PubWorks Occupancy Approval | 3/23/2016 | 3/23/2016 | 3/23/2016 | | DONE |
Jason C. Taylor
|
|
|
Roof Drains tested, hydroseeding installed. Project completed. JCT
|
BLD-Final | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | PASS |
Jim Sly
|
|
|
LARRY// PLEASE CALL FOR ACCESS Phone #: ###-#### Landscape bonded.
|
DOC - Permit Finaled | 2/8/2016 | 2/8/2016 | 2/8/2016 | P | PASS |
Jim Sly
|
|
|
|
PubWorks Occupancy Approval | 2/4/2016 | 2/4/2016 | 2/4/2016 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Other | 11/9/2015 | 11/10/2015 | 11/10/2015 | A | PART |
Tony Young
|
|
|
soffits // Larry Phone #: ###-####
|
BLD-Energy code compliance | 11/9/2015 | 11/9/2015 | 11/9/2015 | P | PASS |
Tony Young
|
|
|
Insulation // Larry Phone #: ###-####
|
BLD-Other | 11/4/2015 | 11/5/2015 | 11/5/2015 | A | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, soffit boxes ok
|
BLD-Framing/Rough-in | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
Plan Modification Accepted | | | 11/2/2015 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 11/2/2015 | | 11/2/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/21/2015 | 10/21/2015 | 10/21/2015 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper,, exterior shear/brace panels ok
|
BLD-Foundation | 9/17/2015 | 9/18/2015 | 9/18/2015 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, ok
|
BLD-Foundation | 9/17/2015 | 9/17/2015 | 9/17/2015 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, work in progress
|
BLD-Foundation | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | CANC |
Tony Young
|
|
|
Chris Phone #: ###-####,, too much rain
|
BLD-Footing | 9/15/2015 | 9/16/2015 | 9/16/2015 | A | PASS |
Phil Shearer
|
|
|
Pouring at 12 - Shawn Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/14/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/14/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/11/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 8/19/2015 | | 9/11/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/11/2015 | | 9/11/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
1st review completed | | | 9/11/2015 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2015 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/11/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (BJM) | 8/31/2015 | 8/31/2015 | 9/9/2015 | | DONE |
Brian McGowan
|
|
|
due 9/9 L2
|
Plan assigned to (LEG) Tisha | 8/19/2015 | | 8/31/2015 | | DEFR |
Tisha Gallop
|
|
|
9/9 L2
|
Routing - MECHANICAL | 8/19/2015 | | 8/25/2015 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 8/19/2015 | | 8/24/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLANNING | 8/19/2015 | | 8/20/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - FIRE | 8/19/2015 | 8/19/2015 | 8/19/2015 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - Addressing | 8/19/2015 | | 8/19/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/19/2015 | | 8/19/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 8/19/2015 | | 8/19/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
WUI Zone A; Permit for the construction of a new 2,799 sq. ft., two story (main level 1,586 sq. ft., upper level 1,247 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 180 sq. ft. of covered patio/porch and a 792 sq. ft. attached garage
|
Intake Approval | | | 8/19/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/19/2015 | | DONE |
|
|
|
|
Intake Approval | | | 8/18/2015 | | FAIL |
|
|
|
Foundation plan needs to be stamped and signed by licensed engineer. Also, need to upload Erosion plan and Erosion plan needs to be signed by Plan Designer.
|
Application received | | | 8/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2015 8:25AM
|