Print Statement | | | 9/23/2016 | | DONE |
|
|
|
|
Telephone call | | | 9/23/2016 | | DONE |
|
|
|
Spoke with Jay to go over the values sent back, some were much lower and others much higher. He stated that he would get with the tenant and contractor to get the correct values and will resend the final values in.
|
First Notice | | 8/19/2016 | 9/13/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Permanent Occupancy | | | 8/9/2016 | | DONE |
|
|
|
|
BLD-Final | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | PASS |
Jim Storey
|
|
|
Please call Chris 30 min. prior to going out Phone #: ###-####
|
Zoning Approval | 8/5/2016 | 8/5/2016 | 8/5/2016 | | DONE |
Sarah Schafer
|
|
|
as per attached approval by Sarah Schafer; okay to sign-off and release bond
|
Zoning Approval | 8/3/2016 | 8/3/2016 | 8/3/2016 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH15-00362. Sidewalks, parking and right-of-way improvements were not completed.
|
PubWorks Occupancy Approval | 8/2/2016 | 8/2/2016 | 8/2/2016 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 6/14/2016 | 6/14/2016 | 6/14/2016 | | PASS |
Jim Storey
|
|
|
|
Temporary Occupancy | 5/11/2016 | 8/9/2016 | 5/11/2016 | | DONE |
Candy A. Nichols
|
|
|
Jason B ok'd 90 extension on temp c of o good thru Aug 9th
|
BLD-Aging Inspection | 4/11/2016 | 4/11/2016 | 4/11/2016 | | NR |
Jim Storey
|
|
|
work to begin in may
|
Temporary Occupancy | 2/10/2016 | 5/10/2016 | 2/10/2016 | | DONE |
Candy A. Nichols
|
|
|
|
PubWorks Temp Occupancy Appr | 2/10/2016 | 2/10/2016 | 2/10/2016 | | DONE |
Brian Murphy
|
|
|
temp OK
|
BLD-Final | 2/10/2016 | 2/10/2016 | 2/10/2016 | P | PART |
Dave Hannah
|
|
|
Please call half an hour prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby ok for temp occ needs to complete ext work
as per David H. inspection was called in on the wrong permit-see permit BLD15-03507
|
BLD-Ceiling Grid Inspection | 2/10/2016 | 1/28/2016 | 2/10/2016 | P | PASS |
Jim Sly
|
|
|
Please call a half hour prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby
|
Plan Reviewer's activity | | | 2/10/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
All inspections completed under BLD15-03507
|
FIRE-Final Inspection | 2/10/2016 | 2/9/2016 | 2/9/2016 | P | DONE |
Jim Page
|
|
|
as per Jim Page-final was called in on the demo not this permit-see BLD15-03507 for sign off
|
Zoning Approval Temp | 2/5/2016 | 2/5/2016 | 2/5/2016 | | PASS |
Josh Wilson
|
|
|
180-day temp occ. Bond is in place for landscaping and concrete flat work.
|
BLD-Conference | 2/10/2016 | 1/29/2016 | 1/29/2016 | P | DONE |
Jim Storey
|
|
|
see notes in BLD15-03507
|
BLD-Conference | 2/10/2016 | 1/28/2016 | 1/28/2016 | P | CANC |
Jim Storey
|
|
|
see notes in BLD15-03507
|
BLD-Conference | 2/10/2016 | 1/28/2016 | 1/28/2016 | P | CANC |
Jim Storey
|
|
|
see notes in BLD15-03507
|
BLD-Conference | 2/10/2016 | 1/28/2016 | 1/28/2016 | P | CANC |
Jim Sly
|
|
|
I just have a few A.D.A questions. Please call a half hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Chris Eby Inspection cancelled from web by: Chris Eby
|
BLD-Wall cover | 2/10/2016 | 12/10/2015 | 12/10/2015 | P | PASS |
Mike Jordan
|
|
|
We need a framing inspection for approval to cover walls. Please give me a call half an hour before the inspection. Phone #: ###-#### Inspection requested via web by Chris Eby
|
BLD-Framing/Rough-in | 2/10/2016 | 12/10/2015 | 12/10/2015 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Eby
|
BLD-Conference | 2/10/2016 | 12/1/2015 | 12/1/2015 | P | PASS |
Jim Storey
|
|
|
I want to go over ADA compliance for the bathrooms. Please give me a call 30 minutes prior to the conference. My name is Chris Eby. Phone #: ###-#### Inspection requested via web by Chris Eby
|
OVERRIDE | | | 11/10/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 9/25/2015 | 9/25/2015 | 11/10/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - The Lift
|
Issue PAID IN FULL permit | | | 11/10/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/10/2015 | | DONE |
|
|
|
|
Routing PW Drainage | 11/10/2015 | | 11/10/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 11/10/2015 | | 11/10/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/10/2015 | | DONE |
|
|
|
NEED RP, GC form, and certificate of value
|
Routing - MECHANICAL | 11/6/2015 | | 11/6/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 11/6/2015 | | 11/6/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
approved pending drainage sign off
|
Routing PW Drainage | 11/6/2015 | | 11/6/2015 | | FAIL |
Brian Murphy
|
|
|
|
Routing PW Flood Plain | 10/23/2015 | | 10/30/2015 | | PASS |
Jim Wyllie
|
|
|
Project improvements do not meet "substantial improvement" definition. Floodplain building conditions do not apply. Jim Wyllie / ###-####
|
Routing - PLAN CHECK | 10/23/2015 | | 10/29/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Drainage | 10/23/2015 | | 10/29/2015 | | FAIL |
Brian Murphy
|
|
|
NEEDS WORKING SYSTEM O/ S TRAP
|
Routing PW Environmental | 9/25/2015 | | 10/29/2015 | | PASS |
Rick Christenson
|
|
|
Needs 1500 Gallon Exterior Grease Interceptor. MopSink connected to interceptor.
|
Routing - MECHANICAL | 10/29/2015 | | 10/29/2015 | | FAIL |
Troy James
|
|
|
uploaded new plans and completed review
|
Routing - PLANNING | 10/23/2015 | | 10/27/2015 | | PASS |
Susan Riggs
|
|
|
This does not approve andy construction, fencing, tables, or landscaping in the right-of-way with our a license agreement from ACHD.
|
Routing - MECHANICAL | 10/23/2015 | | 10/26/2015 | | FAIL |
Troy James
|
|
|
No response to mechanical comments.
|
Routing - PUBLIC WORKS | 10/23/2015 | | 10/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
1st review completed | | | 10/21/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 9/25/2015 | | 10/21/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Drainage | 9/25/2015 | | 10/7/2015 | | FAIL |
Brian Murphy
|
|
|
NEED SEEPAGE BED INFO
|
Routing - PLANNING | 9/25/2015 | | 9/30/2015 | | FAIL |
Cody Riddle
|
|
|
Susan Riggs - CAA-00167
Fail: A lic. agreement from ACHD is required for the patio in the ROW, prior to issuance of permit. Emailed applicant. CER
|
Routing Off Site - C.D.H | 9/25/2015 | | 9/29/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
signe off by Lori Badigian at CDH in e plan
|
Routing PW Sewer Rating | 9/25/2015 | | 9/29/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - FIRE | 9/25/2015 | 9/25/2015 | 9/28/2015 | | PASS |
Scott Arellano
|
|
|
Report attached to case.
|
Routing PW Street Lights | 9/25/2015 | | 9/28/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lights required.
|
Routing - MECHANICAL | 9/25/2015 | | 9/28/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 9/25/2015 | | 9/28/2015 | | PASS |
Bill VanDegrift
|
|
|
ASSE 1070 mixing valve at hand sinks
|
Routing - Design Review | 9/25/2015 | | 9/25/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00362
|
Routing - Addressing | 9/25/2015 | | 9/25/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/25/2015 | | 9/25/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Pending Assignment by JCB | 9/25/2015 | | 9/25/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Erosion and Sediment | 9/25/2015 | | 9/25/2015 | | PASS |
Evan Jenkins
|
|
|
(THE LIFT) Remodel to combine 2 tenant office spaces into one new restaurant tenant space per approved plans. Work to include interior demolition, new exterior work, new exterior patio, new interior walls, interior finish, new restrooms, new commercial kitchen with Type I hood, plumbing work, mechanical work, and electrical work.
|
Intake Approval | | | 9/23/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Intake Approval | | | 9/21/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
9/21/15 Please see mark ups on check list. Only 1 of the items missing was addressed.
|
Intake Approval | | | 9/21/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please upload the completed check list. A pre screen will be done once received.
Please see change mark on documents.
9/8/15
Please re upload your documents (checklist) to read left to right. Please name the files the same in order for them to version. Please see electronic submittal standards for requirements. Once the uploading is correct I will begin the pre screen.
9/10/15- see mark ups on check list sheets for additional items needed.
9/21/15 Please see mark ups on check list. Only 1 of the items missing was addressed.
9/21/15 Please see mark ups on check list. Only 1 additional item missing was addressed. Please see all items that are marked as missing or needing addressed.
|
Intake Approval | | | 9/10/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
9/10/15- see mark ups on check list sheets for additional items needed.
|
Intake Approval | | | 9/8/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please upload the completed check list. A pre screen will be done once received.
Please see change mark on documents.
|
Intake Approval | | | 9/8/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
9/8/15
Please re upload your documents (checklist) to read left to right. Please name the files the same in order for them to version. Please see electronic submittal standards for requirements. Once the uploading is correct I will begin the pre screen.
|
Application received | | | 8/24/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 24 2015 8:27PM
|
BLD-Conference | 2/10/2016 | 2/10/2016 | | P | |
|
|
|
|
Routing PW Flood Plain | 9/25/2015 | | | | FAIL |
Jim Wyllie
|
|
|
NEED SEEPAGE BED INFO
|