Letter of compliance/Occupancy | | | 5/13/2016 | | DONE |
|
|
|
|
BLD-Final | 2/6/2016 | 2/8/2016 | 2/8/2016 | A | PASS |
Jim Storey
|
|
|
call Dan for garage access code Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 2/8/2016 | 2/8/2016 | 2/8/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 12/14/2015 | 12/14/2015 | 12/14/2015 | P | PASS |
Phil Shearer
|
|
|
3:00 PM or later Call Dan I can meet you there to go over engineering Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 12/14/2015 | 12/14/2015 | 12/14/2015 | P | PASS |
Phil Shearer
|
|
|
3:00 PM or later Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Conference | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | DONE |
Phil Shearer
|
|
|
Meeting at 9:00 AM to go over framing corrections with Framing contractor Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | PART |
Phil Shearer
|
|
|
Meeting at 9:00 AM to go over framing corrections with Framing contractor Phone #: ###-#### Inspection requested via web by Daniel Appel. Strapping and interior sheer
|
BLD-Framing/Rough-in | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | NR |
Phil Shearer
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall Bracing | 11/25/2015 | 11/27/2015 | 11/27/2015 | A | PASS |
Phil Shearer
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel. Exterior only
|
BLD-Wall Bracing | 11/24/2015 | 11/25/2015 | 11/25/2015 | P | FAIL |
Phil Shearer
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel. No plans onsite.
|
BLD-Foundation | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Phil Shearer
|
|
|
Chris King Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Footing | 10/30/2015 | 11/2/2015 | 11/2/2015 | A | PASS |
Phil Shearer
|
|
|
Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/27/2015 | | |
|
|
|
|
Plan assigned to (DAF) | 10/14/2015 | 10/20/2015 | 10/27/2015 | | DONE |
David Ferguson
|
|
|
due 10/22 ePlan - failed due to structural issues
|
Routing - PLAN CHECK | 10/27/2015 | | 10/27/2015 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/27/2015 | | DONE |
|
|
|
requirements met
|
Routing - PLANNING | 10/8/2015 | | 10/21/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 10/8/2015 | | 10/20/2015 | | FAIL |
David Ferguson
|
|
|
Need missing pages and engineering/sheerwall
|
1st review completed | | | 10/20/2015 | | FAIL |
David Ferguson
|
|
|
Need missing pages and engineering/sheerwall
|
Plan assigned to (LEG) Tisha | 10/8/2015 | | 10/14/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 10/8/2015 | | 10/14/2015 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 10/8/2015 | | 10/8/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/8/2015 | | 10/8/2015 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 10/8/2015 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/8/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/8/2015 | | DONE |
|
|
|
|
Application received | | | 10/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 7 2015 2:09PM
|
Intake Approval | | | 10/7/2015 | | FAIL |
|
|
|
need revised prescriptive-can't read the one on the plans
|