BLD-Final | 4/11/2016 | 4/12/2016 | 4/12/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
DOC - Permit Finaled | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Conference | 4/8/2016 | 4/11/2016 | 4/11/2016 | A | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### >> Inspection requested via web by Weston Wagner Inspection cancelled from web by: Weston Wagner
|
BLD-Final | 4/7/2016 | 4/8/2016 | 4/8/2016 | A | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### >> Inspection requested via web by Weston Wagner Inspection cancelled from web by: Weston Wagner
|
BLD-Energy code compliance | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Framing/Rough-in | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Framing/Rough-in | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner. Truss bracing, Stairs
|
BLD-Wall Bracing | 1/13/2016 | 1/15/2016 | 1/15/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Foundation | 11/13/2015 | 11/13/2015 | 11/13/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Footing | 11/12/2015 | 11/12/2015 | 11/12/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
OVERRIDE | | | 10/26/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/26/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/26/2015 | | DONE |
|
|
|
|
1st review completed | | | 10/26/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/26/2015 | | DONE |
|
|
|
All requirements met
|
Plan assigned to (LEG) Tisha | 10/13/2015 | | 10/26/2015 | | DONE |
Tisha Gallop
|
|
|
10/27 ePlan
|
Routing - PLAN CHECK | 10/13/2015 | | 10/26/2015 | | PASS |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | | | 10/15/2015 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 10/13/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/13/2015 | | DONE |
|
|
|
|
Routing - Addressing | 10/13/2015 | | 10/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/13/2015 | | 10/13/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | | | 10/13/2015 | | PASS |
|
|
|
Ok per SP-01
|
Application received | | | 10/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 7 2015 4:54PM
|