First Notice | | 7/3/2016 | 7/14/2016 | | DONE |
|
|
|
Mailed 7-15-16
|
BLD-Final | 6/23/2016 | 6/23/2016 | 6/23/2016 | P | PASS |
Mike Jordan
|
|
|
Dutch Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 6/23/2016 | | DONE |
|
|
|
|
BLD-Final | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | NR |
Mike Jordan
|
|
|
Dutch Phone #: ###-####
|
FIRE-Final Inspection | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
Temporary Occupancy | 5/31/2016 | 8/29/2016 | 5/31/2016 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd 60 day exension on temp c of o
|
BLD-Final | 5/27/2016 | 5/27/2016 | 5/27/2016 | P | PART |
Jim Sly
|
|
|
South side tenant OK for Temp. Occ.
|
Telephone call | | | 5/27/2016 | | DONE |
|
|
|
called Dutch to let know temp expires on 6-1-16-left message
|
FIRE-Final Inspection | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PART |
Jim Page
|
|
|
Partial final life fire safety inspection complete, fire sprinkler inspection complete for south side tenant, fire alarm inspection complete for entire builiding, fire extinguishers are in place with current inspection tags in south side tenant space. Final life fire safety inspection for south side tenant space passed/complete. Fire sprinkler permit still in issued status due to completion of work needed in the north tenant space, life fire safety still needs to be completed for north tenant space.
|
BLD-Ceiling Grid Inspection | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 4/20/2016 | 4/20/2016 | 4/20/2016 | A | PASS |
Mike Jordan
|
|
|
This for the Federal side remodel, please call Dutch with any questions. Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
FIRE-Conference | 4/12/2016 | 4/12/2016 | 4/12/2016 | A | DONE |
Troy Cobbley
|
|
|
Please call Barry 1 hr before arrival Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
OVERRIDE | | | 3/28/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 3/18/2016 | 3/18/2016 | 3/28/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 3/28/2016 | | 3/28/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2016 | | |
|
|
|
Plan Mod DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 3/28/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/28/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/18/2016 | | DONE |
|
|
|
Plan Mod requested by Architect 3/18/16
|
BLD-Framing/Rough-in | 3/15/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Mike Jordan
|
|
|
Please call Dutch 1 hr before arrival Thank you, Phone #: ###-#### Inspection requested via web by Dennis Harmon. North half interior steel stud framed walls ok.
|
BLD-Final | 3/3/2016 | 3/3/2016 | 3/3/2016 | A | PART |
Mike Jordan
|
|
|
Please call Dutch 1 hour before arrival, preferably Late AM, Thank You. Phone #: ###-#### Inspection requested via web by Dennis Harmon. Ok for temp occ, south side only. NOted another remodel with aseperate permit for south side in progress.
|
FIRE-Final Inspection | 3/3/2016 | 3/3/2016 | 3/3/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given for the South tenant only with Scott and Jason's approval. Fire alarm and fire sprinkler is complete in this area. The north area has not been inspected.
|
Temporary Occupancy | 5/4/2016 | 6/1/2016 | 3/3/2016 | | DONE |
Christina Prado
|
|
|
Temporary Occupancy back dated to original approval date of 3/3/2016 to keep permit on track for renewals
|
FIRE-Conference | 2/24/2016 | 2/24/2016 | 2/24/2016 | A | DONE |
Troy Cobbley
|
|
|
Dutch and I went over life safety requirements for the north half of the building
|
Zoning Approval | 2/11/2016 | 2/12/2016 | 2/12/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Ceiling Grid Inspection | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Mike Jordan
|
|
|
Please contact Dutch onsite upon arrival. Thank You Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
BLD-Conference | 12/18/2015 | 12/21/2015 | 12/21/2015 | A | DONE |
Mike Jordan
|
|
|
Please call Dutch 1/2 hr prior to arrival Thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon,, frame walk through
|
BLD-Framing/Rough-in | 12/21/2015 | 12/21/2015 | 12/21/2015 | A | PASS |
Mike Jordan
|
|
|
Please call Dutch 1/2 hr prior to arrival Thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon,, frame walk through. Interior steel stud framed walls for south half only ok.
|
BLD-Conference | 12/18/2015 | 12/18/2015 | 12/18/2015 | A | CANC |
Tony Young
|
|
|
Please call Dutch 1/2 hr prior to arrival Thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon,, out of time
|
FIRE-Conference | 12/15/2015 | 12/16/2015 | 12/16/2015 | P | DONE |
Troy Cobbley
|
|
|
Dutch, myself and the electrician went over fire alarm and fire life safety requirements. It appears additional smoke alarms will be required and additional exit signs/emergency lighting will be required as well.
|
FIRE-Conference | 12/15/2015 | 12/16/2015 | 12/15/2015 | A | CANC |
Jim Page
|
|
|
Please call Dutch @ ###-#### 1/2 hour prior to arrival thank you Phone #: ###-#### >> Inspection requested via web by Dennis Harmon Inspection cancelled from web by: Dennis Harmon
|
Issue PAID IN FULL permit | | | 10/23/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/23/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/23/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 10/22/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 8/13/2015 | 8/13/2015 | 10/22/2015 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - Port of Hope
|
Routing - PLAN CHECK | 10/19/2015 | | 10/22/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/22/2015 | | DONE |
|
|
|
***ALL REQUIRMENTS MET (on-file) 10-22-15 //CEV Needs; RP, GC Form, revised certificate of value
|
Routing - PUBLIC WORKS | 10/21/2015 | | 10/21/2015 | | PASS |
Rachael Beierle
|
|
|
|
Plan resubmittals received | | | 10/19/2015 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/19/2015 | | 10/19/2015 | | PASS |
Evan Jenkins
|
|
|
(PORT OF HOPE) Remodel changing occupancy to a re-entry treatment, resident treatment and outpatient treatment center (halfway house per zoning ordinance) per approved plans. Work to include new non-bearing walls, new ceilings, doors, windows, new accessible restrooms and shower rooms, fire sprinkler work, plumbing, mechanical and electrical. Fire sprinkler system and alarm system remodel.
|
1st review completed | | | 9/18/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/13/2015 | | 9/18/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 8/13/2015 | 8/13/2015 | 8/18/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - PLANNING | 8/13/2015 | | 8/17/2015 | | PASS |
Cody Riddle
|
|
|
Cody Riddle - CUP14-00023
|
Routing PW Sewer Rating | 8/15/2015 | | 8/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Reviewer's activity | | | 8/17/2015 | | DONE |
Jason Blais
|
|
|
No ACHD impact fees due and no inspection required per letter attached to this case.
|
Routing - PUBLIC WORKS | 8/13/2015 | | 8/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLUMBING | 8/13/2015 | | 8/14/2015 | | PASS |
Bill VanDegrift
|
|
|
MEP plans coming (are late). Likely need to not pass the plans on first review.
Per plan and ISPC.
|
Routing - Design Review | 8/13/2015 | | 8/14/2015 | | PASS |
Sarah Schafer
|
|
|
OK per Sarah Schafer
|
Routing - Erosion and Sediment | 8/13/2015 | | 8/14/2015 | | FAIL |
Evan Jenkins
|
|
|
Due to how Environmentally Sensative this projec (directly next to a Waters of the US) and size of project far exceeding a Waiver requirement a full ESC Narrative is Required per BCC 8-17.
Evan Jenkins 794.3958
|
Routing - Addressing | 8/13/2015 | | 8/14/2015 | | PASS |
Emily Dixon
|
|
|
|
Plan Reviewer's activity | | | 8/13/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD to determine if any additional impact fees are due. Permit Counter neede written verification prior to the building permit being issued.
|
Intake Approval | | | 8/13/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Pending Assignment by JCB | 8/13/2015 | | 8/13/2015 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 8/11/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 11 2015 2:46PM
|