BLD-Final | 6/27/2016 | 6/28/2016 | 6/28/2016 | A | DONE |
Tony Young
|
|
|
Travis Phone #: ###-####
|
DOC - Permit Finaled | 6/28/2016 | 6/28/2016 | 6/28/2016 | P | PASS |
Tony Young
|
|
|
c of o issued
|
Issue PAID IN FULL permit | | | 6/27/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/16/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 6/6/2016 | 6/6/2016 | 6/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/7/2016 | | 6/16/2016 | | PASS |
Brian McGowan
|
|
|
Jason received the required information.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/16/2016 | | DONE |
|
|
|
PLAN MOD
|
PubWorks Occupancy Approval | 6/15/2016 | 6/15/2016 | 6/15/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
Routing PW Grading-Hillside | 6/7/2016 | | 6/15/2016 | | PASS |
Jason C. Taylor
|
|
|
|
BLD-Final | 6/7/2016 | 6/7/2016 | 6/10/2016 | P | PART |
Tony Young
|
|
|
call ahead for access; Jaysen Phone #: ###-####,, gave paperwork for bank purposes
|
Plan Modification Accepted | | | 6/6/2016 | | DONE |
Christina Prado
|
|
|
For changes to grading plan
|
BLD-Energy code compliance | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####,, ok to insulate walls
|
BLD-Framing/Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PART |
Tony Young
|
|
|
Jason Phone #: ###-####,, frame portion ok,, just need sprinklers passed,,
|
BLD-Framing/Rough-in | 3/21/2016 | 3/22/2016 | 3/22/2016 | P | CANC |
Tony Young
|
|
|
Jaysen Phone #: ###-####
|
BLD-Framing/Rough-in | 3/18/2016 | 3/18/2016 | 3/18/2016 | P | NR |
Tony Young
|
|
|
Travis Phone #: ###-####,, need sprinklers 1st,, walk through only
|
BLD-Wall Bracing | 3/10/2016 | 3/11/2016 | 3/11/2016 | A | PASS |
Phil Shearer
|
|
|
Travis Phone #: ###-####
|
BLD-Foundation | 12/30/2015 | 12/31/2015 | 12/31/2015 | A | PART |
Tony Young
|
|
|
Travis; Phone #: ###-####,, heat and tenting in place
|
BLD-Wall Bracing | 12/28/2015 | 12/28/2015 | 12/28/2015 | P | PART |
Tony Young
|
|
|
Travis Phone #: ###-####,, this was for a foundation,, basement and stem walls,, ok but too cold to pour without tenting and heating
|
BLD-Footing | 12/23/2015 | 12/23/2015 | 12/23/2015 | P | PASS |
Tony Young
|
|
|
Travis Phone #: ###-####
|
PubWorks Subgrade Approval | 12/23/2015 | 12/23/2015 | 12/23/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 12/16/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/16/2015 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 12/16/2015 | | |
|
|
|
|
OVERRIDE | | | 12/3/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 10/29/2015 | 10/29/2015 | 12/3/2015 | | DONE |
Brian McGowan
|
|
|
due 11/17 L2 ePlan. 1st Review Completed, Failed. 11-12-15
Engineering calculations required. Additional structural information needed.
|
Routing - PLAN CHECK | 12/3/2015 | | 12/3/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 12/3/2015 | | 12/3/2015 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2015 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 12/3/2015 | | 12/3/2015 | | PASS |
Jim Wyllie
|
|
|
Per ePlan approval 12/3/15. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Permit Ready to Issue | | | 12/3/2015 | | DONE |
|
|
|
***ALL REQUIRMENTS MET 12-16-15 /CEVneed GC and RP
|
Routing - FIRE | 11/30/2015 | 11/30/2015 | 11/30/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - PLANNING | 11/30/2015 | | 11/30/2015 | | PASS |
David Moser
|
|
|
|
Telephone call | | | 11/19/2015 | | DONE |
|
|
|
owner wanted to let us know that they will not be getting GRD since weather has gotten worse. Just going to wait until they get the BLD
|
Routing - PLANNING | 11/17/2015 | | 11/17/2015 | | FAIL |
David Moser
|
|
|
Need copy of the ACHD license agreement and/or approvals for the improvements located within the ACHD Storm Water & Drainage Easement.
|
1st review completed | | | 11/12/2015 | | FAIL |
Brian McGowan
|
|
|
Engineering calculations required. Additional structural information needed.
|
Routing - PLAN CHECK | 11/12/2015 | | 11/12/2015 | | FAIL |
Brian McGowan
|
|
|
Engineering calculations required. Additional structural information needed.
|
Routing - MECHANICAL | 11/9/2015 | | 11/9/2015 | | PASS |
Troy James
|
|
|
|
Telephone call | | | 11/4/2015 | | DONE |
Katie Marron
|
|
|
Plans examiner spoke with owner (Rich Brown) this morning and the owner indicated that the structure will be fire sprinkered as an alternative to the Fire Code deficiencies. Owner will submit a formal reply to the plan review report.
|
Routing PW Grading-Hillside | 11/4/2015 | | 11/4/2015 | | FAIL |
Jason C. Taylor
|
|
|
see changemark in eplan. JCT
|
Plan assigned to (LEG) Tisha | 10/27/2015 | | 10/29/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 10/27/2015 | | 10/29/2015 | | FAIL |
Troy James
|
|
|
emailed corrections to building energy
|
Routing - FIRE | 10/27/2015 | 10/27/2015 | 10/28/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to case and emailed to applicant.
|
Plans ACCEPTED BY PLAN TECH | | | 10/27/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/27/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/27/2015 | | DONE |
|
|
|
|
Routing - PLANNING | 10/27/2015 | | 10/27/2015 | | FAIL |
David Moser
|
|
|
need to wait for CFH15-00056 appeal period and ACHD approval for improvements in their easement.
|
Routing - Addressing | 10/27/2015 | | 10/27/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/27/2015 | | 10/27/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 10/27/2015 | | 10/27/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Permit for the construction of a new 2,463 sq. ft., two story (first floor 1,543 sq. ft., second floor 920 sq. ft.) single family dwelling with 3 bedrooms, 2 and a half bathrooms, approximately 291 sq. ft. of covered patio/porch and a 1,479 sq. ft. attached garage
|
Application received | | | 9/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 30 2015 12:18PM
|