BLD-Aging Inspection | 3/18/2016 | 3/18/2016 | 3/18/2016 | | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 11/4/2015 | 11/5/2015 | 11/5/2015 | A | PASS |
Jim Storey
|
|
|
Toby Phone #: ###-#### point load ft ok
|
BLD-Framing/Rough-in | 10/6/2015 | 10/7/2015 | 10/7/2015 | P | PART |
Jim Storey
|
|
|
Toby Phone #: ###-#### ok to verify ft latter
|
BLD-Framing/Rough-in | 10/5/2015 | 10/6/2015 | 10/6/2015 | A | CANC |
Jim Storey
|
|
|
Toby Phone #: ###-####
|
Routing Walk-In (BLD) | 9/28/2015 | 9/28/2015 | 9/28/2015 | P | PASS |
Tisha Gallop
|
|
|
plan modification
|
BLD-Framing/Rough-in | 9/14/2015 | 9/15/2015 | 9/15/2015 | P | FAIL |
Jim Storey
|
|
|
call for access; Toby Phone #: ###-####need beam calc. load path and size// floor joist not 2x12// need mech permit.
|
Routing Walk-In (Zoning) | 8/19/2015 | 8/19/2015 | 8/19/2015 | A | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 8/19/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 8/19/2015 | 8/19/2015 | 8/19/2015 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 8/19/2015 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 8/19/2015 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2015 | | DONE |
David Ferguson
|
|
|
|
Override - Parcel Holds | | | 8/19/2015 | | |
|
|
|
|
Override - Parcel Holds | | | 8/19/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/19/2015 | | DONE |
|
|
|
|
1st review completed | | | 8/19/2015 | | DONE |
David Ferguson
|
|
|
|
Permit Ready to Issue | | | 8/19/2015 | | DONE |
Candy A. Nichols
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/19/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | 8/19/2015 | | | |
|
|
|
|