Print Statement | | | 7/19/2016 | | DONE |
|
|
|
|
Third Notice | | 6/15/2016 | 7/11/2016 | | DONE |
|
|
|
|
Second Notice | | 6/2/2016 | 6/10/2016 | | DONE |
|
|
|
|
First Notice | | 4/30/2016 | 5/23/2016 | | DONE |
|
|
|
|
BLD-Final | 4/18/2016 | 4/18/2016 | 4/20/2016 | P | PASS |
Dave Hannah
|
|
|
Kelly Phone #: ###-####
|
Permanent Occupancy | | | 4/20/2016 | | DONE |
|
|
|
|
Temporary Occupancy | 4/19/2016 | 7/18/2016 | 4/19/2016 | | DONE |
Kristal Soland
|
|
|
|
Zoning Approval | 4/18/2016 | 4/18/2016 | 4/18/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 4/14/2016 | 4/15/2016 | 4/15/2016 | P | PART |
Jim Storey
|
|
|
Kelly Phone #: ###-####-fire to be done early PM need p&z sign off/ temp ok basement cleared out at insp. temp on mech
|
FIRE-Final Inspection | 4/15/2016 | 4/15/2016 | 4/15/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher is in place with current inspection tag. Final life fire safety inspection passed/complete
|
Print Occupancy Form | | | 4/15/2016 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 4/11/2016 | 4/12/2016 | 4/12/2016 | A | PASS |
Dave Hannah
|
|
|
Kelly Phone #: ###-####
|
Plan assigned to (AJS) | 4/7/2016 | 4/7/2016 | 4/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Plan Mod. ePlanReview - Even Stevens
|
Routing - PLAN CHECK | 4/7/2016 | | 4/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 4/7/2016 | | 4/11/2016 | | PASS |
Troy James
|
|
|
added type II hood over conveyor oven.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/11/2016 | | DONE |
|
|
|
no plan mod fees due as per Adele Schaffeld-Griffin
|
CHANGE STATUS TO (ISS) | | | 4/11/2016 | | DONE |
|
|
|
no fees due
|
BLD-Conference | 4/8/2016 | 4/8/2016 | 4/9/2016 | P | DONE |
Dave Hannah
|
|
|
Kelly Phone #: ###-####
|
FIRE-Conference | 4/8/2016 | 4/8/2016 | 4/8/2016 | P | DONE |
Jim Page
|
|
|
Life fire safety conference complete
|
Routing - FIRE | 4/7/2016 | 4/7/2016 | 4/8/2016 | | PASS |
Katie Marron
|
|
|
Modification to install a second Type II hood. No additional comments required.
|
Plan Modification Accepted | | | 4/7/2016 | | DONE |
Christina Prado
|
|
|
Plan Mod to add a second hood over conyeyor
|
BLD-Other | 3/23/2016 | 3/24/2016 | 3/24/2016 | A | PASS |
Dave Hannah
|
|
|
fire wall sheathing - Kelly Phone #: ###-####
|
Plan assigned to (AJS) | 2/22/2016 | 2/22/2016 | 3/23/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Plan mod review completed -Plan Mod - Even Stevens
|
CHANGE STATUS TO (ISS) | | | 3/23/2016 | | DONE |
Christina Prado
|
|
|
Plan mod fees paid, status changed back to ISS for inspections
|
Routing - PLAN CHECK | 3/23/2016 | | 3/23/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/23/2016 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE - PLAN MOD APPROVED, All requirements met
Must pay all fees prior to changing status to ISS
|
Routing - PLAN CHECK | 3/21/2016 | | 3/22/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
change marks not addressed need corrected/completed 310 form
|
Routing - PLUMBING | 3/21/2016 | | 3/21/2016 | | PASS |
Bill VanDegrift
|
|
|
1) additional cross connection protection may be required
2) indirectly waste the dish sink
3) R.P. on MAU
4) vent all traps
|
Routing - PLAN CHECK | 3/15/2016 | | 3/17/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 3/15/2016 | | 3/17/2016 | | FAIL |
Daryl Spivey
|
|
|
signed in e plan
|
Routing - PLAN CHECK | 2/22/2016 | | 3/2/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing Off Site - C.D.H | 2/22/2016 | | 3/2/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
BLD-Energy code compliance | 2/26/2016 | 2/29/2016 | 3/1/2016 | P | PART |
Dave Hannah
|
|
|
Kelly Phone #: ###-#### ok to start sheetrocking firewalls and insulation in ceiling
|
BLD-Framing/Rough-in | 2/25/2016 | 2/25/2016 | 2/26/2016 | P | PART |
Dave Hannah
|
|
|
For Part; part is where the modification is // Kelly Phone #: ###-#### ok to insulate 2hr fire wall and ceiling
|
Routing - MECHANICAL | 2/22/2016 | | 2/24/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/22/2016 | | 2/24/2016 | | FAIL |
Bill VanDegrift
|
|
|
1) UPC 910 and Appendix B-- vent all traps
resubmit P101
2) additional cross connection protection may be required
3) R.P> will be required on the make-up water to the MAU
4) indirect waste required for the K-27
|
Routing - FIRE | 2/22/2016 | 2/22/2016 | 2/22/2016 | | PASS |
Katie Marron
|
|
|
Modification reviewed. No changes to report/comments required.
|
Routing - Design Review | 2/22/2016 | | 2/22/2016 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH15-00393 - Storefront changes
|
Routing - Addressing | 2/22/2016 | | 2/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/22/2016 | | 2/22/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Modification Accepted | | | 2/22/2016 | | DONE |
Christina Prado
|
|
|
Per request of architect to modify the kitchen details for Plumbing review
|
Issue PAID IN FULL permit | | | 1/28/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/28/2016 | | DONE |
|
|
|
|
Telephone call | | | 1/26/2016 | | DONE |
|
|
|
spoke with Corey informing him he needs to get with ACHD and that we need gc form and revised value
|
Plan assigned to (AJS) | 11/18/2015 | 11/18/2015 | 1/25/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - Even Stevens
|
Routing - PLAN CHECK | 1/21/2016 | | 1/25/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/25/2016 | | DONE |
Christina Prado
|
|
|
Need ACHD, ***MET*** GC & Revised certificate of value for issuance
|
Routing - FIRE | 1/21/2016 | 1/21/2016 | 1/21/2016 | | PASS |
Katie Marron
|
|
|
Revised comments attached to case.
|
1st review completed | | | 12/17/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 11/18/2015 | | 12/17/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Environmental | 11/19/2015 | | 12/14/2015 | | PASS |
Rick Christenson
|
|
|
Grease Trap Shown.
|
Routing - MECHANICAL | 11/18/2015 | | 11/24/2015 | | PASS |
Troy James
|
|
|
|
Routing PW Sewer Rating | 11/19/2015 | | 11/23/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - FIRE | 11/18/2015 | 11/18/2015 | 11/19/2015 | | FAIL |
Scott Arellano
|
|
|
Report attached to case and emailed to architect.
|
Routing - Erosion and Sediment | 11/18/2015 | | 11/19/2015 | | CANC |
Evan Jenkins
|
|
|
No ESC Permit Required
|
Routing - Design Review | 11/18/2015 | | 11/19/2015 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH15-00393
|
Routing - PLUMBING | 11/18/2015 | | 11/19/2015 | | PASS |
Bill VanDegrift
|
|
|
1) vent all traps
2) additional cross connection protection will be required
|
Routing - Addressing | 11/18/2015 | | 11/19/2015 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/18/2015 | | 11/19/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Reviewer's activity | | | 11/18/2015 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 11/18/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Westfall and plan review fees paid.
|
Pending Assignment by JCB | 11/18/2015 | | 11/18/2015 | | |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 11/18/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to have him contact ACHD to determine if any additional impact fees are due. Will need written verification from ACHD provided to our Permit Counter prior to the building permit being issue.
|
Intake Approval | | | 11/9/2015 | | FAIL |
|
|
|
See the redlines on the plan intake checklist
|
Intake Approval | | | 9/21/2015 | | FAIL |
|
|
|
(9-21-15) See the redlines on the Plan Intake Submittal Checklist for additional items that need to be provided.
|
Application received | | | 9/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 18 2015 9:45AM
|