BLD-Final | 1/25/2016 | 1/25/2016 | 1/25/2016 | P | PASS |
Mike Jordan
|
|
|
Call for access // Joe Phone #: ###-####
|
DOC - Permit Finaled | 1/25/2016 | 1/25/2016 | 1/25/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 1/14/2016 | 1/14/2016 | 1/14/2016 | P | FAIL |
Dave Hannah
|
|
|
call ahead for access; Joe Phone #: ###-#### needs energy certs
|
BLD-Energy code compliance | 11/12/2015 | 11/13/2015 | 11/13/2015 | A | PASS |
Dave Hannah
|
|
|
Joe Phone #: ###-####
|
BLD-Framing/Rough-in | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | FAIL |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Fire block above fireplace, strap top plates at dryer duct, provide truss engineering. Ok to insulate.
|
BLD-Wall Bracing | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | PASS |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
BLD-Wall Bracing | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | FAIL |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Provide the double portal frame at back door as noted on plans.
|
BLD-Footing | 10/2/2015 | 10/2/2015 | 10/3/2015 | P | PASS |
Dave Hannah
|
|
|
Matt Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 10/2/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/1/2015 | | |
|
|
|
|
Plan assigned to (DAF) | 9/28/2015 | 9/28/2015 | 10/1/2015 | | PASS |
David Ferguson
|
|
|
plan modification; added 102 sq. ft. to house
|
Case Summary (BLD) | | | 10/1/2015 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/1/2015 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Routing - PLAN CHECK | 9/30/2015 | | 10/1/2015 | | PASS |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2015 | | DONE |
|
|
|
|
Telephone call | | | 10/1/2015 | | DONE |
|
|
|
Sent an email to Joe, voice mail box was full, informing him that the permit is ready to be picked up and the fee amount due
|
Routing - MECHANICAL | 9/29/2015 | | 9/30/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/24/2015 | | 9/29/2015 | | PASS |
Susan Riggs
|
|
|
|
Plan assigned to (LEG) Tisha | 9/24/2015 | | 9/28/2015 | | DEFR |
Tisha Gallop
|
|
|
routed to planning, deferred to DAF
|
Plan Modification Accepted | | | 9/24/2015 | | DONE |
Christina Prado
|
|
|
Received two sets of new plan sheets marked A0.0, A1.0, A2.0, A3.0E1.0, S1.0 & S2.0 as well as two sets reviced manual j & truss details for plan mod to expand sq footage by ~102 sq. ft. and reduce frond covered porch area. Plans stamped and taken to SAR, LEG & 435 for additional review.
|
BLD-Footing | 9/8/2015 | 9/9/2015 | 9/8/2015 | A | CANC |
Dave Hannah
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/1/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 8/31/2015 | | |
|
|
|
|
Plan assigned to (DAF) | 8/26/2015 | 8/26/2015 | 8/31/2015 | | DONE |
David Ferguson
|
|
|
due 8/31
|
1st review completed | | | 8/31/2015 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/31/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/31/2015 | | DONE |
|
|
|
requirements met
|
Telephone call | | | 8/31/2015 | | DONE |
Christina Prado
|
|
|
called Joseph to advise permit is ready and gave fees due
|
Routing - PLAN CHECK | 8/25/2015 | | 8/31/2015 | | PASS |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 8/17/2015 | | 8/26/2015 | | DEFR |
Tisha Gallop
|
|
|
8/31
|
Routing - MECHANICAL | 8/18/2015 | | 8/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/17/2015 | | 8/18/2015 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 8/17/2015 | | 8/17/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/17/2015 | | 8/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/17/2015 | | DONE |
|
|
|
|
Intake Approval | | | 8/17/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/17/2015 | | DONE |
|
|
|
|
Application received | | 8/14/2015 | | | |
|
|
|
|