BLD-Final | 6/8/2016 | 6/9/2016 | 6/9/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
DOC - Permit Finaled | 6/9/2016 | 6/9/2016 | 6/9/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | NR |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Energy code compliance | 4/1/2016 | 4/4/2016 | 4/4/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Framing/Rough-in | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Energy code compliance | 3/29/2016 | 3/31/2016 | 3/31/2016 | A | NR |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Framing/Rough-in | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner. Fire blocking livingroom at shelving, trussbracing. OK to insulate
|
BLD-Wall Bracing | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Wall Bracing | 3/11/2016 | 3/14/2016 | 3/14/2016 | A | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### >> Inspection requested via web by Weston Wagner Inspection cancelled from web by: Weston Wagner
|
BLD-Foundation | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | CANC |
Phil Shearer
|
|
|
|
BLD-Foundation | 2/16/2016 | 2/16/2016 | 2/16/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 2/12/2016 | 2/12/2016 | 2/12/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 2/9/2016 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 2/9/2016 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 10/30/2015 | | |
|
|
|
|
Plan assigned to (DAF) | 10/23/2015 | 10/23/2015 | 10/30/2015 | | DONE |
David Ferguson
|
|
|
due 11/3 ePlan
|
1st review completed | | | 10/30/2015 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2015 | | DONE |
David Ferguson
|
|
|
|
Permit Ready to Issue | | | 10/30/2015 | | DONE |
|
|
|
all requirements met
|
Routing - PLAN CHECK | 10/20/2015 | | 10/30/2015 | | PASS |
David Ferguson
|
|
|
|
Routing - MECHANICAL | 10/20/2015 | | 10/27/2015 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 10/20/2015 | | 10/23/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/20/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/20/2015 | | DONE |
|
|
|
|
Routing - Addressing | 10/20/2015 | | 10/20/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/20/2015 | | 10/20/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 10/20/2015 | | 10/20/2015 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 10/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 16 2015 9:06AM
|