Permit Information
Permit NumberBLD15-03329
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 611 S 8TH ST
Project NameThe Afton
Customer Number 
ePlanReviewYes
Description
(THE AFTON – PHASE I – CONCRETE PODIUM) (DRH14-00262) The fire sprinkler system (NFPA 13 below and above the podium per the “Special Design Standards for Type V Construction” ordinance) will be used for story and height increase. To construct Phase I of a multi-phase mixed use project. All other drawings are for reference only. After all phases are completed, uses are expected to include parking on the 1st and 2nd stories, live/work units on the 1st and 2nd stories, apartments on the 1st story, two story apartments on the 2nd and 3rd stories, and 1 story apartments on the 3rd, 4th , 5th, and 6th stories. Work under this permit is to include two-way post tensioned concrete slab floors with drop caps and concrete beams (where needed) supported by concrete columns and ordinary shear walls. The podium level (floor of 3rd story) will be a maximum 12 inch thick post tensioned concrete slab having a 3-hr fire-resistance-rating. The floor of the 2nd story will be an 8 inch thick post tensioned concrete slab. Special Inspection is required for soils, concrete including post tensioning, masonry, steel including welding, etc. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. This permit does not establish a Certificate of Occupancy for any portion of this building. Fire sprinkler permits and fire alarm permits are required in conjunction with future building permits. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 10/5/201710/3/2017 DONE
This permit finaled on the web by Ami Tracy
First Notice 9/18/20179/25/2017 DONE
BLD-Final9/8/20179/8/20179/8/2017PPASS
DetailsDave Hannah
for perm occ
DOC - Permit Finaled  9/8/2017 DONE
FIRE-Final Inspection9/7/20179/7/20179/7/2017APASS
DetailsJim Page
Final life fire safety inspection passed/complete
BLD-Final8/30/20178/31/20178/31/2017ACANC
DetailsDave Hannah
Final for 201 and 202 Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Final8/21/20178/22/20178/22/2017PPART
DetailsDave Hannah
First level town homes Phone #: ###-#### Inspection requested via web by Ami Tracy ok to occ units 105,106 and 107
BLD-Framing/Rough-in6/26/20176/26/20176/26/2017PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
Zoning Approval Temp6/14/20176/14/20176/14/2017 DONE
DetailsAndrea Tuning
BLD-Conference6/12/20176/12/20176/12/2017PDONE
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance5/26/20175/30/20175/30/2017APASS
DetailsDave Hannah
6th Floor Trash Chute Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance5/22/20175/23/20175/23/2017APEND
DetailsDave Hannah
1st floor - Jason Phone #: ###-####
BLD-Energy code compliance5/5/20175/5/20175/7/2017PPART
DetailsDave Hannah
6th Floor Trash Chute Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Conference4/12/20174/17/20174/17/2017APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Framing/Rough-in3/16/20173/17/20173/17/2017APEND
DetailsDave Hannah
Trash Chute Walls Phone #: ###-#### Inspection requested via web by Ami Tracy ok to cover all but for sixth floor shaft does not up though attic must cut attic trusses to get shaft though roof
BLD-Energy code compliance3/3/20173/3/20173/3/2017PNR
DetailsDave Hannah
6th Floor Rescheduled Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Wall cover2/20/20172/21/20172/21/2017APART
DetailsJim Sly
Level 6 Ceiling.....and Townhome insulation...3 units Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance2/6/20172/6/20172/6/2017PPASS
DetailsDave Hannah
6th Floor Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance2/1/20172/2/20172/2/2017ANR
DetailsDave Hannah
6th Floor Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance1/30/20171/30/20171/30/2017PPASS
DetailsDave Hannah
Insultion // Jason Phone #: ###-####
BLD-Energy code compliance1/26/20171/27/20171/27/2017APASS
DetailsDave Hannah
Unit 601 insulation - Jesse will be on site Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance12/30/20161/3/20171/3/2017APASS
DetailsDave Hannah
6th Floor Ceilings Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Ceiling Grid Inspection12/27/201612/28/201612/28/2016APART
DetailsDave Hannah
Phone #: ###-#### 5th floor drops ok to cover
BLD-Energy code compliance12/22/201612/22/201612/22/2016PPART
DetailsDave Hannah
Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy ok to cover 501-504
BLD-Energy code compliance12/20/201612/20/201612/20/2016PPART
DetailsDave Hannah
Insulation // Jason Phone #: ###-#### second floor two east apts ok to cover walls
BLD-Conference12/15/201612/15/201612/16/2016PPART
DetailsDave Hannah
5th Floor Framing Phone #: ###-#### Inspection requested via web by Ami Tracy second floor live work units two on th eastend ok to cover ext walls and one side int need to check floor pens and fire wall pens 4th floor west uint ok to cover all but for mec chase by front door
BLD-Wall cover12/2/201612/2/201612/2/2016ACANC
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Conference12/1/201612/1/201612/2/2016PPART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy furred downs on 4th floor
BLD-Framing/Rough-in11/17/201611/18/201611/18/2016PPASS
DetailsDave Hannah
Level 1,2 & 5 - Jason Phone #: ###-####
BLD-Energy code compliance11/17/201611/18/201611/18/2016PPART
DetailsDave Hannah
Level 4 insulation - Jason Phone #: ###-#### first two units ok to cover
BLD-Framing/Rough-in11/14/201611/15/201611/15/2016APART
DetailsDave Hannah
4th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy ok to insulate
BLD-Wall Bracing11/14/201611/15/201611/15/2016APASS
DetailsDave Hannah
4th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy signed off by mti
BLD-Framing/Rough-in11/14/201611/14/201611/14/2016PDEFR
DetailsMike Jordan
4th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy. OUt of time.
BLD-Energy code compliance11/10/201611/10/201611/10/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### 3rd fl ok to cover
BLD-Energy code compliance11/8/201611/9/201611/9/2016APEND
DetailsDave Hannah
Insulation // Jason Phone #: ###-#### walls ok but need to finish fire cualking in drop ceilings
BLD-Energy code compliance11/7/201611/8/201611/8/2016APART
DetailsDave Hannah
Jason Phone #: ###-#### 3rd floor walls ok
BLD-Framing/Rough-in11/2/201611/2/201611/3/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### ok to insulate walls 3rd floor
BLD-Framing/Rough-in10/25/201610/26/201610/26/2016APEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Energy code compliance10/17/201610/17/201610/18/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### ceilings 5th floor
BLD-Energy code compliance10/12/201610/13/201610/13/2016ANR
DetailsPhil Shearer
Jason Phone #: ###-####
BLD-Energy code compliance9/21/20169/22/20169/22/2016APART
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Energy code compliance9/14/20169/15/20169/15/2016APART
DetailsDave Hannah
Unit 304 & 305 - Jason Phone #: ###-#### ceilings sheetrock also ok
BLD-Energy code compliance9/14/20169/14/20169/14/2016PDEFR
DetailsJim Storey
Unit 304 & 305 - Jason Phone #: ###-#### out of time
BLD-Energy code compliance9/8/20169/8/20169/8/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### ceilings in first 4 rooms
BLD-Framing/Rough-in9/2/20169/6/20169/6/2016APASS
DetailsDave Hannah
Roof - Jason Phone #: ###-####
BLD-Framing/Rough-in8/24/20168/24/20168/24/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### roof sheeting ok to cover
BLD-Framing/Rough-in8/15/20168/16/20168/16/2016APASS
DetailsMike Jordan
Nathan Phone #: ###-####. 1st and 2nd. floor exterior steel stud framed walls ok to cover exterior side only.
BLD-Framing/Rough-in8/3/20168/4/20168/5/2016ANR
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Framing/Rough-in8/3/20168/3/20168/3/2016PDEFR
DetailsJim Storey
Jason Phone #: ###-#### out of time rolled to am
BLD-Conference6/30/20166/30/20166/30/2016PPASS
DetailsDave Hannah
Two hour radiant // Jason Phone #: ###-####
BLD-Conference6/8/20166/9/20166/9/2016APASS
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Conference6/6/20166/7/20166/7/2016APASS
DetailsDave Hannah
Requests 9AM - Jason Phone #: ###-####
BLD-Foundation5/2/20165/2/20165/3/2016PPASS
DetailsDave Hannah
Phone #: ###-####
BLD-Framing/Rough-in3/10/20163/11/20163/14/2016APEND
DetailsDave Hannah
Jason Phone #: ###-#### frist level pt dick work in progress mti will signoff this afternoon
BLD-Other3/9/20163/9/20163/10/2016PNR
DetailsDave Hannah
Jason-post tension deck Phone #: ###-####
BLD-Foundation2/18/20162/18/20162/19/2016PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Foundation2/10/20162/10/20162/11/2016PDEFR
DetailsMike Jordan
Jason Phone #: ###-####. As per Jason foundation already placed. he noted that foundation had special inspection. Inspection was scheduled for 2-10. Did not recieve request until this afternoon.
BLD-Footing1/29/20162/1/20162/4/2016PPEND
DetailsDave Hannah
Rebar for columns & footings - Jason Phone #: ###-#### ok after s/i sign off
BLD-Foundation1/25/20161/25/20161/28/2016PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Footing1/21/20161/22/20161/22/2016APEND
DetailsDave Hannah
Jason Phone #: ###-#### ok after spec/insp sign off
BLD-Foundation1/11/20161/11/20161/15/2016PPASS
DetailsDave Hannah
Jason-shear walll rebar and column rebar Phone #: ###-####
BLD-Footing1/6/20161/7/20161/7/2016APEND
DetailsDave Hannah
Jay-footings, calumns & Shear walls Phone #: ###-####
BLD-Foundation12/31/201512/31/20151/4/2016PPEND
DetailsDave Hannah
Rebar // Jason Phone #: ###-####
BLD-Foundation12/29/201512/30/201512/31/2015PPART
DetailsDave Hannah
Rebar // Jason Phone #: ###-#### ok after mti sign off
BLD-Foundation12/21/201512/22/201512/23/2015PPART
DetailsDave Hannah
rebar; Jason Phone #: ###-#### ok after mti does final on rebar
Issue PAID IN FULL permit  11/12/2015 DONE
Inspection Record Card- Bld  11/12/2015 DONE
Inspection Record Card- Bld  11/12/2015 DONE
OVERRIDE  10/30/2015  
Plan assigned to (CJW)9/16/20159/16/201510/30/2015 PASS
DetailsCarl Westfall
(1st done) AFTON PODIUM (Oct 5 - 15 days)
Routing - PLAN CHECK10/27/2015 10/30/2015 PASS
DetailsCarl Westfall
Podium phase approved
PLANS/APPL TAKEN TO FRONT DESK  10/30/2015 DONE
Permit Ready to Issue  10/30/2015 DONE
***ALL REQUIRMENTS MET 11-12-15 CEV Needs; ACHD approval
Routing Off Site - STRUCTURAL10/27/2015 10/29/2015 PASS
DetailsCarl Westfall
Jared Bauder
Plan resubmittals received  10/27/2015 DONE
Routing - PLAN CHECK10/14/2015 10/21/2015 PASS
DetailsCarl Westfall
Last item resolved
Plan resubmittals requested  10/21/2015 DONE
Routing - PLUMBING10/14/2015 10/20/2015 PASS
DetailsBill VanDegrift
Bill Vandegrift
Routing Off Site - STRUCTURAL10/14/2015 10/19/2015 FAIL
DetailsCarl Westfall
Jared Bauder with CH2M Hill
Routing PW Sewer Design10/14/2015 10/15/2015 PASS
DetailsKyle S. Rosenmeyer
Kyle Rosenmeyer
Plan resubmittals received  10/14/2015 DONE
Routing - PLAN CHECK10/14/2015 10/14/2015 FAIL
DetailsCarl Westfall
Item #2 is not resolved
Routing - FIRE10/14/2015 10/14/2015 PASS
DetailsKatie Marron
Updated report attached to case.
Routing - Design Review10/14/2015 10/14/2015 PASS
DetailsJosh Wilson
Ok- podium only.
Route to Impact Fee Review10/6/201510/9/201510/7/2015 PASS
DetailsCindy M. Gould
No commercial or dwellings on this phase of th project.
Routing PW Environmental9/16/2015 10/6/2015 PASS
DetailsRick Christenson
Interceptor shown for future use.
1st review completed  10/6/2015 DONE
Plan resubmittals requested  10/6/2015 DONE
Routing - PLAN CHECK9/16/2015 10/6/2015 FAIL
DetailsCarl Westfall
Revised drawings required
Routing - FIRE9/16/2015 10/6/2015 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing PW Drainage9/16/2015 10/5/2015 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL9/16/2015 9/30/2015 FAIL
DetailsCarl Westfall
Jared Bauder with CH2M Hill
Routing PW Street Lights9/16/2015 9/25/2015 PASS
DetailsRob Bousfield
Routing PW Sewer Design9/16/2015 9/25/2015 FAIL
DetailsKyle S. Rosenmeyer
Please update sewer standard notes to the October 2014 version, available on City of Boise's website.

Type C connection for 6" Services not allowed. 2% minimum slope required inside Public Works easement area.
Routing - Design Review9/25/2015 9/25/2015 PASS
DetailsJosh Wilson
Ok for concrete podium only.
Routing - Addressing9/16/2015 9/21/2015 PASS
DetailsEmily Dixon
Correct address is 611 S 8th St. 32 additional address for apartments and suites.
Routing PW Geothermal9/16/2015 9/18/2015 PASS
DetailsJon R. Gunnerson
Not using geothermal.
Routing - Design Review9/18/2015 9/18/2015 FAIL
DetailsJosh Wilson
Drawings including building elevations, site plan, landscape plan, and floor plans do not match approved drawings for DRH14-00262. Please submit revised drawings or apply for a Modification to DRH14-00262.
Routing - PLUMBING9/16/2015 9/17/2015 FAIL
DetailsDaryl Spivey
1) address suds relief through out
2) vent interceptors
Routing - PLANNING Land Div9/16/2015 9/16/2015 PASS
DetailsDave Abo
Parcel A of ROS 10203.
Pending Assignment by TLW9/16/2015 9/16/2015 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS9/16/2015 9/16/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment9/16/2015 9/16/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

Afton condominiums - Phase I, 28 condos, retail and 2-story parking structure (This phase
includes only the concrete podium)
Plan Reviewer's activity  9/15/2015 DONE
DetailsAdele J Schaffeld-Griffin
Spoke with Dave, verificationof legal lot form completed.
Plan Reviewer's activity  9/15/2015 DONE
DetailsAdele J Schaffeld-Griffin
Spoke with Josh Wilson, planning good to take in podium.
Intake Approval  9/15/2015 PASS
Application received  9/14/2015 DONE
Application submitted via PDS Online on Sep 14 2015 3:24PM