Letter of compliance/Occupancy | | | 6/10/2016 | | DONE |
|
|
|
|
BLD-Final | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Tony Young
|
|
|
Nate Phone #: ###-####
|
DOC - Permit Finaled | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 5/16/2016 | 5/17/2016 | 5/17/2016 | P | NR |
Tony Young
|
|
|
Nate Phone #: ###-####,, needs hand rail per code ,,interior and exterior,, need steps on front to meet code,, ladder out of basement window wells
|
Zoning Approval | 5/13/2016 | 5/13/2016 | 5/13/2016 | | DONE |
Matthew A Halitsky
|
|
|
|
BLD-Energy code compliance | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Tony Young
|
|
|
Nate Phone #: ###-####
|
BLD-Energy code compliance | 2/16/2016 | 2/17/2016 | 2/17/2016 | A | NR |
Tony Young
|
|
|
Nate Phone #: ###-####,, on site conf only
|
BLD-Energy code compliance | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | NR |
Tony Young
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Tony Young
|
|
|
Nate Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 2/1/2016 | 2/2/2016 | 2/3/2016 | P | NR |
Tony Young
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PART |
Tony Young
|
|
|
Nate Phone #: ###-####,, frame walk through only,, need fire place inspection,, need seal pack
|
BLD-Wall Bracing | 1/21/2016 | 1/22/2016 | 1/22/2016 | A | PART |
Tony Young
|
|
|
Nate Phone #: ###-####,, house ok
|
Plan Modification Accepted | | | 1/21/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/21/2016 | | 1/21/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | PART |
Tony Young
|
|
|
Mana-pour time 11:00 Phone #: ###-####
|
BLD-Footing | 10/20/2015 | 10/21/2015 | 10/21/2015 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, basement footings
|
Issue PAID IN FULL permit | | | 10/9/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/9/2015 | | DONE |
|
|
|
|
Routing - PLANNING | 10/1/2015 | | 10/1/2015 | | PASS |
Matthew A Halitsky
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/1/2015 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (DAF) | 9/18/2015 | 9/18/2015 | 9/28/2015 | | DONE |
David Ferguson
|
|
|
due 9/30 ePlan
|
1st review completed | | | 9/28/2015 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 9/16/2015 | | 9/28/2015 | | PASS |
David Ferguson
|
|
|
|
Routing - MECHANICAL | 9/16/2015 | | 9/25/2015 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 9/16/2015 | | 9/18/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 9/16/2015 | 9/19/2015 | 9/17/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/16/2015 | | DONE |
|
|
|
|
Intake Approval | | | 9/16/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/16/2015 | | DONE |
|
|
|
|
Routing - PLANNING | 9/16/2015 | | 9/16/2015 | | FAIL |
Matthew A Halitsky
|
|
|
Landscaping buffer and windows.
|
Routing - Addressing | 9/16/2015 | | 9/16/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/16/2015 | | 9/16/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 9/15/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 15 2015 10:18AM
|