 | | 8/7/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 8/6/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see check list for the additional items needed.
This project will route as a major TI.
|
Application received | | | 8/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 5 2015 10:34AM
|