BLD-Final | 6/23/2016 | 6/23/2016 | 6/23/2016 | P | PASS |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
DOC - Permit Finaled | 6/23/2016 | 6/23/2016 | 6/23/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Jim Storey
|
|
|
Insulation // Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 3/8/2016 | 3/8/2016 | 3/8/2016 | P | PASS |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 3/3/2016 | 3/4/2016 | 3/4/2016 | A | PART |
Phil Shearer
|
|
|
Bob Phone #: ###-####. Nailling at T16 3 ply girder/ clips needed in garage.
|
BLD-Energy code compliance | 2/25/2016 | 2/26/2016 | 2/26/2016 | P | NR |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 2/25/2016 | 2/26/2016 | 2/26/2016 | P | PART |
Jim Storey
|
|
|
Bob Phone #: ###-#### missing bracing on webs/ nailling at 3 ply/ clips need verified at exterior/ bearing for hangers/ cluster nailling at 3 ply
|
BLD-Wall Bracing | 1/27/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####,, exterior ok
|
Plan Modification Accepted | | | 1/12/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/12/2016 | | 1/12/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 11/23/2015 | 11/23/2015 | 11/23/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 11/18/2015 | 11/18/2015 | 11/18/2015 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 11/6/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/6/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/4/2015 | | |
|
|
|
|
Routing PW Sewer Rating | 11/4/2015 | | 11/4/2015 | | PASS |
Beverly Mountain
|
|
|
|
Permit Ready to Issue | | | 11/4/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (BJM) | 10/7/2015 | 10/7/2015 | 11/3/2015 | | DONE |
Brian McGowan
|
|
|
due 10/20 ePlan. 1st review complete. Failed for structure verification
|
Routing - PLAN CHECK | 11/3/2015 | | 11/3/2015 | | PASS |
Javier Guzman
|
|
|
Brian did review, showed Brian the information on the sprayed foam in the crawl space with a ignition barrier requirements or fire damper option
|
Routing - PLAN CHECK | 11/3/2015 | | 11/3/2015 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2015 | | DONE |
|
|
|
|
Routing - PLANNING | 10/6/2015 | | 11/3/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 10/6/2015 | | 10/22/2015 | | FAIL |
Brian McGowan
|
|
|
Need structural verification of 2x12 rafters
|
1st review completed | | | 10/22/2015 | | FAIL |
Brian McGowan
|
|
|
Need structure verified for 2x12 rafters
|
Routing - MECHANICAL | 10/6/2015 | | 10/8/2015 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/6/2015 | 10/9/2015 | 10/7/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (LEG) Tisha | 10/6/2015 | | 10/7/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - PUBLIC WORKS | 10/6/2015 | | 10/7/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 10/6/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/6/2015 | | DONE |
|
|
|
|
Routing - Addressing | 10/6/2015 | | 10/6/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 10/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 2 2015 4:51PM
|