BLD-Final | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | PASS |
Tony Young
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 9/14/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Tony Young
|
|
|
|
Zoning Approval | 9/9/2016 | 9/9/2016 | 9/9/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Energy code compliance | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Framing/Rough-in | 7/21/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Framing/Rough-in | 7/19/2016 | 7/20/2016 | 7/20/2016 | A | PART |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Work in progress on framing corrections. ok to insulate. Will inspect remainder on energy code inspection.
|
BLD-Framing/Rough-in | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | FAIL |
Phil Shearer
|
|
|
Dave Phone #: ###-####
|
BLD-Wall Bracing | 6/9/2016 | 6/10/2016 | 6/10/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Wall Bracing | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | FAIL |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Needs to install all floor to floor straps.
|
BLD-Conference | 4/27/2016 | 4/27/2016 | 4/28/2016 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Foundation | 4/25/2016 | 4/26/2016 | 4/26/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####. interior thickend footings.
|
BLD-Foundation | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | PART |
Mike Jordan
|
|
|
Late AM please - Manuel Phone #: ###-####
|
BLD-Footing | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/28/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 2/23/2016 | | DONE |
|
|
|
1st 180 days approved by Jason B. See documents
|
Expiration Notice | 2/18/2016 | 3/10/2016 | 2/18/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 2/4/2016 | | |
|
|
|
|
Routing - MECHANICAL | 2/4/2016 | | 2/4/2016 | | PASS |
Tisha Gallop
|
|
|
per ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/4/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/4/2016 | | DONE |
Christina Prado
|
|
|
Need RP & GC Form for issuance
|
Plan assigned to (LEG) Tisha | 9/21/2015 | | 2/4/2016 | | DONE |
Tisha Gallop
|
|
|
3rd review 1/28 pending mech; 2nd review 12/1; 1st review 10/12; L2 ePlan*
|
Routing - MECHANICAL | 2/1/2016 | | 2/2/2016 | | FAIL |
Troy James
|
|
|
ref activity in Bld15-03117
|
Plan resubmittals received | | | 2/1/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/26/2016 | | 1/28/2016 | | PASS |
Tisha Gallop
|
|
|
pending approval by mechanical
|
Routing - MECHANICAL | 1/26/2016 | | 1/28/2016 | | FAIL |
Troy James
|
|
|
Previous comment has not been addressed dated 11-25-15.
|
Plan resubmittals received | | | 1/25/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/1/2015 | | 12/1/2015 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
Routing - Design Review | 11/30/2015 | | 11/30/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - MECHANICAL | 11/24/2015 | | 11/24/2015 | | FAIL |
Troy James
|
|
|
|
Plan resubmittals received | | | 11/20/2015 | | DONE |
|
|
|
|
Routing - Design Review | 9/23/2015 | | 10/12/2015 | | FAIL |
Andrea Tuning
|
|
|
per ePlan
|
1st review completed | | | 10/12/2015 | | DONE |
|
|
|
pending approval from Mechanical, Design Review, Plan Check
|
Routing - PLAN CHECK | 9/21/2015 | | 10/12/2015 | | FAIL |
Tisha Gallop
|
|
|
see changemarks
|
Routing - MECHANICAL | | | 9/24/2015 | | FAIL |
|
|
|
|
Routing - PLANNING | | | 9/23/2015 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/21/2015 | | DONE |
|
|
|
|
Intake Approval | | | 9/21/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/21/2015 | | DONE |
|
|
|
|
Routing - Addressing | 9/21/2015 | | 9/21/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/21/2015 | | 9/21/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 9/17/2015 | | | |
|
|
|
|