BLD-Final | 6/23/2016 | 6/24/2016 | 6/24/2016 | A | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-####
|
DOC - Permit Finaled | 6/24/2016 | 6/24/2016 | 6/24/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Wall Bracing | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | CANC |
Phil Shearer
|
|
|
Josh Phone #: ###-####
|
BLD-Other | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | PASS |
Phil Shearer
|
|
|
Josh Phone #: ###-####. Sofit sheet rock
|
BLD-Framing/Rough-in | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Phil Shearer
|
|
|
Josh Phone #: ###-####
|
BLD-Energy code compliance | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Phil Shearer
|
|
|
Josh Phone #: ###-####
|
BLD-Energy code compliance | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PART |
Phil Shearer
|
|
|
Josh Phone #: ###-####. air seal only
|
BLD-Framing/Rough-in | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PART |
Phil Shearer
|
|
|
Josh Phone #: ###-####. Truss bracing, Engineered fix for cut truss, Hold downs nuts on front wall, fire stop mech chase, Strap top plate at beam over stairs, point load support transfer to foundation at stairs.
|
BLD-Wall Bracing | 3/8/2016 | 3/9/2016 | 3/9/2016 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 12/14/2015 | 12/15/2015 | 12/15/2015 | P | PASS |
Jim Sly
|
|
|
Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/2/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/8/2015 | | |
|
|
|
|
Plan assigned to (DAF) | 8/26/2015 | 8/26/2015 | 9/8/2015 | | PASS |
David Ferguson
|
|
|
8/31 Failed due to insufficiently sized floor system.
|
Inspection Record Card- Bld | | | 9/8/2015 | | DONE |
|
|
|
|
Telephone call | | | 9/8/2015 | | DONE |
|
|
|
called Aaron- told him fees due and permit is ready for pick up
|
Routing - PLAN CHECK | 9/8/2015 | | 9/8/2015 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 9/8/2015 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/8/2015 | | DONE |
|
|
|
ALL REQUIRMENTS MET
|
Plan resubmittals received | | | 9/4/2015 | | DONE |
|
|
|
received two copies of sheet S1.1- put on DAF desk
|
1st review completed | | | 8/31/2015 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 8/25/2015 | | 8/31/2015 | | FAIL |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 8/13/2015 | | 8/26/2015 | | DEFR |
Tisha Gallop
|
|
|
8/27 (D)
|
Routing - MECHANICAL | | | 8/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/17/2015 | | 8/19/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 8/14/2015 | | 8/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 8/13/2015 | | 8/14/2015 | | PASS |
Emily Dixon
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/13/2015 | | DONE |
|
|
|
|
Intake Approval | | | 8/13/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/13/2015 | | DONE |
|
|
|
|
Application received | | 8/13/2015 | | | |
|
|
|
|