Permit Information
Permit NumberBLD15-03566
StatusFinaled
Name CULPAN & COMPANY
Site Address 386 N STRATA VIA PL
Project NameMcbeath
Customer Number 
ePlanReviewYes
Description
WUI Zone A; Permit for the construction of a new 4470 sq. ft., two story (first story 3036 sq. ft., second story 1488 sq. ft.) single family dwelling with 4 bedrooms, 4 bathrooms and 2 half bathrooms, approximately 944 sq. ft. of covered patio/porch and a 968 sq. ft. attached garage per the approved plans, plan review report and any notations. A-1 zoning and setbacks per planning. //LEG A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/31/201610/31/201610/31/2016PPASS
DetailsDave Hannah
Clive Phone #: ###-####
DOC - Permit Finaled10/31/201610/31/201610/31/2016PPASS
DetailsDave Hannah
BLD-Final10/25/201610/26/201610/26/2016AFAIL
DetailsDave Hannah
Doug Phone #: ###-#### c/n on site
PubWorks Occupancy Approval10/17/201610/17/201610/17/2016 DONE
DetailsJason C. Taylor
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
BLD-Aging Inspection9/21/20169/21/20169/22/2016 PEND
DetailsDave Hannah
BLD-Aging Inspection9/22/20169/22/20169/22/2016 PEND
DetailsDave Hannah
BLD-Energy code compliance5/9/20165/10/20165/10/2016APASS
DetailsDave Hannah
Clive Phone #: ###-####
BLD-Wall Bracing5/5/20165/5/20165/5/2016PPASS
DetailsDave Hannah
BLD-Framing/Rough-in5/4/20165/5/20165/5/2016APASS
DetailsDave Hannah
Clive Phone #: ###-####
Plan Modification Accepted  4/25/2016 DONE
new manual j report
Routing - MECHANICAL4/25/2016 4/25/2016 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing4/15/20164/18/20164/18/2016PFAIL
DetailsJim Storey
Clive Phone #: ###-#### c/n posted
BLD-Wall cover4/13/20164/14/20164/14/2016ANR
DetailsDave Hannah
Clive Phone #: ###-####
BLD-Foundation12/2/201512/3/201512/3/2015APASS
DetailsDave Hannah
Pat Phone #: ###-####
BLD-Footing11/24/201511/24/201511/24/2015PPASS
DetailsDave Hannah
Pat Phone #: ###-####
PubWorks Subgrade Approval11/24/201511/24/201511/24/2015 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  11/10/2015 DONE
Inspection Record Card- Bld  11/10/2015 DONE
OVERRIDE  11/6/2015  
Plan assigned to (DAF)10/23/201510/23/201511/6/2015 DONE
DetailsDavid Ferguson
due 11/5 L2 ePlan / Troy failed mechanical-wait for resubmittal
PLANS/APPL TAKEN TO FRONT DESK  11/6/2015 DONE
Permit Ready to Issue  11/6/2015 DONE
requirements met
Routing - MECHANICAL10/15/2015 11/6/2015 PASS
DetailsTroy James
1st review completed  11/3/2015 DONE
DetailsDavid Ferguson
Routing - PLAN CHECK10/15/2015 11/3/2015 PASS
DetailsDavid Ferguson
Plan assigned to (LEG) Tisha10/15/2015 10/23/2015 DEFR
DetailsTisha Gallop
Routing PW Grading-Hillside10/15/2015 10/19/2015 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.

Routing - FIRE10/15/201510/15/201510/15/2015 PASS
DetailsKatie Marron
Reviewed for fire department vehicle access and hydrant availability. Fire Sprinklers and NOT REQUIRED for Nativa Terra Sub 3 Block 4 Lot 10.
Routing - PLANNING10/15/2015 10/15/2015 PASS
DetailsColleen T Carroll
Routing - Addressing10/15/2015 10/15/2015 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS10/15/2015 10/15/2015 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment10/15/2015 10/15/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

Permit for the construction of a new 4470 sq. ft., two story (first story 3036 sq. ft., second story 1488 sq. ft.) single family dwelling with 4 bedrooms, 4 bathrooms and 2 half bathrooms, approximately 944 sq. ft. of covered patio/porch and a 968 sq. ft. attached garage
Plans ACCEPTED BY PLAN TECH  10/15/2015 DONE
Intake Approval  10/15/2015 PASS
Recd Pcfee & Taken To Pln CK  10/15/2015 DONE
Intake Approval  10/6/2015 FAIL
needs grading and drainage plans
Intake Approval  10/6/2015 FAIL
DetailsCandy A. Nichols
still need grading and drainage plans uploaded
Application received  9/30/2015 DONE
Application submitted via PDS Online on Sep 30 2015 3:08PM