Third Notice | | 12/15/2015 | 12/21/2015 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Second Notice | | 11/19/2015 | 12/10/2015 | | DONE |
|
|
|
mailed 12-11-15
|
First Notice | | 11/1/2015 | 11/9/2015 | | DONE |
|
|
|
Mailed 11-10-15
|
BLD-Final | 10/21/2015 | 10/22/2015 | 10/22/2015 | A | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 10/22/2015 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 10/7/2015 | 10/7/2015 | 10/7/2015 | P | DONE |
Troy Cobbley
|
|
|
Went over exit signs
|
BLD-Framing/Rough-in | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/28/2015 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 9/14/2015 | | 9/18/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 9/14/2015 | | 9/18/2015 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 9/18/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/18/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/18/2015 | | DONE |
|
|
|
***MET*** Need GC and Revised Cert of Value
|
Print Occupancy Form | | | 9/18/2015 | | DONE |
|
|
|
|
Telephone call | | | 9/18/2015 | | DONE |
|
|
|
calleed Nate to let know permit is ready and that we need the GC and rev cert of val
|
Plans ACCEPTED BY PLAN TECH | | | 9/14/2015 | | DONE |
|
|
|
|
Intake Approval | | | 9/14/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/14/2015 | | DONE |
|
|
|
|
Application received | | 9/11/2015 | | | |
|
|
|
|