Permanent Occupancy | | | 7/13/2016 | | DONE |
|
|
|
|
BLD-Final | 6/27/2016 | 6/28/2016 | 6/28/2016 | P | PASS |
Tony Young
|
|
|
Tj Phone #: ###-####,, ok for occupancy pending others
|
BLD-Conference | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | NR |
Tony Young
|
|
|
Tj Phone #: ###-####,, needs zoning,, address #s, occupancy posting
|
FIRE-Final Inspection | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags, commercial hood is type II hood, a fire suppression sustem is not required. Exterior egress lights will be re-installed after stucco is completed. Final life fire safety inspection passed/complete
|
Zoning Approval | 6/27/2016 | 6/27/2016 | 6/27/2016 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Wall cover | 4/22/2016 | 4/25/2016 | 4/25/2016 | A | PASS |
Tony Young
|
|
|
TJ Phone #: ###-####,, ok to cover now
|
BLD-Framing/Rough-in | 4/20/2016 | 4/21/2016 | 4/21/2016 | P | PASS |
Tony Young
|
|
|
TJ Phone #: ###-####,, ok to sheet rock
|
BLD-Framing/Rough-in | 4/19/2016 | 4/20/2016 | 4/20/2016 | P | PART |
Tony Young
|
|
|
TJ Phone #: ###-####,, need to fireblock a few areas,, ok to start sheetrocking the lid,, will need to see more of the new cut in doors in the rear side wall
|
Telephone call | | | 4/18/2016 | | DONE |
|
|
|
Spoke with Eric of Modus Architects reqarding smoke detection requirements. I informed him that based on the occupancy and occupant load that they will not be required.
|
BLD-Wall cover | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PART |
Tony Young
|
|
|
TJ Phone #: ###-####,, rear south fire wall above ceiling ok,, ok to insulate pending trades
|
BLD-Wall cover | 3/23/2016 | 3/25/2016 | 3/25/2016 | A | DEFR |
Tony Young
|
|
|
TJ Phone #: ###-####
|
BLD-Framing/Rough-in | 3/22/2016 | 3/23/2016 | 3/23/2016 | P | PART |
Tony Young
|
|
|
TJ Phone #: ###-####,, 1st layer of south firewall ok,, ok to start 2nd layer
|
BLD-Framing/Rough-in | 3/22/2016 | 3/22/2016 | 3/22/2016 | P | PART |
Tony Young
|
|
|
TJ Phone #: ###-####,, south/west wall 1st layer 5/8" sheet rock,, work in place,, ok,, remainder of framing ok
|
CHANGE STATUS TO (ISS) | | | 3/22/2016 | | DONE |
|
|
|
plan mod
|
(F) Reprint permit | | | 3/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/15/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 3/9/2016 | 3/9/2016 | 3/15/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Plan Mod. North End Pizza
|
Routing - PLAN CHECK | 3/11/2016 | | 3/15/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
CLOSED CELL INSULATIONS
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/15/2016 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE - Plan Mod approved and all requirements met
**Must pay all fees prior to inspections and changing status to ISS
|
Routing - FIRE | 3/11/2016 | 3/11/2016 | 3/11/2016 | | PASS |
Katie Marron
|
|
|
Review for approved alternate rated wall/ceiling assemblies. Updated report attached to case.
|
Plan Modification Accepted | | | 3/9/2016 | | DONE |
Christina Prado
|
|
|
Plan mod requested to add details for moisture control above ceiling
|
OVERRIDE | | | 3/7/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 2/19/2016 | 2/19/2016 | 3/7/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Plan Mod. - North End Pizza
|
CHANGE STATUS TO (ISS) | | | 3/7/2016 | | DONE |
|
|
|
Plan mod
|
(F) Reprint permit | | | 3/7/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/7/2016 | | 3/7/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
sent back to architect to upload latest revised drawing per their request.
|
Routing - PLAN CHECK | 3/7/2016 | | 3/7/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan mod for rated wall modification and ul rating ceiling
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/7/2016 | | DONE |
|
|
|
DO NOT RE-ISSUE - Plan Mod approved and all requirements met
**Must pay all fees prior to inspections and changing status to ISS
|
Plan Reviewer's activity | | | 2/26/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
routed alternate to BO, Fire Marshal
|
BLD-Conference | 2/24/2016 | 2/24/2016 | 2/24/2016 | P | PART |
Tony Young
|
|
|
fireblocking; TJ Phone #: ###-####,, fire wall block backing,, work in progress,, ok so far south side
|
BLD-Conference | 2/17/2016 | 2/24/2016 | 2/24/2016 | A | PART |
Tony Young
|
|
|
would like call ahead; TJ Phone #: ###-####,, architect meeting with plan review
|
Routing - PLAN CHECK | 2/22/2016 | | 2/24/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
met with Bruce Poe, he will uploade additioal information on 2 hour wall, unvented attic space and revision to 1 hour ceiling, and plan mod writen letter.
|
BLD-Conference | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | PEND |
Tony Young
|
|
|
TJ Phone #: ###-####
|
Routing - FIRE | 2/22/2016 | 2/22/2016 | 2/22/2016 | | PASS |
Katie Marron
|
|
|
Modifications reviewed. Minor updates to previous comments were made and see revised report.
|
Plan Modification Accepted | | | 2/19/2016 | | DONE |
Christina Prado
|
|
|
Request to modify details for two hour party wall
|
BLD-Conference | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PART |
Tony Young
|
|
|
would like call ahead; TJ Phone #: ###-#### ,, opened up ceiling areas for horizontal firewall areas to start rebuilding backing,, ok so far
|
BLD-Conference | 2/9/2016 | 2/11/2016 | 2/11/2016 | A | PEND |
Tony Young
|
|
|
would like call ahead; TJ Phone #: ###-####
|
BLD-Conference | 2/8/2016 | 2/9/2016 | 2/9/2016 | P | PEND |
Tony Young
|
|
|
would like call ahead; TJ Phone #: ###-####, conf with Bruce Poe, architect on firewalls,, need to get detail to plan review
|
BLD-Conference | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | FAIL |
Jim Storey
|
|
|
TJ-please call to meet Phone #: ###-#### arch to provide 1 hr assembley and address drops that will not meet listing for roof assembly as well as conbustable space.
|
BLD-Conference | 1/7/2016 | 1/11/2016 | 1/11/2016 | A | PASS |
Tony Young
|
|
|
TJ Phone #: ###-####,, 2 hour wall ?s,, stuff with fire mineral wool,, then 2 layers of 5/8" rock,, fire caulk
|
Case Summary (BLD) | | | 12/21/2015 | | DONE |
|
|
|
Case summary printed in preparation for a general report and issuing a citation.
|
OVERRIDE | | | 12/1/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 10/8/2015 | 10/8/2015 | 12/1/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - North End Pizza TI
|
Print Occupancy Form | | | 12/1/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/1/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/1/2015 | | DONE |
|
|
|
NEED RP, GC form, and Certificate of value
|
Routing - Design Review | 11/18/2015 | | 11/30/2015 | | PASS |
Matthew A Halitsky
|
|
|
|
Routing - PLAN CHECK | 11/18/2015 | | 11/20/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 11/4/2015 | | 11/10/2015 | | FAIL |
Matthew A Halitsky
|
|
|
failed in e plan
|
Routing - MECHANICAL | 11/4/2015 | | 11/9/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 11/4/2015 | | 11/6/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 10/8/2015 | | 10/29/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLANNING | 10/8/2015 | | 10/29/2015 | | PASS |
Brent Moore
|
|
|
Brent Moore - CUP15-00078
|
Routing Off Site - C.D.H | 10/8/2015 | | 10/29/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
signed off in e plan Joe Antonucci
|
Routing PW Sewer Rating | 10/12/2015 | | 10/29/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Environmental | 10/12/2015 | | 10/29/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 10/12/2015 | | 10/29/2015 | | PASS |
Peter J. McCullough
|
|
|
Access to trash enclosure must be at least 13' wide with 15' overhead clearance. Actual conditions at location may limit available services.
|
1st review completed | | | 10/29/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 10/8/2015 | | 10/21/2015 | | FAIL |
Matthew A Halitsky
|
|
|
Matt Halitsky - DRH15-00374
Recessed entries shall be preserved.
|
Routing - MECHANICAL | 10/8/2015 | | 10/14/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 10/8/2015 | | 10/12/2015 | | PASS |
Bill VanDegrift
|
|
|
vent all traps
asse 1070 mixing valves required at all lavs and hand sinks
|
Routing - PUBLIC WORKS | 10/8/2015 | | 10/12/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - FIRE | 10/8/2015 | 10/8/2015 | 10/9/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case
|
Routing - Erosion and Sediment | 10/8/2015 | | 10/9/2015 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. No RP designated at time of application - need to designate licensed RP for ESC contact information.
|
Plan Reviewer's activity | | | 10/8/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD to determine if any additional impact fees are due. Our Permit Counter will need written verification from ACHD prior to the building permit being issued.
|
Routing - Addressing | 10/8/2015 | | 10/8/2015 | | PASS |
Emily Dixon
|
|
|
|
Pending Assignment by JCB | 10/8/2015 | | 10/8/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 10/7/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard and plan review fees paid.
|
Application received | | | 10/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 2 2015 5:32PM
|