Print Statement | | | 1/28/2016 | | DONE |
|
|
|
|
First Notice | | 12/14/2015 | 1/12/2016 | | DONE |
|
|
|
Mailed 1-13-16
|
Print Occupancy Form | | | 12/4/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/4/2015 | | DONE |
|
|
|
|
BLD-Final | 12/1/2015 | 12/2/2015 | 12/3/2015 | P | PASS |
Dave Hannah
|
|
|
Thanks Matt, Phone #: ###-#### Inspection requested via web by Richard Schultz
|
FIRE-Final Inspection | 12/1/2015 | 12/2/2015 | 12/2/2015 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete. Life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PASS |
Dave Hannah
|
|
|
Thanks Matt, Phone #: ###-#### Inspection requested via web by Richard Schultz
|
Inspection Record Card- Bld | | | 10/23/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/23/2015 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/7/2015 | 10/7/2015 | 10/9/2015 | | PASS |
Javier Guzman
|
|
|
Pending others for first review, L1 HH & Associates #380
|
1st review completed | | | 10/9/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/9/2015 | | DONE |
Christina Prado
|
|
|
***MET 10-23-15*** Need GC & Revised certificate of vlaue for issuance
|
Routing - PLAN CHECK | 10/7/2015 | | 10/8/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 10/7/2015 | | 10/8/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2015 | | 10/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 10/8/2015 | | 10/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 10/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 7 2015 12:19PM
|
1st review completed | | | 10/7/2015 | | DONE |
Javier Guzman
|
|
|
|