Third Notice | | 4/17/2016 | 4/13/2016 | | DONE |
|
|
|
This permit finaled on the web by Paula Swensen
|
Second Notice | | 3/20/2016 | 4/12/2016 | | DONE |
|
|
|
sent in mail 4-13-16
|
First Notice | | 2/29/2016 | 3/10/2016 | | DONE |
|
|
|
mailed 3-11-16
|
BLD-Final | 2/19/2016 | 2/19/2016 | 2/19/2016 | P | PASS |
Dave Hannah
|
|
|
would like call ahead; Paula Phone #: ###-####
|
Permanent Occupancy | | | 2/19/2016 | | DONE |
|
|
|
|
BLD-Final | 2/18/2016 | 2/18/2016 | 2/18/2016 | P | PART |
Phil Shearer
|
|
|
would like call ahead; Paula Phone #: ###-####. Need new side door hardware. OK for Temp CO
|
FIRE-Final Inspection | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide automatic flush bolts on the double exit door and single action hardware on the north exit door prior to a building inspection as per conversation.
|
Temporary Occupancy | 2/18/2016 | 5/18/2016 | 2/18/2016 | | DONE |
Brittany Hill
|
|
|
|
BLD-Ceiling Grid Inspection | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PASS |
Phil Shearer
|
|
|
would like call ahead; Paula Phone #: ###-####
|
BLD-Framing/Rough-in | 1/25/2016 | 1/26/2016 | 1/26/2016 | A | PASS |
Phil Shearer
|
|
|
Ken Phone #: ###-####. Soffit OK to cover
|
BLD-Framing/Rough-in | 1/14/2016 | 1/14/2016 | 1/14/2016 | P | PART |
Phil Shearer
|
|
|
Ken Phone #: ###-####. Back rooms ok for cover
|
Issue PAID IN FULL permit | | | 12/4/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/4/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 10/19/2015 | 10/19/2015 | 12/3/2015 | | DONE |
Carl D Madsen
|
|
|
Level 3 TI - Paper - Dominoes Pizza
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/3/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/3/2015 | | DONE |
|
|
|
***requirements met 12-3-15 CAN***need GC & rev cert of val
|
Telephone call | | | 12/3/2015 | | DONE |
|
|
|
Spoke with Paula informing him that the permit is ready and that a 306 and 306 from the GC is needed to place the final fees in there
|
Routing - PLAN CHECK | 11/19/2015 | | 12/3/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 11/25/2015 | | 11/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 11/17/2015 | | 11/19/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to plans.
|
1st review completed | | | 11/19/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 11/17/2015 | | FAIL |
Carl D Madsen
|
|
|
E-Mailed the plan review report to the architect, 11-17-15
|
Routing - PLUMBING | | | 10/22/2015 | | PASS |
Bill VanDegrift
|
|
|
1) provide shutoff valve at MAU water
2) indirect 3 compartment sink
3) ASSE 1070 mixing valve required at hand sinks and lavs
|
Routing - Addressing | 10/19/2015 | | 10/20/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 10/20/2015 | | 10/20/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Environmental | 10/20/2015 | | 10/20/2015 | | PASS |
Rick Christenson
|
|
|
|
Pending Assignment by JCB | 10/16/2015 | | 10/19/2015 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 10/19/2015 | | DONE |
Jason Blais
|
|
|
Emailed representative to have them contact ACHD to evaluate if any impact fees are due. Our Permit Counter will need written verification prior to the building permit being issued.
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/16/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2015 | | DONE |
|
|
|
|
Application received | | 10/16/2015 | | | |
|
|
|
|