BLD-Final | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | DONE |
Dave Hannah
|
|
|
Christina Phone #: ###-####
|
CHANGE STATUS TO (FNL) | | | 9/12/2017 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | CANC |
Jim Page
|
|
|
Duplicate inspection request.
|
FIRE-Final Inspection | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for this permit passed/complete
|
Zoning Approval | 6/27/2017 | 6/27/2017 | 6/27/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 3/28/2017 | 3/29/2017 | 3/30/2017 | A | PEND |
Dave Hannah
|
|
|
Want to walk with Dave to see if we can close out this permit as work has been done for some time Phone #: ###-#### Inspection requested via web by Joel Halfhill
|
BLD-Wall cover | 6/15/2016 | 6/17/2016 | 6/17/2016 | A | PART |
Dave Hannah
|
|
|
Shear // Joel Phone #: ###-#### ext penthouse ok to cover
|
BLD-Framing/Rough-in | 6/15/2016 | 6/17/2016 | 6/17/2016 | A | PART |
Dave Hannah
|
|
|
Joel Phone #: ###-#### ext penthouse
|
BLD-Other | 6/2/2016 | 6/3/2016 | 6/14/2016 | A | PART |
Dave Hannah
|
|
|
Joel// roof Phone #: ###-#### south side parapet
|
BLD-Wall Bracing | 5/27/2016 | 5/31/2016 | 6/1/2016 | P | PART |
Dave Hannah
|
|
|
Joel Phone #: ###-#### pareppit along 10th street ok
|
BLD-Framing/Rough-in | 4/14/2016 | 4/14/2016 | 4/15/2016 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Billy Williams
|
BLD-Framing/Rough-in | 3/21/2016 | 3/21/2016 | 3/24/2016 | P | PART |
Dave Hannah
|
|
|
Rough framing inspection and dicuss other inspections for other trades. Phone #: ###-#### Inspection requested via web by Billy Williams. I walked project with contractor looked at floor framing and floor sheeting nailing top floor
|
BLD-Conference | 3/6/2016 | 3/7/2016 | 3/8/2016 | P | PASS |
Dave Hannah
|
|
|
CMU and rebar inspection. Review Exterior plans and permit. Schedule an onsite inspection for 3-15-16 with City Inspector and Fire Department for Gurny Access to Elevator. Phone #: ###-#### Inspection requested via web by Billy Williams
|
BLD-Footing | 2/3/2016 | 2/4/2016 | 2/6/2016 | P | PEND |
Dave Hannah
|
|
|
Footing inspection in basement ladder access on site. Phone #: ###-#### Inspection requested via web by Billy Williams ok after spec/insp oks
|
BLD-Conference | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | DONE |
Dave Hannah
|
|
|
Discuss elevators and gurny access Phone #: ###-#### Inspection requested via web by Billy Williams
|
CHANGE STATUS TO (ISS) | | | 1/28/2016 | | DONE |
|
|
|
Plan Mod
|
(F) Reprint permit | | | 1/28/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 1/14/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 12/11/2015 | 12/11/2015 | 1/14/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) Athlos 1st plan mod
|
Routing - PLAN CHECK | 1/6/2016 | | 1/14/2016 | | PASS |
Carl Westfall
|
|
|
Structrual consultant approved
|
Routing Off Site - STRUCTURAL | 1/7/2016 | | 1/14/2016 | | PASS |
Carl Westfall
|
|
|
Jan Welch
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/14/2016 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE PLAN MOD ONLY
All requirements met for plan mod, all fees must be paid prior to changing status to ISS
|
Plan resubmittals received | | | 1/7/2016 | | DONE |
|
|
|
|
BLD-Conference | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | DONE |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Wall Bracing | 1/5/2016 | 1/5/2016 | 1/5/2016 | P | NR |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
Plan resubmittals requested | | | 12/23/2015 | | DONE |
Cheyne Weston
|
|
|
|
Routing - PLAN CHECK | 12/11/2015 | | 12/23/2015 | | FAIL |
Carl Westfall
|
|
|
Failed structural
|
Routing Off Site - STRUCTURAL | 12/14/2015 | | 12/22/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
BLD-Conference | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | DONE |
Dave Hannah
|
|
|
Would like to have a short meeting before we move forward with construction. Thanks Bill Williams Phone #: ###-#### Inspection requested via web by Billy Williams
|
Plan Modification Accepted | | | 12/11/2015 | | DONE |
|
|
|
submitting structural plans as per Ron Hill
|
Plan Modification Accepted | | | 12/11/2015 | | DONE |
|
|
|
Workflow received
|
Issue PAID IN FULL permit | | | 12/10/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/10/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 12/8/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 10/7/2015 | 10/7/2015 | 12/8/2015 | | PASS |
Carl Westfall
|
|
|
(1st done) ATHLOS ACADEMIES (Oct 26 - 15 days) Level 3 TI - ePlanReview
|
Routing - PLAN CHECK | 12/1/2015 | | 12/8/2015 | | PASS |
Carl Westfall
|
|
|
Approved after Code Modification letter was signed by the Building Official.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/8/2015 | | DONE |
Christina Prado
|
|
|
ALL REQUIRMENTS MET 12-10-15 Need GC, & Revised certificate of value for issuance
|
Plan resubmittals received | | | 12/1/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/24/2015 | | 11/25/2015 | | FAIL |
Carl Westfall
|
|
|
See changemarks on the drawings.
|
Plan resubmittals requested | | | 11/25/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/24/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/13/2015 | | 11/20/2015 | | FAIL |
Carl Westfall
|
|
|
One item not resolved. See the plan review report.
|
Routing Off Site - STRUCTURAL | 11/13/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
Jan Welch
|
Plan resubmittals requested | | | 11/20/2015 | | DONE |
|
|
|
|
Routing - Design Review | 11/13/2015 | | 11/16/2015 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 11/13/2015 | | DONE |
|
|
|
|
Route to Impact Fee Review | 11/2/2015 | 11/5/2015 | 11/4/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 11/2/2015 | | DONE |
|
|
|
|
1st review completed | | | 11/2/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/7/2015 | | 11/2/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 10/7/2015 | | 10/21/2015 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing - FIRE | 10/7/2015 | 10/7/2015 | 10/14/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Pending Assignment by JCB | 10/7/2015 | | 10/7/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Erosion and Sediment | 10/7/2015 | | 10/7/2015 | | PASS |
Evan Jenkins
|
|
|
(ATHLOS ACADEMIES - HEADQUARTERS) Structural upgrades to the existing building that include seismic upgrades, new ramp to basement level for new parking garage, addition of a new stair tower, and extension of the existing stair tower and elevator shaft.
|
Routing - Design Review | 10/7/2015 | | 10/7/2015 | | FAIL |
Andrea Tuning
|
|
|
The applicant is required to do a DR application.
|
Routing - Addressing | 10/7/2015 | | 10/7/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2015 | | 10/7/2015 | | PASS |
Jennifer Bruner
|
|
|
Proposing new parking garage in basement; No PW review required per Bev Mountain
|
Intake Approval | | | 10/6/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard and plan review fees paid.
|
Application received | | | 10/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 5 2015 5:17PM
|