Third Notice | | 6/17/2017 | 6/20/2017 | | DONE |
|
|
|
This permit finaled on the web by Cecyle Brock
|
Third Notice | | 5/15/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
Third Notice | | 4/16/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
Second Notice | | 3/20/2017 | 4/11/2017 | | DONE |
|
|
|
Mailed 4-12-17
|
First Notice | | 2/20/2017 | 3/10/2017 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 3-13-17
|
PubWorks Occupancy Approval | 2/10/2017 | 2/10/2017 | 2/10/2017 | | DONE |
Mike Sheppard
|
|
|
|
Permanent Occupancy | | | 2/10/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/9/2017 | | DONE |
|
|
|
|
BLD-Final | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | PASS |
Dave Hannah
|
|
|
Josh/ please call ahead Phone #: ###-####
|
BLD-Final | 12/5/2016 | 12/6/2016 | 12/6/2016 | A | PART |
Dave Hannah
|
|
|
Josh// please call ahead Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 12/5/2016 | 12/5/2016 | 12/5/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher mounted in common area with current inspection tag. Final life fire safety inspection passed/complete.
|
BLD-Conference | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Dave Hannah
|
|
|
Josua-please call 30 minutes prior to meet Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | PASS |
Dave Hannah
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 10/6/2016 | 10/7/2016 | 10/10/2016 | A | PART |
Dave Hannah
|
|
|
Josh-2nd half-struc steel and 1st floor wood system Phone #: ###-#### ok to insulate floor/ceiling
|
BLD-Framing/Rough-in | 9/8/2016 | 9/9/2016 | 9/9/2016 | P | PASS |
Dave Hannah
|
|
|
Josh Phone #: ###-####
|
Telephone call | | | 7/25/2016 | | DONE |
|
|
|
Rhonda called to ask for extension, I told her the permit expired 180 days from 7/7/16 because they had an inspection.
|
BLD-Conference | 7/6/2016 | 7/6/2016 | 7/7/2016 | P | DONE |
Dave Hannah
|
|
|
Phone #: ###-####
|
BLD-Footing | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | PEND |
Dave Hannah
|
|
|
Shawn Phone #: ###-####
|
Inspection Record Card- Bld | | | 6/21/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/21/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/20/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/20/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/7/2016 | | DONE |
|
|
|
Cecyle emailed nme the GC and rev cert of val as well as the ACHD info and i emailed her the fees due amounts on both BLD15-03403 & 03345
|
Extend Review Timeline | | | 3/14/2016 | | DONE |
|
|
|
1st 180 days approved by Jason B. See documents
|
Telephone call | | | 3/7/2016 | | DONE |
|
|
|
Left a message for Bruce informing him that is permit is going to expire in ten days. Stated that if he would like an extension he would need to email Jason B; left email and building permit.
|
Expiration Notice | 2/23/2016 | 3/15/2016 | 2/23/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 12/21/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 9/24/2015 | 9/24/2015 | 12/21/2015 | | PASS |
Carl Westfall
|
|
|
(1st done) REDFEATHER LOUNGE - BASEMENT TI (Oct 13 - 15 days) Level 3 TI - ePlanReview
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/21/2015 | | DONE |
|
|
|
***MET***need ACHD, GC & rev cert of val
|
Routing - PLUMBING | 12/16/2015 | | 12/18/2015 | | PASS |
Bill VanDegrift
|
|
|
Sorry, I routed it to plumbing on accident.
vent all traps
|
Routing - MECHANICAL | 12/16/2015 | | 12/17/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 12/15/2015 | | 12/16/2015 | | PASS |
Carl Westfall
|
|
|
Resubmittal reviewed and approved
|
Plan resubmittals received | | | 12/15/2015 | | DONE |
|
|
|
|
Routing - FIRE | 12/10/2015 | | 12/11/2015 | | PASS |
Katie Marron
|
|
|
Revised report attached to plans
|
Routing - MECHANICAL | 12/10/2015 | | 12/11/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 12/10/2015 | | 12/11/2015 | | PASS |
Bill VanDegrift
|
|
|
vent floor sink
per plans and ISPC
|
Plan resubmittals requested | | | 12/11/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/8/2015 | | 12/10/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Plan resubmittals received | | | 12/8/2015 | | DONE |
|
|
|
|
1st review completed | | | 10/23/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/23/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/24/2015 | | 10/23/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required. Review delayed because of Jury Duty.
|
Routing Off Site - C.D.H | 9/24/2015 | | 10/13/2015 | | PASS |
Carl Westfall
|
|
|
Joe Antonucci
|
Routing PW Environmental | 9/24/2015 | | 10/6/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 9/24/2015 | | 9/30/2015 | | FAIL |
Troy James
|
|
|
|
Routing PW Sewer Rating | 9/24/2015 | | 9/28/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLUMBING | 9/24/2015 | | 9/28/2015 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - FIRE | 9/24/2015 | 9/24/2015 | 9/25/2015 | | FAIL |
Scott Arellano
|
|
|
Report attached to case and emailed to architect.
|
Pending Assignment by JCB | 9/24/2015 | | 9/24/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 9/24/2015 | | 9/24/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/24/2015 | | 9/24/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 9/24/2015 | | 9/24/2015 | | PASS |
Evan Jenkins
|
|
|
(RED FEATHER LOUNGE)(BASEMENT) Final work to bring the existing space in the Red Feather Lounge Basement up to code for occupancy. A structural (shell & core) major T.I. has been submitted under BLD15-03345. Work to include new walk-in cooler, food storage, new dining room, interior finish, mechanical work, plumbing work, electrical work and fire sprinkler work.
|
Intake Approval | | | 9/23/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen and plan review fees paid.
|
Application received | | | 9/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 18 2015 6:06PM
|