BLD-Aging Inspection | 3/24/2016 | 3/24/2016 | 3/25/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 3/23/2016 | 3/23/2016 | 3/25/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Wall Bracing | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PASS |
Mike Jordan
|
|
|
Drywall, shear - Brad Phone #: ###-####
|
BLD-Energy code compliance | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Tony Young
|
|
|
Brad Phone #: ###-####
|
BLD-Framing/Rough-in | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Tony Young
|
|
|
Brad Phone #: ###-####
|
BLD-Energy code compliance | 11/3/2015 | 11/3/2015 | 11/3/2015 | P | PART |
Tony Young
|
|
|
Brad Phone #: ###-####
|
BLD-Framing/Rough-in | 11/3/2015 | 11/3/2015 | 11/3/2015 | P | PART |
Tony Young
|
|
|
Brad Phone #: ###-####
|
BLD-Energy code compliance | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | NR |
Tony Young
|
|
|
Brad Phone #: ###-####
|
BLD-Framing/Rough-in | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | NR |
Tony Young
|
|
|
Brad Phone #: ###-####
|
Plan Modification Accepted | | | 11/3/2015 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 11/3/2015 | | 11/3/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
Contractor requesting a lower cfm design for cooling. Air balance report shall show the cfm to be at least 350 per ton.
|
BLD-Framing/Rough-in | 10/29/2015 | 10/29/2015 | 10/29/2015 | P | PASS |
Tony Young
|
|
|
Brad Phone #: ###-####
|
BLD-Framing/Rough-in | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | NR |
Tony Young
|
|
|
Brad Phone #: ###-####,, need mech pass 1st,, no inspection
|
BLD-Wall Bracing | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | PASS |
Tony Young
|
|
|
Bradley Phone #: ###-####
|
BLD-Wall Bracing | 10/15/2015 | 10/16/2015 | 10/16/2015 | A | FAIL |
Dave Hannah
|
|
|
Shear // Joe Phone #: ###-#### c/n on site
|
BLD-Foundation | 9/11/2015 | 9/11/2015 | 9/11/2015 | P | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 9/10/2015 | 9/11/2015 | 9/11/2015 | A | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 9/10/2015 | 9/10/2015 | 9/10/2015 | P | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 9/10/2015 | 9/10/2015 | 9/10/2015 | P | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 9/10/2015 | 9/10/2015 | 9/10/2015 | A | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, work in progress,, most forms in place
|
BLD-Footing | 9/9/2015 | 9/9/2015 | 9/9/2015 | P | NR |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
OVERRIDE | | | 9/4/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/4/2015 | | DONE |
|
|
|
|
Routing - MECHANICAL | 9/4/2015 | | 9/4/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 9/4/2015 | | 9/4/2015 | | PASS |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2015 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 9/4/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/4/2015 | | 9/4/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
Permit Ready to Issue | | | 9/4/2015 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (BJM) | 9/2/2015 | 9/2/2015 | 9/2/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing Walk-In (Zoning) | 8/27/2015 | 8/27/2015 | 8/27/2015 | P | DONE |
Sue Cummings
|
|
|
Front posts need to be at 15" with no more than 24' roof overhang!
|
Routing Walk-In (BLD) | 8/27/2015 | 8/27/2015 | 8/27/2015 | P | FAIL |
Brian McGowan
|
|
|
Did not have a Checklist prior to bringing in plans. Did not have all the needed drawings or details. It is a major remodel/addition and should be taken in instead of a walk in.
|
1st review completed | | | 8/27/2015 | | DONE |
Brian McGowan
|
|
|
|
Application received | | 8/27/2015 | | | |
|
|
|
|