Permit Information
Permit NumberBLD15-02792
StatusFinaled
Name STEED CONSTRUCTION
Site Address 7960 W RIFLEMAN ST Unit: 150
Project NameArtisan Optics Build Suite 150
Customer Number 
ePlanReviewYes
Description
(ARTISAN OPTICS – SUITE #150) Permit is to remodel existing 6,306 sq. ft. tenant space. This permit is approved contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing walls and construction of select interior non-bearing walls to create two new rooms and reduce the existing mechanical room, mechanical duct work, relocate lighting fixtures, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  11/24/2015 DONE
Spoke with Kevin about TVR INC's final value. They put in 2,200 and he only had 500. He said he was going to give them a call and get back to me. BLH
First Notice10/29/201510/29/201511/9/2015 DONE
DetailsMike Jordan
Mailed 11-10-15
BLD-Final10/28/201510/29/201510/29/2015PPASS
DetailsMike Jordan
Kent Phone #: ###-####
DOC - Permit Finaled10/29/201510/29/201510/29/2015PPASS
DetailsMike Jordan
FIRE-Final Inspection10/28/201510/28/201510/28/2015PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection10/20/201510/20/201510/20/2015PFAIL
DetailsTroy Cobbley
Provide ADA hardware for the pocket door, repair the exit signs and provide annual inspection for the fire extinguishers. Also need the project related fire sprinkler permit finaled.
BLD-Ceiling Grid Inspection10/14/201510/15/201510/15/2015PPART
DetailsMike Jordan
Kent Phone #: ###-####. ceiling grid ok, pending fire sprinkler rough in inspection.
BLD-Framing/Rough-in9/30/201510/1/201510/1/2015APASS
DetailsDave Hannah
Rob Phone #: ###-#### ok to cover after other trades ok
Issue PAID IN FULL permit  8/25/2015 DONE
Inspection Record Card- Bld  8/25/2015 DONE
Plan assigned to (JG)8/7/20158/7/20158/12/2015 PASS
DetailsJavier Guzman
1st review completed, 8/13 Artisan Optics Build Room
Routing - PLAN CHECK8/7/2015 8/12/2015 FAIL
DetailsJavier Guzman
ePlan
Plan Reviewer's activity  8/12/2015 DONE
DetailsJavier Guzman
Spoke with Wesley Steele and requested clarification on the removal of the CMU wall if it was bearing and he replied it was for sound, a generator that was in the room.
Routing - PLAN CHECK8/12/2015 8/12/2015 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  8/12/2015 DONE
Permit Ready to Issue  8/12/2015 DONE
**ALL REQUIREMENTS MET**need GC & rev cert of val
1st review completed  8/12/2015 DONE
DetailsJavier Guzman
Routing - PUBLIC WORKS8/7/2015 8/10/2015 PASS
DetailsBeverly Mountain
Application received  8/7/2015 DONE
Application submitted via PDS Online on Aug 7 2015 11:17AM
Intake Approval  8/7/2015 PASS
DetailsAdele J Schaffeld-Griffin
Routing - Addressing8/7/2015 8/7/2015 PASS
DetailsEmily Dixon
Suite 150 added.