First Notice | | 3/20/2017 | 4/11/2017 | | DONE |
|
|
|
Mailed 4-12-17
|
Print Occupancy Form | | | 3/10/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/10/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/10/2017 | | DONE |
|
|
|
|
BLD-Final | 3/3/2017 | 3/6/2017 | 3/6/2017 | P | PASS |
Jim Sly
|
|
|
Adin Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 3/1/2017 | 3/2/2017 | 3/2/2017 | A | NR |
Jim Sly
|
|
|
Adin Phone #: ###-####
|
FIRE-Final Inspection | 2/28/2017 | 3/1/2017 | 3/1/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Adin was going to conference with the building inspector for requirements o the one hour riser room. I noted holes in the wall and the interior doors bottom sweep catching on the carpet.
|
FIRE-Final Inspection | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | FAIL |
Troy Cobbley
|
|
|
Provide panic hardware on the two west side doors, mount occupant load signs, provide Riser Room signage on exterior door, provide one hour riser room, provide small documents, provide 20' clearance on the south gate to the west side parking area that accesses the west side of the building.
|
FIRE-Conference | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | DONE |
Katie Marron
|
|
|
Discussed existing gate width of 18' with Ron Johnson. He is ok with it as is since no work being completed on gate or grading and gate is not required for access to riser room. Email attached to case.
|
CHANGE STATUS TO (ISS) | | | 2/22/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/22/2017 | | DONE |
|
|
|
|
Zoning Approval | 2/7/2017 | 2/7/2017 | 2/7/2017 | | DONE |
Leon Letson
|
|
|
|
OVERRIDE | | | 2/1/2017 | | |
|
|
|
|
Plan assigned to (CJW) | 2/1/2017 | 2/1/2017 | 2/1/2017 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 2/1/2017 | | 2/1/2017 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2017 | | DONE |
Christina Prado
|
|
|
All requirements met for PLAN MOD
DO NOT RE-ISSUE, Fees must be paid in full prior to changing status to ISS
|
Plan Modification Accepted | | | 2/1/2017 | | DONE |
Christina Prado
|
|
|
Plan mod to delay installation on MEn's room lav & urinal
|
BLD-Conference | 1/13/2017 | 1/17/2017 | 1/17/2017 | A | DONE |
Jim Sly
|
|
|
Adim Phone #: ###-####
|
BLD-Final | 12/9/2016 | 12/9/2016 | 12/9/2016 | A | PEND |
Jim Sly
|
|
|
Contractor to call for final insp......
|
BLD-Aging Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 | | CANC |
Jim Sly
|
|
|
|
BLD-Conference | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | DONE |
Jim Sly
|
|
|
Adin Phone #: ###-#### Framing OK at North wall openings.
|
BLD-Framing/Rough-in | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | PART |
Jim Sly
|
|
|
Adin-front canopy Phone #: ###-#### Pull test for Special inspection on epoxy bolting for steel columns was approved . Canopy Framing......OK.
|
FIRE-Conference | 7/27/2016 | 7/28/2016 | 7/28/2016 | P | DONE |
Troy Cobbley
|
|
|
Draft stops for the upright sprinklers installed piping can be covered.
|
CHANGE STATUS TO (ISS) | | | 7/27/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/27/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/11/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 7/8/2016 | 7/8/2016 | 7/11/2016 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 7/8/2016 | | 7/11/2016 | | PASS |
Carl Westfall
|
|
|
Received late on Friday. July 9 was a Saturday and July 10 was a Sunday.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/11/2016 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Plan Modification Accepted | | | 7/8/2016 | | DONE |
Christina Prado
|
|
|
Plan Mod to reflect floor plan updates to create new gathering areas from original storage room proposed
|
Plan Modification Accepted | | | 7/8/2016 | | DONE |
|
|
|
Workflow in ePlanReview received
|
BLD-Conference | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | DONE |
Jim Sly
|
|
|
Adin Phone #: ###-####
|
BLD-Framing/Rough-in | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PASS |
Jim Sly
|
|
|
Adin Phone #: ###-####
|
Meeting | | | 4/27/2016 | | DONE |
Scott Arellano
|
|
|
Meeting with Fire Code official regarding proximity of existing fire hydrant along North Christine road which exceeds 300 lineal feet from the new FDC. Fire Code Official approves existing hydrant as qualifying hydrant for the purpose of the Islamic Center FDC.
|
BLD-Conference | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | DONE |
Jim Sly
|
|
|
Adin Phone #: ###-####
|
BLD-Foundation | 2/16/2016 | 2/17/2016 | 2/17/2016 | A | PART |
Jim Sly
|
|
|
Ardi Phone #: ###-#### Stairs OK.
|
BLD-Other | 1/27/2016 | 1/28/2016 | 1/28/2016 | A | NR |
Jim Sly
|
|
|
Ardi-ramp Phone #: ###-####
|
BLD-Footing | 12/2/2015 | 12/2/2015 | 12/2/2015 | P | NR |
Jim Sly
|
|
|
Ari Phone #: ###-#### Not ready for inspection.....Talked with Ari. Need Special insp on soils, reinforcement, epoxy and test samples. No agency notified yet.
|
Print Occupancy Form | | | 10/5/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/5/2015 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/3/2015 | 9/6/2015 | 9/8/2015 | | PASS |
Cindy M. Gould
|
|
|
|
OVERRIDE | | | 9/4/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 8/12/2015 | 8/12/2015 | 9/4/2015 | | PASS |
Carl Westfall
|
|
|
ISLAMIC CENTER OF BOISE (Sept 1 - 15 days) Level 3 TI - ePlanReview
|
Routing - PLAN CHECK | 9/3/2015 | | 9/4/2015 | | DONE |
Carl Westfall
|
|
|
|
Routing - PLANNING | 9/3/2015 | | 9/4/2015 | | PASS |
Leon Letson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/4/2015 | | DONE |
|
|
|
Need RP, GC and Revised Cert of Value
|
Routing - PLAN CHECK | 8/12/2015 | | 9/3/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Plan resubmittals requested | | | 9/3/2015 | | DONE |
|
|
|
|
1st review completed | | | 9/3/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/3/2015 | | DONE |
|
|
|
|
Routing - PLUMBING | 8/12/2015 | | 8/14/2015 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - FIRE | 8/12/2015 | 8/12/2015 | 8/13/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing PW Sewer Rating | 8/13/2015 | | 8/13/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 8/13/2015 | | 8/13/2015 | | PASS |
Jason C. Taylor
|
|
|
No requirements. JCT
|
Routing PW Street Lights | 8/13/2015 | | 8/13/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lighting required.
|
Routing - PUBLIC WORKS | 8/12/2015 | | 8/13/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 8/12/2015 | | 8/13/2015 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Need to designate valid RP on permit
|
Intake Approval | | | 8/12/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard and plan review fees paid.
|
Pending Assignment by JCB | 8/12/2015 | | 8/12/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - PLANNING | 8/12/2015 | | 8/12/2015 | | FAIL |
Leon Letson
|
|
|
Leon Letson - CUP14-00088
The applicant shall install bike racks with capacity for up to 14 bicycles, with a minimum of 4 to be covered.
|
Routing - Addressing | 8/12/2015 | | 8/12/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 8/11/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 11 2015 11:48AM
|