BLD - Request for Extension | 2/25/2019 | 2/25/2019 | 2/25/2019 | | DONE |
Bob Archibald
|
|
|
180 day extension granted. Applicant cited medical reasons for delay.
|
BLD-Conference | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | PASS |
Jim Sly
|
|
|
OK for Extension.....
|
BLD-Aging Inspection | 9/22/2017 | 9/22/2017 | 9/28/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 9/21/2017 | 9/21/2017 | 9/28/2017 | | DONE |
Jim Sly
|
|
|
WIP
|
BLD - Request for Extension | 5/9/2017 | 5/10/2017 | 5/10/2017 | P | PASS |
Jim Sly
|
|
|
Timothy Phone #: ###-####
|
BLD-Conference | 5/9/2017 | 5/10/2017 | 5/10/2017 | P | PASS |
Jim Sly
|
|
|
Timothy Phone #: ###-#### WIP
|
BLD-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | DONE |
Jim Sly
|
|
|
Work in progress.
|
BLD-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 | A | DONE |
Jim Sly
|
|
|
WIP.
|
BLD-Final | 3/29/2016 | 5/13/2016 | 5/9/2016 | P | DONE |
Jim Sly
|
|
|
Not close to being done
|
Plan Reviewer's activity | | | 5/9/2016 | | DONE |
Jason Blais
|
|
|
180 day extension granted.
|
BLD-Aging Inspection | 3/25/2016 | 3/25/2016 | 3/29/2016 | | CANC |
Jim Sly
|
|
|
|
BLD-Foundation | 11/10/2015 | 11/12/2015 | 11/12/2015 | A | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-####
|
OVERRIDE | | | 8/27/2015 | | |
|
|
|
|
Routing Walk-In (Zoning) | 8/27/2015 | 8/27/2015 | 8/27/2015 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 8/27/2015 | 8/27/2015 | 8/27/2015 | P | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 8/27/2015 | | 8/27/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
1st review completed | | | 8/27/2015 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 8/27/2015 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 8/27/2015 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/27/2015 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 8/27/2015 | | DONE |
|
|
|
|
Application received | | 8/27/2015 | | | |
|
|
|
|