BLD-Final | 4/19/2016 | 4/20/2016 | 4/20/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
DOC - Permit Finaled | 4/20/2016 | 4/20/2016 | 4/20/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 2/16/2016 | 2/17/2016 | 2/17/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Framing/Rough-in | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Energy code compliance | 2/16/2016 | 2/18/2016 | 2/16/2016 | P | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### >> Inspection requested via web by Weston Wagner Inspection cancelled from web by: Weston Wagner
|
BLD-Framing/Rough-in | 2/12/2016 | 2/16/2016 | 2/16/2016 | A | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner. D3 girder nailing, Point load support transfer though the floor. PK to insulate.
|
BLD-Wall Bracing | 1/28/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Wall Bracing | 1/26/2016 | 1/27/2016 | 1/27/2016 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner no foundation pass no wall bracing until passed
|
BLD-Foundation | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 12/10/2015 | 12/10/2015 | 12/10/2015 | A | NR |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 12/3/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/3/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/20/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 10/23/2015 | 10/23/2015 | 11/20/2015 | | DONE |
Brian McGowan
|
|
|
due 11/4 ePlan. 1st Review Complete, Failed. Incorrect Engineering provided, missing support for point loads on Foundation Plan.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/20/2015 | | DONE |
|
|
|
requirements met
|
Routing - PLAN CHECK | 11/19/2015 | | 11/19/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/19/2015 | | 11/19/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
1st review completed | | | 11/5/2015 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 10/21/2015 | | 11/5/2015 | | FAIL |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 10/21/2015 | | 10/27/2015 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 10/21/2015 | | 10/23/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/21/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/21/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/21/2015 | | DONE |
|
|
|
|
Routing - Addressing | 10/21/2015 | | 10/21/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PLANNING | 10/21/2015 | | 10/21/2015 | | PASS |
Leon Letson
|
|
|
|
Routing PW Sewer Rating | 10/21/2015 | | 10/21/2015 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 10/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 16 2015 9:38AM
|