Third Notice | | 1/16/2017 | 2/13/2017 | | DONE |
Christina Prado
|
|
|
Called and spoke to Dan - FInal value for TI is combined with Shell & Core. Final certificate for both permits attached and values verified
|
Third Notice | | 12/17/2016 | 1/11/2017 | | DONE |
|
|
|
|
Third Notice | | 11/22/2016 | 12/12/2016 | | DONE |
|
|
|
sent with a letter
|
Third Notice | | 10/15/2016 | 11/17/2016 | | DONE |
|
|
|
|
Third Notice | | 9/24/2016 | 10/10/2016 | | DONE |
|
|
|
|
Second Notice | | 8/22/2016 | 9/19/2016 | | DONE |
|
|
|
|
First Notice | 8/8/2016 | 8/8/2016 | 8/12/2016 | | DONE |
Carlos Velazquez
|
|
|
mailed 8-22-16
|
BLD-Final | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
DOC - Permit Finaled | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | PASS |
Mike Jordan
|
|
|
|
PubWorks Occupancy Approval | 8/5/2016 | 8/5/2016 | 8/5/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 8/3/2016 | 8/3/2016 | 8/3/2016 | | PASS |
Sarah Schafer
|
|
|
Bench chained to the bike rack MUST be moved. 2 bicycle parking spaces are not provided with the bench chained to the rack.
|
BLD-Conference | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PART |
Mike Jordan
|
|
|
All other inspections have been performed. Owner posted landscape bond as per zoning temporary sign off requirements. Phone #: ###-#### Inspection requested via web by Antonio Carone. Ok for temp. occ. Will be ok for perm occ. once zoning and public works signs perm.
|
PubWorks Temp Occupancy Appr | 6/8/2016 | 6/8/2016 | 6/8/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 6/8/2016 | 6/8/2016 | 6/8/2016 | | PASS |
Josh Wilson
|
|
|
180 day ok- landscape bond in place
|
BLD-Final | 6/6/2016 | 6/6/2016 | 6/7/2016 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
FIRE-Final Inspection | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide address numbers facing the street, as discussed, prior to a building inspection.
|
Plan assigned to (CDM) | 5/24/2016 | 5/24/2016 | 6/3/2016 | | DONE |
Carl D Madsen
|
|
|
Plan mod should have been under BLD15-04511
|
Routing - PLAN CHECK | 5/24/2016 | | 6/3/2016 | | PASS |
Carl D Madsen
|
|
|
Plan mod should have been under BLD15-04511
|
Routing PW Solid Waste | 5/24/2016 | | 6/3/2016 | | PASS |
Peter J. McCullough
|
|
|
Need more information on modification prior to passing PW. NO CHANGE IN MOD FROM WHEN PASSED BY MD
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2016 | | DONE |
Christina Prado
|
|
|
Plan mod should have been under BLD15-04511
|
CHANGE STATUS TO (ISS) | | | 6/3/2016 | | DONE |
Christina Prado
|
|
|
Plan mod should have been under BLD15-04511
|
Routing - PUBLIC WORKS | 5/24/2016 | | 5/26/2016 | | PASS |
Rachael Beierle
|
|
|
NO CHANGE IN SOLID WASTE. PASS VIA PW
|
Routing PW Sewer Rating | 5/24/2016 | | 5/24/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plan Modification Accepted | | | 5/24/2016 | | DONE |
Christina Prado
|
|
|
For minor revisions as per Tom WIlliams
|
BLD-Conference | 4/29/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Mike Jordan
|
|
|
I will not be onsite this morning. I have dry wallers waiting to hang. Please send me a text or voice mail with the status. Thank you Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Final | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Framing/Rough-in | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Wall Bracing | 3/31/2016 | 3/31/2016 | 3/31/2016 | P | PASS |
Mike Jordan
|
|
|
Sheer inspection Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Framing/Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Mike Jordan
|
|
|
Roof nail inspection request for approval to cover. Phone #: ###-#### Inspection requested via web by Antonio Carone
|
CHANGE STATUS TO (ISS) | | | 2/18/2016 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 2/16/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 1/28/2016 | 1/28/2016 | 2/16/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/16/2016 | | DONE |
Christina Prado
|
|
|
Plam Mod approved - All requirements met for Plan Mod
DO NOT RE-ISSUE - Must pay all remaining fees prior to changing status to ISS
|
Routing - PLANNING | 2/10/2016 | | 2/12/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 2/10/2016 | | 2/10/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 1/28/2016 | | 2/2/2016 | | FAIL |
Carl D Madsen
|
|
|
|
BLD-Footing | 1/27/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Jim Sly
|
|
|
Have concrete scheduled for 1:00pm. We would like to be as close to 12:00pm as possible with the inspection for footings. Phone #: ###-#### Inspection requested via web by Antonio Carone
No special insp req. besides soil. Footing OK.
|
Plan Modification Accepted | | | 1/28/2016 | | DONE |
|
|
|
modifications to include; landscape plan, roof layout, elevations
|
BLD-Conference | 1/27/2016 | 1/27/2016 | 1/27/2016 | A | DEFR |
Mike Jordan
|
|
|
Per structural engineer for the project David Sansotta, no special inspections required for the 1500 psf minimum bearing pressures soil however he requested that the city inspector verify the conditions are acceptable. Footings are excavated and the soil appears to meet or exceed the allowable requirements. Request a conference to confer with inspector. Call Antonio Carone with questions. Phone #: ###-#### Inspection requested via web by Antonio Carone. No geo-tech report for project. Project site has had 2ft. to 3ft. of uncontrolled fill from previous construction to the south. Also noted construction debries within the building pad site and excavated footings. Noted to contractor that a sub grade inspection would be required by a geo-tech engineer.
|
Issue PAID IN FULL permit | | | 1/22/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 1/7/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 1/7/2016 | | DONE |
Christina Prado
|
|
|
***req met Candy has scans***Need RP, GC form & Revised certificate of value for issuance
DO NOT ISSUE WITHOUT BLD15-034511 & BLD15-04512
|
Plan assigned to (CDM) | 10/13/2015 | 10/13/2015 | 1/6/2016 | | PASS |
Carl D Madsen
|
|
|
New Commercial - ePlanReview - Cattle Kate First and second reviews completed
|
Routing - PLAN CHECK | 12/21/2015 | | 1/6/2016 | | PASS |
Carl D Madsen
|
|
|
Failed pending Solid waste approval
|
Routing PW Solid Waste | 1/6/2016 | | 1/6/2016 | | PASS |
Megan Durrell
|
|
|
Site is limited to trash/recycle carts (max 4 trash carts). No dumpster allowed from this enclosure location.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2016 | | DONE |
|
|
|
|
Routing PW Solid Waste | 12/22/2015 | | 12/24/2015 | | FAIL |
Megan Durrell
|
|
|
Trash enclosure does not meet requirements (notified 3x). Service is not possible from proposed location. Must have 50 feet backing distance. http://curbit.cityofboise.org/media/2299/CommercialEnclosureRequirements.pdf
|
Routing - Design Review | 12/22/2015 | | 12/22/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 10/13/2015 | | 12/22/2015 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 11/18/2015 | 11/21/2015 | 11/19/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 10/13/2015 | | 11/18/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/13/2015 | | 11/18/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 11/18/2015 | | FAIL |
|
|
|
|
Routing PW Solid Waste | 10/13/2015 | | 10/29/2015 | | FAIL |
Peter J. McCullough
|
|
|
Trash enclosure does not meet requirements - access to the dumpster is restricted and backing distance does not meet 50' requirement. Enclosure should be 12'x12' interior dimensions and gates must swing open 120-degrees.
|
Routing PW Drainage | 10/13/2015 | | 10/22/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 10/13/2015 | | 10/19/2015 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - FIRE | 10/13/2015 | 10/13/2015 | 10/13/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - Addressing | 10/13/2015 | | 10/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 10/13/2015 | | 10/13/2015 | | PASS |
Evan Jenkins
|
|
|
(CATTLE KATE) The project owner / tenant of approximately half of the building, Cattle Kate is a business that custom creates and manufactures late 1800’s period western wear clothing as well as accessories sales.
|
Routing PW Sewer Rating | 10/13/2015 | | 10/13/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Sewer Design | 10/13/2015 | | 10/13/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PLANNING Land Div | 10/13/2015 | | 10/13/2015 | | PASS |
Dave Abo
|
|
|
Lot 5, Block 1 of Keeneland Park Subdivision.
|
Routing - Design Review | 10/13/2015 | | 10/13/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00348
|
Pending Assignment by JCB | 10/13/2015 | | 10/13/2015 | | DONE |
Jason Blais
|
|
|
First review completed
|
Intake Approval | | | 10/12/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Javier Guzman and plan review fees paid.
|
Intake Approval | | | 10/9/2015 | | FAIL |
Javier Guzman
|
|
|
Please provide the following: (Incomplete submittals will not be accepted)
• Form #304 – Registered Design Professional have owner sign document
• Form #310 – Statement of Special Inspections fill out all information on form completely and have owner sign document
|
Application received | | | 9/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 25 2015 1:59PM
|
Routing Off Site - STRUCTURAL | 12/21/2015 | | | | |
|
|
|
|