VOIDED CHANGE STATUS | | | 2/27/2017 | | DONE |
|
|
|
Per Thomas Williams this project is not going through
|
BLD-Conference | 1/31/2017 | 1/31/2017 | 1/31/2017 | P | DONE |
Jim Sly
|
|
|
Just need to make sure work wasn't done. Claim that customer is not going to pick up permit and have the work done. PLEASE DO NOT VOID OR EXPIRE PERMIT. Thank you........ No apparent work going on.
|
Telephone call | | | 1/31/2017 | | DONE |
|
|
|
Spoke with Thomas Williams and he informed me that the customer isn't going to have the work done.
|
Telephone call | | | 1/30/2017 | | DONE |
|
|
|
Left a message for Tom that this permit is going to expire in 24 days and that he has had the two extensions we can grant. Asked him to give me a call so that we may go over how they would like to continue with the permit
|
Extend Review Timeline | | | 8/15/2016 | | DONE |
|
|
|
Final 180 day extension approved by Adele. See documents
|
Expiration Notice | 8/2/2016 | 8/23/2016 | 8/2/2016 | | DONE |
Brittany Hill
|
|
|
|
Extend Review Timeline | | | 2/18/2016 | | DONE |
|
|
|
1st 180 days approved by Jason B. See documents
|
Expiration Notice | 2/10/2016 | 3/3/2016 | 2/10/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 9/25/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 9/8/2015 | 9/8/2015 | 9/25/2015 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - Western Auto Sales
|
Routing - PLAN CHECK | 9/25/2015 | | 9/25/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/25/2015 | | DONE |
|
|
|
***STILL NEEDS RP 2-17-16 /CEV
NEED GC form, certificate of value, and RP
|
1st review completed | | | 9/21/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 9/8/2015 | | 9/21/2015 | | FAIL |
Carl D Madsen
|
|
|
Engineering for the beam does not match what is on the plans.
|
Routing - FIRE | 9/8/2015 | 9/8/2015 | 9/11/2015 | | PASS |
Scott Arellano
|
|
|
No separate comments attached to plans.
|
Routing PW Environmental | 9/9/2015 | | 9/10/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing - Design Review | 9/8/2015 | | 9/10/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00306
|
Routing - Erosion and Sediment | 9/8/2015 | | 9/9/2015 | | PASS |
Evan Jenkins
|
|
|
(WESTERN AUTO SALES) Removal of an exterior wall section facing Fairview Ave. and 2 other partial walls between old car wash bays. Commercial Demo
|
Routing - Addressing | 9/8/2015 | | 9/9/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/8/2015 | | 9/9/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 9/8/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen and plan review fees paid.
|
Pending Assignment by JCB | 9/8/2015 | | 9/8/2015 | | DONE |
Jason Blais
|
|
|
First review completed
|
Intake Approval | | | 9/3/2015 | | FAIL |
|
|
|
Please provide either a esc waiver requuest or an esc plan.
Please provide a building code analysis as it is not an optional item.
|
Application received | | | 9/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 2 2015 7:33AM
|