BLD-Aging Inspection | 9/8/2016 | 9/8/2016 | 9/9/2016 | | DONE |
Tony Young
|
|
|
|
BLD-Final | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | PASS |
Tony Young
|
|
|
Shane Phone #: ###-####
|
DOC - Permit Finaled | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by SHANE JAYO,,, needs fire caulking,, guard rail on master landing
|
BLD-Energy code compliance | 4/26/2016 | 4/27/2016 | 4/27/2016 | A | PASS |
Tony Young
|
|
|
Jodie ###-#### Shane Phone #: ###-####
|
BLD-Other | 4/20/2016 | 4/21/2016 | 4/21/2016 | A | PART |
Dave Hannah
|
|
|
soffit inspection Phone #: ###-#### Inspection requested via web by SHANE JAYO can lights boxs ok crew has started sheetrock
|
BLD-Framing/Rough-in | 4/20/2016 | 4/21/2016 | 4/21/2016 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by SHANE JAYO,, correction notice posted,, ok to insulate
|
BLD-Other | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | FAIL |
Tony Young
|
|
|
need firebox inspected for can lights in ext. soffits. Phone #: ###-#### Inspection requested via web by SHANE JAYO,, need electrical passed 1st
|
BLD-Foundation | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Wall Bracing | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | CANC |
Jim Sly
|
|
|
Derick Phone #: ###-####
|
BLD-Footing | 1/27/2016 | 1/28/2016 | 1/28/2016 | A | PART |
Tony Young
|
|
|
Derek Phone #: ###-####
|
BLD-Footing | 1/27/2016 | 1/27/2016 | 1/27/2016 | P | CANC |
Tony Young
|
|
|
Derek Phone #: ###-####
|
PubWorks Subgrade Approval | 12/7/2015 | 12/7/2015 | 12/7/2015 | | DONE |
Jason C. Taylor
|
|
|
***BASEMENT AND RESIDENCE FOOTINGS ONLY***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/17/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/28/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 10/14/2015 | 10/14/2015 | 10/28/2015 | | DONE |
Brian McGowan
|
|
|
due 10/27 L2
|
Inspection Record Card- Bld | | | 10/28/2015 | | DONE |
|
|
|
|
Telephone call | | | 10/28/2015 | | DONE |
|
|
|
called Shane- let him know permit is ready for pick up
|
Routing - PLAN CHECK | 10/28/2015 | | 10/28/2015 | | PASS |
David Ferguson
|
|
|
|
Permit Ready to Issue | | | 10/28/2015 | | DONE |
|
|
|
All Requirements Met
|
1st review completed | | | 10/27/2015 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 10/27/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | | | 10/27/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 10/7/2015 | | 10/27/2015 | | PASS |
Susan Riggs
|
|
|
|
Plan assigned to (LEG) Tisha | 10/12/2015 | | 10/14/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - FIRE | 10/9/2015 | | 10/12/2015 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - MECHANICAL | 10/7/2015 | | 10/9/2015 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 10/9/2015 | | 10/9/2015 | | PASS |
Andy J. Long
|
|
|
ESC site map and SWPPP narrative approved. Valid PD and RP designated. Site prep inspection required.
|
Routing PW Grading-Hillside | | | 10/7/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing - Addressing | 10/6/2015 | | 10/7/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 10/6/2015 | | 10/7/2015 | | PASS |
Beverly Mountain
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/6/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/6/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/6/2015 | | DONE |
|
|
|
|
Application received | | 10/5/2015 | | | |
|
|
|
|