Permit Information
Permit NumberBLD15-03348
StatusFinaled
Name BLUE RIDGE CONSTRUCTION
Site Address 2164 S BROADWAY AVE
Project NameBroadway Music
Customer Number 
ePlanReviewYes
Description
(BROADWAY MUSIC)(BROADWAY PARK) Permit is for remodel of existing 2,100 sq. ft. tenant space. This permit is approved contingent upon adhering to the approved plans on file. Work to include: construction of interior nonbearing walls to create (2) new offices, new nonbearing furred out full height walls at the existing adjacent tenant demising walls, new ADA compliant drinking fountains, relocated mop sink, adjustments to restroom fixtures to make ADA compliant restroom, new gypsum ceiling, new light fixtures, mechanical ductwork and interior finishes in compliance with Ch. 8 of the 2012 IBC. Note: the rear sales area of the tenant space shall not be used as storage. This building is not Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/16/20162/11/2016 DONE
Second Notice 12/20/20151/11/2016 DONE
Mailed 1-12-16
First Notice 12/3/201512/10/2015 DONE
Mailed 12-11-15
BLD-Final11/23/201511/23/201511/23/2015PPASS
DetailsJim Storey
Larry Phone #: ###-####
Permanent Occupancy  11/23/2015 DONE
FIRE-Final Inspection11/19/201511/20/201511/20/2015PPASS
DetailsJim Page
No fire sprinklers for this project, no fire alarms for this project. Life fire safety passed/complete.
BLD-Framing/Rough-in11/4/201511/5/201511/5/2015APASS
DetailsJim Storey
Larry Phone #: ###-#### fw and fb ok to cover front canopy area
BLD-Energy code compliance10/30/201511/2/201511/2/2015PPASS
DetailsJim Storey
Larry Phone #: ###-####
BLD-Framing/Rough-in10/29/201510/30/201510/30/2015PPASS
DetailsJim Storey
Larry Phone #: ###-####
Plan assigned to (JG)9/18/20159/18/20159/25/2015 PASS
DetailsJavier Guzman
1st review completed, 9/24 L1 Doyle Music
Routing - PLAN CHECK9/25/2015 9/25/2015 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  9/25/2015 DONE
Permit Ready to Issue  9/25/2015 DONE
Need GC and Revised Cert of Value
Print Occupancy Form  9/25/2015 DONE
Issue PAID IN FULL permit  9/25/2015 DONE
Routing - PLAN CHECK9/18/2015 9/23/2015 FAIL
DetailsJavier Guzman
ePlan
1st review completed  9/23/2015 FAIL
DetailsJavier Guzman
Routing - PUBLIC WORKS9/18/2015 9/21/2015 PASS
DetailsJennifer Bruner
Routing PW Sewer Rating9/21/2015 9/21/2015 PASS
DetailsJennifer Bruner
Intake Approval  9/18/2015 PASS
DetailsJavier Guzman
Routing - Addressing9/18/2015 9/18/2015 PASS
DetailsEmily Dixon
Application received  9/16/2015 DONE
Application submitted via PDS Online on Sep 16 2015 8:00AM
Intake Approval  9/16/2015 FAIL
DetailsDavid Ferguson
Please provide a Key Plan of the building as indicated as a required submittal document on the TI Checklist.