BLD-Final | 2/21/2018 | 2/22/2018 | 2/23/2018 | A | PASS |
Dave Hannah
|
|
|
Please call ahead for access - Shane Phone #: ###-####
|
DOC - Permit Finaled | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 1/11/2018 | 1/11/2018 | 1/11/2018 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Other | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | PASS |
Dave Hannah
|
|
|
steel insp// Shane Phone #: ###-####
|
BLD-Foundation | 7/5/2017 | 7/7/2017 | 7/7/2017 | A | PASS |
Dave Hannah
|
|
|
Rebar // Shane Phone #: ###-####
|
BLD-Final | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | NR |
Dave Hannah
|
|
|
Shane Phone #: ###-####
|
Routing Walk-In (Zoning) | 7/11/2016 | 7/11/2016 | 7/11/2016 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 7/11/2016 | 7/11/2016 | 7/11/2016 | A | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 7/11/2016 | | 7/11/2016 | | PASS |
Brian McGowan
|
|
|
For Plan Modification 7-11-16
|
Case Summary (BLD) | | | 7/11/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/11/2016 | | DONE |
|
|
|
Plan mod only - do NOT re-issue
|
CHANGE STATUS TO (ISS) | | | 7/11/2016 | | DONE |
|
|
|
plan mod fees paid
|
Plan Modification Accepted | | | 7/11/2016 | | DONE |
|
|
|
modification being done to the plans (including exterior)
|
Routing Walk-In (BLD) | 7/5/2016 | 7/5/2016 | 7/5/2016 | A | FAIL |
Brian McGowan
|
|
|
The home owner is proposing to construct the project in a different manor than the engineering provided. I requested a drawing or letter be provided from the Engineer (JDE) verifying the alterations were acceptable.
|
Routing Walk-In (BLD) | 9/28/2015 | 9/28/2015 | 9/28/2015 | A | PASS |
Tisha Gallop
|
|
|
Phase I only
|
Plan assigned to (LEG) Tisha | 9/28/2015 | | 9/28/2015 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 9/28/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/28/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/28/2015 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 9/21/2015 | 9/21/2015 | 9/21/2015 | A | PASS |
Matthew A Halitsky
|
|
|
|
Routing Walk-In (BLD) | 9/21/2015 | 9/21/2015 | 9/21/2015 | A | FAIL |
Tisha Gallop
|
|
|
need engineering, non-typical steel frame construction
|
1st review completed | | | 9/21/2015 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 9/17/2015 | | | |
|
|
|
|