First Notice | | 6/11/2016 | 6/1/2016 | | DONE |
|
|
|
|
Print Statement | | | 6/1/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 6/1/2016 | | DONE |
|
|
|
|
BLD-Final | 5/31/2016 | 6/1/2016 | 5/31/2016 | A | PASS |
Jim Sly
|
|
|
Ceasar Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 5/24/2016 | 5/24/2016 | 5/24/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete (FIR16-00278), final fire alarm inspection complete (FIR16-00307), final commercial hood suppression system inspection complete (FIR16-00250), fire extinguishers are on site with current inspection tags, discussed locations for fire extinguisher mounting after painting is complete. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 5/13/2016 | 5/13/2016 | 5/13/2016 | P | PASS |
Mike Jordan
|
|
|
Ceasar Phone #: ###-####
|
BLD-Framing/Rough-in | 4/26/2016 | 4/27/2016 | 4/27/2016 | P | PART |
Tony Young
|
|
|
Cesar-early of possible Phone #: ###-####,, walls,, hard lids,, soffit areas ok to cover where trades are approved
|
BLD-Framing/Rough-in | 4/22/2016 | 4/25/2016 | 4/26/2016 | P | PART |
Tony Young
|
|
|
would like call ahead; Ceasar Phone #: ###-####,, walls ok
|
BLD-Foundation | 4/14/2016 | 4/15/2016 | 4/15/2016 | A | PASS |
Mike Jordan
|
|
|
Cesar-rebar-would like at 10:oo if possible Phone #: ###-####. Trench infill ok.
|
BLD-Conference | 4/7/2016 | 4/8/2016 | 4/8/2016 | A | DONE |
Jim Sly
|
|
|
Cesar-please call with an estimate time Phone #: ###-####
|
Print Occupancy Form | | | 4/7/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/7/2016 | | DONE |
|
|
|
|
Telephone call | | | 3/22/2016 | | DONE |
|
|
|
talked to Tina-she meialed me the gc and rev cert and will git me the RP-emailed her the fees due
|
Extend Review Timeline | | | 3/14/2016 | | DONE |
|
|
|
1st 180 days granted by Jason B. See documents
|
Expiration Notice | 3/7/2016 | 3/28/2016 | 3/7/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 12/10/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 12/10/2015 | | 12/10/2015 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/10/2015 | | DONE |
|
|
|
***MET CAN 3/22/16*** Needs; GC Form, Revised Cert of Value, & RP
|
Plan assigned to (JG) | 10/20/2015 | | 12/10/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/12 Level 3 TI - ePlanReview - Smashburger
|
Routing PW Solid Waste | 11/17/2015 | | 12/1/2015 | | PASS |
Megan Durrell
|
|
|
signed off in ePlan by Megan Durrel
|
Routing - MECHANICAL | 11/18/2015 | | 11/18/2015 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 11/17/2015 | | 11/17/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 11/17/2015 | | 11/17/2015 | | PASS |
Evan Jenkins
|
|
|
**(SMASHBURGER)** Permit for new assembly restaurant tenant within an 1,808 sq. ft. area of vacant shell space of an existing building (Shell building constructed under BLD15-02398). Approval is contingent upon adhering to the approved plans on file. Work to include new interior nonbearing walls to create two ADA compliant restrooms, a kitchen area, a beverage area, a POS area, a queing area and interior and exterior dining areas,
|
Routing - PLAN CHECK | 11/17/2015 | | 11/17/2015 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 10/30/2015 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - Addressing | 10/30/2015 | | 10/30/2015 | | PASS |
Emily Dixon
|
|
|
Suite 130 added
|
Routing Off Site - C.D.H | 10/20/2015 | | 10/30/2015 | | PASS |
Javier Guzman
|
|
|
signed of in ePlan by Natasha Ferney of Central District Health in ePlan review
|
Routing - PLAN CHECK | 10/20/2015 | | 10/29/2015 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing PW Solid Waste | 10/20/2015 | | 10/29/2015 | | FAIL |
Peter J. McCullough
|
|
|
No trash enclosure. No site plan.
|
Routing - MECHANICAL | 10/20/2015 | | 10/26/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 10/20/2015 | | 10/26/2015 | | PASS |
Bill VanDegrift
|
|
|
Provide RPBP on filtered water system.
|
Routing - FIRE | 10/20/2015 | 10/20/2015 | 10/21/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Pending Assignment by JCB | 10/20/2015 | | 10/20/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Design Review | 10/20/2015 | | 10/20/2015 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH15-00302
|
Routing PW Sewer Rating | 10/20/2015 | | 10/20/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 10/20/2015 | | 10/20/2015 | | FAIL |
Emily Dixon
|
|
|
Need clear floor plan of entire building so I can assign a accurate suite number.
|
Routing - PUBLIC WORKS | 10/20/2015 | | 10/20/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 10/20/2015 | | 10/20/2015 | | FAIL |
Evan Jenkins
|
|
|
Due to Concrete Work and all Plumbing Work, ESC Permit Required. Please submit an ESC Waiver Letter Request for 2nd review and approval. Evan Jenkins 794.3958
|
Intake Approval | | | 10/19/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Dave Ferguson and plan review fees paid.
|
Intake Approval | | | 10/8/2015 | | FAIL |
David Ferguson
|
|
|
Jeff,
I couldn't find page E100 which you indicate on the Checklist shows the location of Exit signs and emergency lighting. Please upload this page or direct me to a page where these items can be found. As discussed on the phone yesterday, you had concerns about the district health applications. I am told that we will send those applications over to District Health for approval.
You also mentioned that you spoke to someone in our Planning & Zoning department and they said that the existing patio had prior approval. After viewing the patio plan sheet, it appears that you're also proposing a new fence. Has this been approved by our Planning department? It would expedite the processing of this application if you could provide us a letter of approval(Zoning Certification) from whomever you spoke with.
Lastly, you indicated on the checklist that you've uploaded form #304 - Registered Design Professional form but I can't find it. Please upload this form or direct me where it can be found in your submittal.
|
Intake Approval | | | 10/6/2015 | | FAIL |
|
|
|
Please fill out and upload form #520 - Major Tenant Improvement Submittal Checklist and required documents that are called out for on the checklist. It appears that you'll also need to submit the requirements for Central District Health Department as well as Planning & Zoning letters of approval (Zoning Certification)as indicated on the checklist.
|
Application received | | | 10/3/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 3 2015 8:33AM
|