Information based on query as of Sunday, June 23, 2024.
Permit Information
Permit NumberBLD15-02837
StatusFinaled
Name SILVER LINING LLC
Site Address 10173 W OVERLAND RD
Project NameHoneymoon Cove West
Customer Number 
ePlanReviewYes
Description
(SHELL & CORE – Honeymoon Cove - West Building) PLAN MODIFICATION- REMOVE RATED CEILING AND WALL FINISH FROM THIE PORTION OF THE PROJECT. RATED CEILING AND WALL FINISH SHALL BE INSTALLED UNDER THE TENENT IMPROVEMENT PERMIT. This permit is to construct a new 3,826 square foot office building and related site improvements. The building is not fire sprinklered and utilizes ANSI 90.1 (2010) Standard to show compliance. Scope of work includes: construction of a poured concrete foundation, construction of a wood framed exterior envelope, installation of new windows and accessible doors, site work, and interior finishes. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  3/15/2017 DONE
First Notice2/17/20172/17/20173/9/2017 DONE
DetailsJim Storey
BLD-Final2/16/20172/17/20172/17/2017APASS
DetailsJim Storey
Richard Phone #: ###-####per planreview notes
DOC - Permit Finaled2/17/20172/17/20172/17/2017PPASS
DetailsJim Storey
(F) Reprint permit  1/31/2017 DONE
CHANGE STATUS TO (ISS)  1/31/2017 DONE
Plan Mod
OVERRIDE  1/30/2017  
Plan assigned to (AJS)1/20/20171/20/20171/30/2017 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK1/30/2017 1/30/2017 PASS
DetailsAdele J Schaffeld-Griffin
Plan mod to remove rated finish material for ceiling and walls, to be installed under TI permit
PLANS/APPL TAKEN TO FRONT DESK  1/30/2017 DONE
Permit Ready to Issue  1/30/2017 DONE
plan mod ONLY - DO NOT RE-ISSUE
Plan Modification Accepted  1/20/2017 DONE
DetailsChristina Prado
Received request from architecture firm to modify the exterior wall construction
BLD-Final12/6/201612/7/201612/7/2016AFAIL
DetailsMike Jordan
Richard Phone #: ###-####. Submit plan mod to modify scope of work showing the removal of the 1hr. ceiling assembly from the shell scope of work. THis will have to completed on the tenant improvement work. Aslo the west exit door exterio landing needs to be at the same elevation as the interior slab.
Zoning Approval12/6/201612/6/201612/6/2016 DONE
DetailsAndrea Tuning
FIRE-Final Inspection11/23/201611/23/201611/23/2016PPASS
DetailsTroy Cobbley
Life safety passed. Remove the thumbturn deadbolt as discussed prior to a building inspection
BLD-Framing/Rough-in11/16/201611/17/201611/17/2016APASS
DetailsDave Hannah
Richard Phone #: ###-####
BLD-Framing/Rough-in11/15/201611/16/201611/16/2016APART
DetailsMike Jordan
Richard Phone #: ###-####. Repairs to 1hr. soffit ok. ok to cover soffit. Architect to provide percent of unprotected openings on 1hr. wall. (windows).
BLD-Conference10/25/201610/25/201610/25/2016PDONE
DetailsMike Jordan
Richard Phone #: ###-####
BLD-Final9/23/20169/23/20169/23/2016PNR
DetailsJim Storey
Richard Phone #: ###-####
BLD-Framing/Rough-in9/23/20169/23/20169/23/2016PPART
DetailsJim Storey
Richard Phone #: ###-#### c/n on site
BLD-Wall Bracing4/6/20164/7/20164/7/2016APASS
DetailsMike Jordan
call for access; Richard Phone #: ###-####
BLD-Foundation3/7/20163/8/20163/8/2016PPASS
DetailsMike Jordan
Dane Phone #: ###-####
BLD-Footing3/4/20163/7/20163/7/2016PPASS
DetailsMike Jordan
Dane Phone #: ###-####. Perimeter footings.
Issue PAID IN FULL permit  2/25/2016 DONE
Inspection Record Card- Bld  2/25/2016 DONE
Telephone call  2/24/2016 DONE
Spoke with Glenn and recommended that he send a request to Jason B for an extension since it looks like the review went a bit longer.
OVERRIDE  2/23/2016  
Routing - PLAN CHECK2/4/2016 2/23/2016 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  2/23/2016 DONE
Permit Ready to Issue  2/23/2016 DONE
DetailsChristina Prado
Need RP for issuance
Plan assigned to (TLW)12/22/2015 2/23/2016 PASS
DetailsTim L. Woodard
Plan resubmittals received  2/4/2016  
DetailsTim L. Woodard
Route to Impact Fee Review2/1/20162/4/20162/2/2016 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK2/1/2016 2/1/2016 FAIL
DetailsTim L. Woodard
1st review completed  1/22/2016  
Routing - PLAN CHECK12/22/2015 1/22/2016 FAIL
DetailsTim L. Woodard
Need rated wall assembly. TLW
Routing PW Sewer Design12/22/2015 1/13/2016 PASS
DetailsKyle S. Rosenmeyer
Building pad is served with existing 4" sewer service.
Routing PW Drainage12/22/2015 12/31/2015 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL12/22/2015 12/29/2015 PASS
DetailsTim L. Woodard
Routing PW Solid Waste12/22/2015 12/28/2015 PASS
DetailsMegan Durrell
Approved in eplan. TLW
Routing - Erosion and Sediment12/22/2015 12/23/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

A new office building - shell only totaling 3,826 sq. ft.
Routing - FIRE12/22/201512/22/201512/22/2015 PASS
DetailsKatie Marron
Comments attached to case.
Routing - Design Review12/22/2015 12/22/2015 PASS
DetailsAndrea Tuning
Routing PW Street Lights12/22/2015 12/22/2015 PASS
DetailsMike D Hedge
No new street lighting required.
Routing - PLANNING Land Div12/22/2015 12/22/2015 PASS
DetailsDave Abo
Lot 1, Block 1 of Honeymoon Cove Subdivision
Routing - PLUMBING12/22/2015 12/22/2015 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing12/22/2015 12/22/2015 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS12/22/2015 12/22/2015 PASS
DetailsRachael Beierle
Intake Approval  12/22/2015 PASS
Pending Assignment by TLW12/22/2015 12/22/2015 DONE
DetailsTim L. Woodard
Application received  8/11/2015 DONE
Application submitted via PDS Online on Aug 11 2015 11:17AM
Intake Approval  8/11/2015 FAIL
Glenn,

Please provide structural calculations stamped and signed by the engineer.

Best regards,

Tim Woodard
twoodard@cityofboise.org