BLD-Final | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | PASS |
Tony Young
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 9/14/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Tony Young
|
|
|
|
Zoning Approval | 9/9/2016 | 9/9/2016 | 9/9/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Energy code compliance | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Framing/Rough-in | 7/21/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Framing/Rough-in | 7/19/2016 | 7/20/2016 | 7/20/2016 | A | PART |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Work in progress on framing corrections. ok to insulate. Will inspect remainder on energy code inspection.
|
BLD-Framing/Rough-in | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | FAIL |
Phil Shearer
|
|
|
Dave Phone #: ###-####
|
Routing - MECHANICAL | 7/13/2016 | | 7/13/2016 | | PASS |
Troy James
|
|
|
Another plan mod submitted for manual j report
|
Plan Modification Accepted | | | 7/1/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 7/1/2016 | | 7/1/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 6/9/2016 | 6/10/2016 | 6/10/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Wall Bracing | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | FAIL |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Needs to install all floor to floor straps.
|
BLD-Conference | 4/27/2016 | 4/27/2016 | 4/28/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 4/25/2016 | 4/26/2016 | 4/26/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####. interior thickend footings.
|
BLD-Foundation | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | PASS |
Mike Jordan
|
|
|
As late as possible /// Manuel Phone #: ###-####
|
BLD-Footing | 4/5/2016 | 4/5/2016 | 4/5/2016 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####. interior footing for garage/dwelling seperation wall.
|
BLD-Foundation | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | PART |
Mike Jordan
|
|
|
Late AM please - Manuel Phone #: ###-####
|
BLD-Footing | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/28/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 2/18/2016 | | DONE |
|
|
|
1st 180 days approve by Jason B. See documents
|
Telephone call | | | 2/17/2016 | | DONE |
|
|
|
Left a message for Chad that this permit is going to expire in ten days.
|
Expiration Notice | 2/10/2016 | 3/3/2016 | 2/10/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 2/4/2016 | | |
|
|
|
|
Routing - MECHANICAL | 2/4/2016 | | 2/4/2016 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/4/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/4/2016 | | DONE |
Christina Prado
|
|
|
Need RP & GC Form for issuance
|
Plan assigned to (LEG) Tisha | 9/21/2015 | | 2/4/2016 | | DONE |
Tisha Gallop
|
|
|
3rd review 1/28 pending mech; 2nd review 12/1; 1st review 10/12; L2 eplan*
|
Routing - MECHANICAL | 2/1/2016 | | 2/2/2016 | | FAIL |
Troy James
|
|
|
emailed corrrections to architect
|
Plan resubmittals received | | | 2/1/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/26/2016 | | 1/28/2016 | | PASS |
Tisha Gallop
|
|
|
pending approval from Mechanical
|
Routing - MECHANICAL | 1/26/2016 | | 1/28/2016 | | FAIL |
Troy James
|
|
|
Previous comment has not been addressed dated 11-25-15.
|
Plan resubmittals received | | | 1/25/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/1/2015 | | 12/1/2015 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
Routing - Design Review | 11/30/2015 | | 11/30/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - MECHANICAL | 11/24/2015 | | 11/24/2015 | | FAIL |
Troy James
|
|
|
eplan
|
Plan resubmittals received | | | 11/20/2015 | | DONE |
|
|
|
|
Telephone call | | | 10/26/2015 | | DONE |
|
|
|
called Dave again, he will come pick up the plans that were submitted over counter (paper). He said the plan moc was already submitted thru e plan review
|
1st review completed | | | 10/12/2015 | | FAIL |
|
|
|
pending approval from Mechanical, Design Review, Plan Check
|
Routing - PLAN CHECK | 9/21/2015 | | 10/12/2015 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
Routing - MECHANICAL | | | 9/24/2015 | | FAIL |
|
|
|
|
Routing - Design Review | 9/23/2015 | | 9/23/2015 | | FAIL |
Andrea Tuning
|
|
|
No landscape plan was provided.
|
Routing - PLANNING | | | 9/23/2015 | | PASS |
|
|
|
|
Routing - Addressing | 9/21/2015 | | 9/21/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/21/2015 | | 9/21/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 9/21/2015 | | PASS |
|
|
|
|
Telephone call | | | 9/11/2015 | | DONE |
|
|
|
called Dave to let know we received paper resubmittals and that they need picked up and to be uploaded into e plan review. He's sending someone in to pick the plans up. They're on the counter behind the permit techs
|
Intake Approval | | | 9/2/2015 | | FAIL |
|
|
|
The new addresses are not approved by addressing, informed Chad that he will need to speak with Emily. Informed Chad that he will need an application for each address and can upload one with the plans and email me the other five. Also informed him that he would need a Manual J/S for each address. He will also need to revise his plans showing where things will be in each unit. Also missing the second story floor plans
|
Application received | | | 8/31/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 31 2015 8:49AM
|