Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-03560
StatusFinaled
Name CORE BUILDING COMPANY
Site Address 2602 N HARRISON HILLS DR
Project NameBrown Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A. Permit for the construction of a new 2,463 sq. ft., two story (first floor 1,543 sq. ft., second floor 920 sq. ft.) single family dwelling with 3 bedrooms, 2 and a half bathrooms, approximately 461 sq. ft. of covered patio/porch and a 1,479 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1B zoning and setbacks per planning. This residence is required to be fire sprinklered in accordance with NFPA 13D. A separate fire sprinkler permit will be required; as regulated by the Fire Department. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/27/20166/28/20166/28/2016ADONE
DetailsTony Young
Travis Phone #: ###-####
DOC - Permit Finaled6/28/20166/28/20166/28/2016PPASS
DetailsTony Young
c of o issued
Issue PAID IN FULL permit  6/27/2016 DONE
OVERRIDE  6/16/2016  
Plan assigned to (BJM)6/6/20166/6/20166/16/2016 DONE
DetailsBrian McGowan
Routing - PLAN CHECK6/7/2016 6/16/2016 PASS
DetailsBrian McGowan
Jason received the required information.
PLANS/APPL TAKEN TO FRONT DESK  6/16/2016 DONE
DetailsBrian McGowan
Permit Ready to Issue  6/16/2016 DONE
PLAN MOD
PubWorks Occupancy Approval6/15/20166/15/20166/15/2016 DONE
DetailsJason C. Taylor
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
Routing PW Grading-Hillside6/7/2016 6/15/2016 PASS
DetailsJason C. Taylor
BLD-Final6/7/20166/7/20166/10/2016PPART
DetailsTony Young
call ahead for access; Jaysen Phone #: ###-####,, gave paperwork for bank purposes
Plan Modification Accepted  6/6/2016 DONE
DetailsChristina Prado
For changes to grading plan
BLD-Energy code compliance3/31/20164/1/20164/1/2016APASS
DetailsTony Young
Jason Phone #: ###-####
BLD-Framing/Rough-in3/28/20163/29/20163/29/2016APASS
DetailsTony Young
Jason Phone #: ###-####,, ok to insulate walls
BLD-Framing/Rough-in3/24/20163/25/20163/25/2016APART
DetailsTony Young
Jason Phone #: ###-####,, frame portion ok,, just need sprinklers passed,,
BLD-Framing/Rough-in3/21/20163/22/20163/22/2016PCANC
DetailsTony Young
Jaysen Phone #: ###-####
BLD-Framing/Rough-in3/18/20163/18/20163/18/2016PNR
DetailsTony Young
Travis Phone #: ###-####,, need sprinklers 1st,, walk through only
BLD-Wall Bracing3/10/20163/11/20163/11/2016APASS
DetailsPhil Shearer
Travis Phone #: ###-####
BLD-Foundation12/30/201512/31/201512/31/2015APART
DetailsTony Young
Travis; Phone #: ###-####,, heat and tenting in place
BLD-Wall Bracing12/28/201512/28/201512/28/2015PPART
DetailsTony Young
Travis Phone #: ###-####,, this was for a foundation,, basement and stem walls,, ok but too cold to pour without tenting and heating
BLD-Footing12/23/201512/23/201512/23/2015PPASS
DetailsTony Young
Travis Phone #: ###-####
PubWorks Subgrade Approval12/23/201512/23/201512/23/2015 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  12/16/2015 DONE
Inspection Record Card- Bld  12/16/2015 DONE
CHANGE ISSUED DATE  12/16/2015  
OVERRIDE  12/3/2015  
Plan assigned to (BJM)10/29/201510/29/201512/3/2015 DONE
DetailsBrian McGowan
due 11/17 L2 ePlan. 1st Review Completed, Failed. 11-12-15
Engineering calculations required. Additional structural information needed.
Routing - PLAN CHECK12/3/2015 12/3/2015 PASS
DetailsBrian McGowan
Routing - PLAN CHECK12/3/2015 12/3/2015 PASS
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  12/3/2015 DONE
Routing PW Grading-Hillside12/3/2015 12/3/2015 PASS
DetailsJim Wyllie
Per ePlan approval 12/3/15. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Permit Ready to Issue  12/3/2015 DONE
***ALL REQUIRMENTS MET 12-16-15 /CEVneed GC and RP
Routing - FIRE11/30/201511/30/201511/30/2015 PASS
DetailsScott Arellano
Attached comments to plans.
Routing - PLANNING11/30/2015 11/30/2015 PASS
DetailsDavid Moser
Telephone call  11/19/2015 DONE
owner wanted to let us know that they will not be getting GRD since weather has gotten worse. Just going to wait until they get the BLD
Routing - PLANNING11/17/2015 11/17/2015 FAIL
DetailsDavid Moser
Need copy of the ACHD license agreement and/or approvals for the improvements located within the ACHD Storm Water & Drainage Easement.
1st review completed  11/12/2015 FAIL
DetailsBrian McGowan
Engineering calculations required. Additional structural information needed.
Routing - PLAN CHECK11/12/2015 11/12/2015 FAIL
DetailsBrian McGowan
Engineering calculations required. Additional structural information needed.
Routing - MECHANICAL11/9/2015 11/9/2015 PASS
DetailsTroy James
Telephone call  11/4/2015 DONE
DetailsKatie Marron
Plans examiner spoke with owner (Rich Brown) this morning and the owner indicated that the structure will be fire sprinkered as an alternative to the Fire Code deficiencies. Owner will submit a formal reply to the plan review report.
Routing PW Grading-Hillside11/4/2015 11/4/2015 FAIL
DetailsJason C. Taylor
see changemark in eplan. JCT
Plan assigned to (LEG) Tisha10/27/2015 10/29/2015 DEFR
DetailsTisha Gallop
Routing - MECHANICAL10/27/2015 10/29/2015 FAIL
DetailsTroy James
emailed corrections to building energy
Routing - FIRE10/27/201510/27/201510/28/2015 FAIL
DetailsScott Arellano
Comments attached to case and emailed to applicant.
Plans ACCEPTED BY PLAN TECH  10/27/2015 DONE
Intake Approval  10/27/2015 PASS
Recd Pcfee & Taken To Pln CK  10/27/2015 DONE
Routing - PLANNING10/27/2015 10/27/2015 FAIL
DetailsDavid Moser
need to wait for CFH15-00056 appeal period and ACHD approval for improvements in their easement.
Routing - Addressing10/27/2015 10/27/2015 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS10/27/2015 10/27/2015 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment10/27/2015 10/27/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

Permit for the construction of a new 2,463 sq. ft., two story (first floor 1,543 sq. ft., second floor 920 sq. ft.) single family dwelling with 3 bedrooms, 2 and a half bathrooms, approximately 291 sq. ft. of covered patio/porch and a 1,479 sq. ft. attached garage
Application received  9/30/2015 DONE
Application submitted via PDS Online on Sep 30 2015 12:18PM