Permit Information
Permit NumberBLD15-02772
StatusFinaled
Name CM COMPANY
Site Address 481 W GOWEN RD
Project NameBoise School District O&M Bldg
Customer NumberBLD15-03937; BLD15-03938
ePlanReviewYes
Description
(BOISE SCHOOL DISTRICT OPERATIONS & MAINTENANCE BUILDING – Building “A”) Permit to include construction of a 50,564 square foot building primarily used as office area and a vehicle repair shop. PLAN MODIFICATION 2-23-15 – Modification submitted to value engineer the mechanical system and related work. **TLW** This building is fire sprinklered for area increases. Work to include: concrete foundation, typical metal building structural frame, interior partitions to create several offices, several separate warehouses, 7 separate mezzanines each under 3,000 square feet and each for separate “tenants” within the overall building, new plumbing, new mechanical, new electrical, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 5/15/20175/24/2017 DONE
This permit finaled on the web by Jackie Phelps
Second Notice 4/21/20175/10/2017 DONE
sent in mail 5-11-17
First Notice 3/31/20174/11/2017 DONE
sent in mail 4-12-17
Permanent Occupancy  3/21/2017 DONE
FIRE-Final Inspection3/20/20173/20/20173/20/2017PPASS
DetailsTroy Cobbley
life safety passed per Scott Arellano
BLD-Final3/17/20173/20/20173/20/2017PPASS
DetailsJim Storey
Tom Phone #: ###-#### final ok
BLD-Final3/17/20173/17/20173/17/2017PNR
DetailsJim Sly
Tom Phone #: ###-####
Need to verify that ACHD has been finaled. Need Fire alarm, Fire sprinkler and Fire/ Life safety Finals, To obtain C of O.
BLD-Final2/16/20172/16/20172/16/2017PPASS
DetailsJim Storey
Tom Phone #: ###-#### final ok
BLD-Aging Inspection2/14/20172/14/20172/15/2017 PASS
DetailsJim Storey
PubWorks Occupancy Approval12/5/20162/7/20172/7/2017 DONE
DetailsTiffany Lowery
BLD-Final12/15/201612/16/201612/16/2016APART
DetailsJim Storey
Tom Phone #: ###-#### temp ok/ glazing at 3/4 hr doors
Temporary Occupancy12/16/20163/16/201712/16/2016 DONE
DetailsCandy A. Nichols
pending final ele, mech, fire & structural
FIRE-Final Inspection12/14/201612/15/201612/15/2016PPART
DetailsJim Page
Partial life fire safety inspection complete for TCO, fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, emergency lighting including exit discharge has been inspected, knox box is in place. Fuel island is still under construction, fuel island is under this permit and will be inspected when completed. Paint booth is to be built at a later date, paint booth has an FIR permit associated with the fire sprinklers that will remain in issued status until paint booth is complete (FIR16-00716) Exit sign that is in place for the paint shop exit is temporary, permanent exit sign for this area is on order, will verify install at a later date. Fire hydrants located on the northwest and southwestside of compound will need to be rotated so the large discharge is not pointing at bollards, fire hydrant rotation will be verified during permanet CO inspection.
Zoning Approval12/12/201612/12/201612/12/2016 DONE
DetailsAndrea Tuning
BLD-Other12/2/201612/2/201612/2/2016PPASS
DetailsJim Storey
Tom-fire caulking above ceiling Phone #: ###-####
BLD-Ceiling Grid Inspection11/28/201611/29/201611/29/2016APASS
DetailsJim Storey
Tom Phone #: ###-#### ceillings ok all but rated walls
BLD-Other11/17/201611/18/201611/18/2016AFAIL
DetailsJim Storey
Above ceiling // Tom Phone #: ###-#### provide listings for through pentrations
BLD-Ceiling Grid Inspection11/16/201611/17/201611/17/2016APART
DetailsJim Storey
Tom Phone #: ###-####
BLD-Ceiling Grid Inspection11/10/201611/10/201611/10/2016PCANC
DetailsPhil Shearer
Dave Phone #: ###-####
BLD-Conference10/10/201610/11/201610/11/2016APASS
DetailsJim Storey
tom ###-####
BLD-Framing/Rough-in9/29/20169/30/20169/30/2016APART
DetailsDave Hannah
Tom Phone #: ###-#### walked project with contractor
BLD-Framing/Rough-in9/9/20169/9/20169/9/2016PPASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Framing/Rough-in8/11/20168/12/20168/12/2016APASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Concrete8/1/20168/2/20168/2/2016PPASS
DetailsJim Storey
Tom Phone #: ###-####
OVERRIDE  8/1/2016  
CHANGE STATUS TO (ISS)  8/1/2016 DONE
NO plan mod fees due
PLANS/APPL TAKEN TO FRONT DESK  8/1/2016 DONE
Permit Ready to Issue  8/1/2016 DONE
No plan mod fees due as per Tim Woodard
Routing - PLAN CHECK7/11/2016 8/1/2016 PASS
DetailsTim L. Woodard
2nd Plan Mod for minor Exterior Changes. Approved by DR and PW. No fees due OK to re-issue. TLW
Plan assigned to (TLW)7/11/2016 8/1/2016 PASS
DetailsTim L. Woodard
Routing PW Drainage7/11/2016 7/27/2016 PASS
DetailsBrian Murphy
revised drainage plan.
BLD-Conference7/15/20167/18/20167/18/2016APASS
DetailsJim Storey
Fire Wall questions - Tom Phone #: ###-#### 9:00 appt
BLD-Conference7/14/20167/15/20167/15/2016PDEFR
DetailsJim Storey
Fire Wall questions - Tom Phone #: ###-####
Routing - Design Review7/11/2016 7/12/2016 PASS
DetailsSarah Schafer
Plan Modification Accepted  7/11/2016 DONE
DetailsChristina Prado
Per LCA - Plan mod to update civil drawings
Routing - PUBLIC WORKS7/11/2016 7/11/2016 PASS
DetailsRachael Beierle
BLD-Foundation5/27/20165/27/20165/27/2016PPART
DetailsPhil Shearer
Dave Phone #: ###-####. Pending MTI inspection
BLD-Footing5/19/20165/20/20165/20/2016APART
DetailsJim Storey
Tom Phone #: ###-####placed w si
BLD-Footing5/16/20165/16/20165/16/2016PPASS
DetailsJim Storey
Tom Phone #: ###-#### with si
BLD-Wall cover5/12/20165/13/20165/13/2016APASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Wall Bracing5/11/20165/12/20165/12/2016ADEFR
DetailsJim Storey
Tom Phone #: ###-#### out of time
BLD-Foundation5/4/20165/5/20165/5/2016APASS
DetailsJim Storey
Rebar // Tom Phone #: ###-####wip/si
BLD-Footing4/28/20164/29/20164/29/2016APASS
DetailsJim Storey
Spread footing & stemwall with 10AM pour - Tom Phone #: ###-####w/si
BLD-Other4/26/20164/27/20164/28/2016PPASS
DetailsJim Storey
slab on grade - Tom Phone #: ###-####si pending out of time
BLD-Foundation4/19/20164/19/20164/20/2016PPASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Footing4/14/20164/14/20164/14/2016PPASS
DetailsJim Storey
Tom-spread footing and pier pads Phone #: ###-#### placed w/si
BLD-Footing4/8/20164/12/20164/12/2016APASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Footing4/7/20164/8/20164/8/2016APASS
DetailsJim Storey
would like call ahead; Dave Phone #: ###-####
BLD-Foundation4/4/20164/5/20164/5/2016APASS
DetailsJim Storey
would like call ahead; Tom Phone #: ###-####pwsi
BLD-Footing3/31/20164/1/20164/1/2016PPASS
DetailsJim Storey
Tom Phone #: ###-#### placed w si
BLD-Foundation3/30/20163/31/20163/31/2016APART
DetailsJim Storey
would like call ahead; Tom Phone #: ###-#### wall ok pend s
BLD-Foundation3/25/20163/28/20163/28/2016APART
DetailsMike Jordan
Tom Phone #: ###-####. West concrete wall and column pad footings at main building. COlumn pad footings need rings at 3 inches on center and crossties. Special inspector to verify repair.
BLD-Footing3/21/20163/22/20163/22/2016ADEFR
DetailsMike Jordan
Tom// 1pm pour time Phone #: ###-####. Special inspector on site.
BLD-Footing3/18/20163/21/20163/21/2016ACANC
DetailsJim Storey
Tom Phone #: ###-####
BLD-Foundation3/16/20163/17/20163/17/2016APART
DetailsJim Storey
10:30 pour; Tom Phone #: ###-####pwsi
BLD-Footing3/10/20163/11/20163/11/2016APASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Footing3/8/20163/9/20163/9/2016AFAIL
DetailsJim Storey
Tom Phone #: ###-#### fill without compaction/ rebar in the dirt bottom and sides of foottings
BLD-Foundation2/29/20163/1/20163/1/2016APART
DetailsJim Storey
Wall // Tom Phone #: ###-#### pending si reports
Place hold on job2/24/2016 2/29/2016 DONE
DetailsBrittany Hill
FIRE REVIEW FEES DUE ON BLD15-03937 & BLD15-03938-- DO NO RE-ISSUE THIS PERMIT WITHOUT THOSE FEES BEING PAID
CHANGE STATUS TO (ISS)  2/29/2016 DONE
Plan Mod
(F) Reprint permit  2/29/2016 DONE
BLD-Footing2/23/20162/24/20162/24/2016APASS
DetailsJim Storey
Tom Phone #: ###-####pending si
OVERRIDE  2/24/2016  
PLANS/APPL TAKEN TO FRONT DESK  2/24/2016 DONE
Permit Ready to Issue  2/24/2016 DONE
DetailsChristina Prado
DO NOT RE-ISSUE
All requirements met for Plan Mod

Must pay all fees prior to changing status to ISS
Routing Off Site - STRUCTURAL1/26/2016 2/24/2016 PASS
DetailsTim L. Woodard
Plan assigned to (TLW)1/25/2016 2/24/2016 PASS
DetailsTim L. Woodard
new plan mod in e plan review
Routing - PLAN CHECK1/26/2016 2/24/2016 PASS
DetailsTim L. Woodard
BLD-Footing2/17/20162/18/20162/18/2016APART
DetailsJim Storey
Tom Phone #: ###-#### pending si
Routing - MECHANICAL1/26/2016 1/28/2016 PASS
DetailsTroy James
Plan Modification Accepted  1/25/2016 DONE
e plan review
Override - Parcel Holds  12/22/2015  
Issue PAID IN FULL permit  12/22/2015 DONE
Print Occupancy Form  12/22/2015 DONE
OVERRIDE  12/11/2015  
Permit Ready to Issue  12/11/2015 DONE
all requirements met-see ACHD letter in documents-inspection required***3 permits**need ACHD all other requirements have been met
Plan assigned to (TLW)8/13/2015 12/10/2015 PASS
DetailsTim L. Woodard
1st review complete - School District
Routing - PLAN CHECK11/20/2015 12/10/2015 PASS
DetailsTim L. Woodard
Routing Off Site - STRUCTURAL11/20/2015 12/10/2015 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  12/10/2015 DONE
Routing PW Environmental10/13/2015 11/20/2015 PASS
DetailsRick Christenson
Approved Flammable interceptor.
Routing PW Sewer Design10/13/2015 11/20/2015 PASS
DetailsKyle S. Rosenmeyer
Approved in E-Plan. TLW
Plan resubmittals received  11/20/2015 DONE
Routing PW Environmental10/13/2015 11/20/2015 PASS
DetailsRick Christenson
Approved in E-Plan. TLW
Routing - PLAN CHECK10/13/2015 11/20/2015 PASS
DetailsTim L. Woodard
Routing Off Site - STRUCTURAL10/13/2015 11/20/2015 FAIL
DetailsTim L. Woodard
Routing - FIRE10/13/201510/13/201510/14/2015 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - MECHANICAL10/13/2015 10/14/2015 PASS
DetailsTroy James
Plan resubmittals received  10/13/2015 DONE
DetailsJason Blais
Received resubmittals via ePlanReview. Rerouted resubmittal plans out for review.
Routing - PUBLIC WORKS10/13/2015 10/13/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment10/13/2015 10/13/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

(BOISE SCHOOL DISTRICT OPERATIONS & MAINTENANCE BUILDING) New 50,500 square feet operations and maintenance facility for the Boise School District. One main operations / maintenance / office building, one storage building and one air open shed building.
Routing - Design Review10/13/2015 10/13/2015 PASS
DetailsAndrea Tuning
Andrea Tuning
Routing PW Sewer Design10/13/2015 10/13/2015 PASS
DetailsKyle S. Rosenmeyer
Route to Impact Fee Review9/15/20159/18/20159/17/2015 PASS
DetailsStephanie Jensen
Routing PW Solid Waste8/13/2015 9/14/2015 PASS
DetailsMegan Durrell
Approved in E-Plan Review
1st review completed  9/14/2015 DONE
Routing - PLAN CHECK8/13/2015 9/14/2015 FAIL
DetailsTim L. Woodard
Routing Off Site - STRUCTURAL8/13/2015 9/14/2015 FAIL
DetailsTim L. Woodard
Routing - PLUMBING8/31/2015 8/31/2015 PASS
DetailsBill VanDegrift
updated interceptor ok
Routing PW Environmental8/13/2015 8/21/2015 FAIL
DetailsRick Christenson
Wash bay and trough drains need to be connected to an approved 1500 gallon flammable liquids interceptor.
Routing - MECHANICAL8/13/2015 8/21/2015 FAIL
DetailsTroy James
Routing - PLUMBING8/13/2015 8/20/2015 PASS
DetailsDaryl Spivey
provide an approved flammable liquids interceptor per public works pretreament requirements
Routing PW Drainage8/14/2015 8/19/2015 PASS
DetailsBrian Murphy
Routing - FIRE8/13/20158/13/20158/18/2015 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing PW Sewer Design8/13/2015 8/17/2015 FAIL
DetailsKyle S. Rosenmeyer
Show detail for point of connection to public force main. Ball valve and check valve need to be installed on the service branch within close proximitiy to connection to the public force main.

Contact Public Works 48 hours prior to making connection to schedule inspection.
Routing PW Sewer Rating8/13/2015 8/15/2015 PASS
DetailsJennifer Bruner
Routing - PUBLIC WORKS8/13/2015 8/15/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment8/13/2015 8/14/2015 FAIL
DetailsEvan Jenkins
SWPPP Narrative (Document) is blank. Might have been an upload issue. Please re-upload SWPPP document for 2nd review.
Evan Jenkins 794.3958
Routing PW Drainage8/13/2015 8/14/2015 CANC
DetailsBrian Murphy
Routing - PLANNING Land Div8/13/2015 8/14/2015 PASS
DetailsDave Abo
Parcel over 5 acres in size.
Routing - Design Review8/13/2015 8/14/2015 FAIL
DetailsAndrea Tuning
Condition 1g required the applicant to extend the concrete foundation approximately 3’4” in height and add vertical elements located at the corners of the main building adjacent to the office portion of the building. It appears the wainscot is only 3-feet in height and the vertical elements that were required at the corner of the main building adjacent to the office have not been added.
Intake Approval  8/13/2015 PASS
Pending Assignment by TLW8/13/2015 8/13/2015 DONE
DetailsTim L. Woodard
Routing - Addressing8/13/2015 8/13/2015 PASS
DetailsEmily Dixon
Routing PW Street Lights8/13/2015 8/13/2015 PASS
DetailsMike D Hedge
Application received  8/6/2015 DONE
Application submitted via PDS Online on Aug 6 2015 8:54AM