Plan Reviewer's activity | | | 8/6/2018 | | DONE |
Jason Blais
|
|
|
This project received LEED V4 Silver Certification. Is the first V4 project in Idaho.
|
Third Notice | | 11/19/2017 | 11/30/2017 | | DONE |
|
|
|
|
Print Statement | | | 11/30/2017 | | DONE |
|
|
|
|
Third Notice | | 10/17/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
Second Notice | | 9/29/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
First Notice | | 8/18/2017 | 9/19/2017 | | DONE |
|
|
|
sent in mail 9-20-17
|
Permanent Occupancy | | | 8/8/2017 | | DONE |
|
|
|
|
BLD-Final | 8/4/2017 | 8/4/2017 | 8/4/2017 | P | PASS |
Mike Jordan
|
|
|
ok for perm occ. Commissioning letter was sent and received as per Carl Madsen.
|
BLD-Final | 8/4/2017 | 8/4/2017 | 8/4/2017 | P | PEND |
Mike Jordan
|
|
|
Bruce-has temp c of o-was pending sub permit finals Phone #: ###-####. All trades have signed off. Noted to Bruce with CM that they need to submit the commissioning letter to building official.
|
BLD-Aging Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 | | DEFR |
Jim Storey
|
|
|
admin
|
Temporary Occupancy | 7/14/2017 | 10/12/2017 | 7/14/2017 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Meeting | | | 7/14/2017 | | DONE |
|
|
|
waiting to hear from Rob Bousfield to confirm if we can issue the temp c of o
|
BLD-Final | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | PART |
Jim Storey
|
|
|
Bruce Phone #: ###-####partial pending others-ok for temp c of o
|
Zoning Approval | 5/4/2017 | 5/4/2017 | 5/4/2017 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler ispection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is in place. Final life fire safety inspection passed/complete.
|
PubWorks Occupancy Approval | 4/26/2017 | 4/26/2017 | 4/26/2017 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 4/20/2017 | 4/20/2017 | 4/20/2017 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 4/19/2017 | 4/19/2017 | 4/20/2017 | | PASS |
Jim Storey
|
|
|
|
BLD-Ceiling Grid Inspection | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/20/2017 | 3/21/2017 | 3/21/2017 | A | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-####
|
BLD-Conference | 2/10/2017 | 2/13/2017 | 2/13/2017 | A | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-####
|
BLD-Conference | 2/9/2017 | 2/10/2017 | 2/10/2017 | A | DEFR |
Jim Storey
|
|
|
Bruce Phone #: ###-####
|
FIRE-Conference | 2/6/2017 | 2/7/2017 | 2/7/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
BLD-Conference | 2/2/2017 | 2/2/2017 | 2/2/2017 | A | FAIL |
Jim Storey
|
|
|
submit envelope report to planreview to reflect glazing frams and slylights
|
BLD-Framing/Rough-in | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-#### hard ceilling ok
|
BLD-Framing/Rough-in | 10/7/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-#### as noted on site
|
BLD-Energy code compliance | 10/10/2016 | 10/10/2016 | 10/10/2016 | A | PART |
Jim Storey
|
|
|
Bruce Phone #: ###-#### grid as noted on site
|
BLD-Framing/Rough-in | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | PART |
Dave Hannah
|
|
|
Bruce Phone #: ###-#### ok to cover int walls and ok to insulate ext walls see sign off sheet for location
|
BLD-Framing/Rough-in | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-#### roof deck atchment ok to cover
|
BLD-Framing/Rough-in | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-####exterior and paripett
|
BLD-Other | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | PASS |
Jim Storey
|
|
|
Slab pour - Bruce Phone #: ###-####
|
BLD-Foundation | 3/17/2016 | 3/18/2016 | 3/18/2016 | P | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-####
|
BLD-Footing | 3/9/2016 | 3/10/2016 | 3/10/2016 | A | PASS |
Jim Storey
|
|
|
Footing/foundation wall - Bruce Phone #: ###-####
|
BLD-Foundation | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PART |
Jim Storey
|
|
|
Wall rebar Phone #: ###-####pending report
|
BLD-Foundation | 2/11/2016 | 2/12/2016 | 2/12/2016 | P | PASS |
Jim Storey
|
|
|
Bruce Phone #: ###-#### rebar ok 3 wall and ft
|
BLD-Conference | 1/27/2016 | 1/27/2016 | 1/27/2016 | P | PART |
Jim Storey
|
|
|
Bruce Phone #: ###-#### pending si
|
OVERRIDE | | | 1/7/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 12/22/2015 | 12/22/2015 | 1/7/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/24/2015 | | 1/7/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/7/2016 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE
|
CHANGE STATUS TO (ISS) | | | 1/7/2016 | | DONE |
Christina Prado
|
|
|
No fees due for plan mod - permit status changed to issue
|
Plan Modification Accepted | | | 12/22/2015 | | |
|
|
|
|
(F) Reprint permit | | | 11/17/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/17/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/12/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (PND) | | | 11/12/2015 | | DONE |
|
|
|
FEES STILL DUE----ISSUED IN ERROR---- DON NOT RE-ISSUE ONCE FEES ARE PAID, JUST DO RE-PRINT :)
|
CHANGE STATUS TO (ISS) | | | 11/12/2015 | | DONE |
Rita DeYoung
|
|
|
Fees process via JV
|
OVERRIDE | | | 11/4/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 9/22/2015 | 9/22/2015 | 11/4/2015 | | PASS |
Carl D Madsen
|
|
|
Green Tag Library
First review completed 10-12-15
|
Routing - PLAN CHECK | 10/23/2015 | | 11/4/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/4/2015 | | DONE |
|
|
|
Needs; GC Form, Revised Cert of Value---- ALL REQUIREMENTS MET
|
Routing PW Sewer Design | 10/23/2015 | | 11/3/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - FIRE | 10/23/2015 | 10/23/2015 | 10/23/2015 | | PASS |
Scott Arellano
|
|
|
Revised comments attached to plans.
|
Routing - PUBLIC WORKS | 10/23/2015 | | 10/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 10/23/2015 | | 10/23/2015 | | PASS |
Brian Murphy
|
|
|
|
Route to Impact Fee Review | 10/12/2015 | 10/15/2015 | 10/19/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 10/12/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/22/2015 | | 10/12/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 9/22/2015 | | 10/12/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 9/23/2015 | | 10/6/2015 | | FAIL |
Brian Murphy
|
|
|
NEED C33 SAND IN DRAINAGE WINDOWS PRIOR TOFREEDRAINING GRAVELS
|
Routing - PLANNING | 9/22/2015 | | 10/2/2015 | | PASS |
Todd Tucker
|
|
|
CUP15-00065
|
Routing PW Sewer Design | 9/23/2015 | | 10/1/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Manhole exists near connection point that is not shown, and service out of that manhole that serves 2141 Parkcenter is not shown.
|
Routing - FIRE | 9/22/2015 | 9/22/2015 | 9/28/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to case and emailed to architect.
|
Routing PW Sewer Rating | 9/23/2015 | | 9/24/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLUMBING | 9/22/2015 | | 9/24/2015 | | PASS |
Daryl Spivey
|
|
|
mv-1 AND 2 TO BE asse 1070
|
Routing PW Solid Waste | 9/23/2015 | | 9/23/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing PW Street Lights | 9/23/2015 | | 9/23/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lighting required.
|
Routing - PLANNING Land Div | 9/22/2015 | | 9/23/2015 | | PASS |
Dave Abo
|
|
|
Parcel C of ROS 6530.
|
Routing - PUBLIC WORKS | 9/22/2015 | | 9/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 9/22/2015 | | 9/23/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
(GREEN TAG - PROJECT MANAGEMENT - Angela Brosious) A NEW 16,000 SF LIBRARY FOR THE CITY OF BOISE IS COMPRISED OF THREE PARTS, INCLUDING A 5,020 SF LOBBY AND MEETING AREA, A 7,390 SF READING ROOM, AND A 3,590 SF STAFF AREA. THE LOBBY AND MEETING AREA INCLUDES THE LOBBY, PUBLIC RESTROOMS, A MEETING ROOM, MULTIPURPOSE MEETING ROOM, STUDY AREAS, AND A BOOK DROP ROOM. THE READING ROOM INCLUDES A CHILDREN'S AREA, AN ADULT LOUNGE AREA, BOOK STACKS, AND A CIRCULATION DESK. THE STAFF AREA INCLUDES OPEN OFFICE AREA, BOOK HANDLING AREA, PRIVATE OFFICE, STORAGE ROOMS, STAFF BATHROOMS, MECHANICAL AND ELECTRICAL ROOM, JANITORS CLOSETS,AND A STAFF BREAK ROOM.
|
Routing - Addressing | 9/22/2015 | | 9/22/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - Design Review | 9/22/2015 | | 9/22/2015 | | PASS |
Andrea Tuning
|
|
|
DRH15-00304
|
Intake Approval | | | 9/22/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 9/22/2015 | | 9/22/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 9/21/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
9/21/15 Please see mark ups on checklist for items that need to be addressed prior to prescreen approval.
|
Application received | | | 9/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 18 2015 4:49PM
|