BLD-Final | 3/23/2016 | 3/23/2016 | 3/23/2016 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Keath Bennett
|
DOC - Permit Finaled | 3/23/2016 | 3/23/2016 | 3/23/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 12/18/2015 | 12/21/2015 | 12/21/2015 | A | PASS |
Jim Storey
|
|
|
Keath Bennett is the contact on site Phone #: ###-#### Inspection requested via web by Keath Bennett
|
BLD-Wall Bracing | 12/1/2015 | 12/2/2015 | 12/2/2015 | A | PASS |
Jim Storey
|
|
|
Dan Phone #: ###-####
|
BLD-Footing | 10/26/2015 | 10/26/2015 | 10/26/2015 | P | PASS |
Jim Storey
|
|
|
2 pm - Shawn Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/21/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/20/2015 | | |
|
|
|
|
Routing - FIRE | 10/15/2015 | 10/15/2015 | 10/20/2015 | | PASS |
Scott Arellano
|
|
|
*Need site plan showing common driveway access* No plan review report attached.
*10/20/15 - Site plan verified through plat document. Visited site to verify access roadway and fire hydrant locations. -SJA
|
Plan assigned to (CDM) | 10/15/2015 | 10/15/2015 | 10/20/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 10/20/2015 | | 10/20/2015 | | PASS |
Sue Cummings
|
|
|
New site plan matches ROS Good to go now. SC
|
Routing - PLAN CHECK | 10/20/2015 | | 10/20/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/20/2015 | | DONE |
|
|
|
requirements met
|
1st review completed | | | 10/15/2015 | | FAIL |
|
|
|
|
Plan assigned to (LEG) Tisha | 10/5/2015 | | 10/15/2015 | | DEFR |
Tisha Gallop
|
|
|
10/19 eplan - Reassigned to Carl Madsen
|
Routing - PLAN CHECK | 10/5/2015 | | 10/15/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 10/13/2015 | | 10/13/2015 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 10/5/2015 | | 10/8/2015 | | FAIL |
Troy James
|
|
|
emailed corrections to western heating
|
Routing - PUBLIC WORKS | 10/5/2015 | | 10/6/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Telephone call | | | 10/5/2015 | | DONE |
|
|
|
called Keath back to let him know that the 3 credits for the 3 demo's on this parcel have been met. The parcel was split for a total of 6 lots. Only 3 credits for demo's will be givien-i let him know that he will have to pay ACHD, PRK & SWR on the remaining 3 lots- left message on his phone
|
Plans ACCEPTED BY PLAN TECH | | | 10/5/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/5/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/5/2015 | | DONE |
|
|
|
|
Routing - Addressing | 10/5/2015 | | 10/5/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 10/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 4 2015 11:50PM
|
Routing - PLANNING | 10/5/2015 | | | | FAIL |
|
|
|
Site plan and and ROS don't match
|