Permit Information
Permit NumberBLD15-03835
StatusFinaled
Name MICHAEL J BROWN
Site Address 505 W BROAD ST
Project NameThe Fowler - Below Podium TI
Customer NumberREF:BLD15-03423 & 3424
ePlanReview 
Description
(THE FOWLER – Core Area Build Out – Below Podium Structure) **GREEN TAG-Expedited Review-LEED Project - PROJECT MANAGEMENT-Angie Brosious**Plan mod for ASI046 only, removing partition wall in commercial space A/B and D and associated plumbing and mechanical. **6-2-17**ajs**Permit to build out a new 68,730 square foot (2) story shell building originally constructed under BLD15-02043. The first floor is around 34,000 square feet and the second floor is around 34,730 square feet. This building is fully fire sprinklered with an NFPA 13 system to comply with the 5 story wood construction ordinance. Scope of work includes: [installation of interior non-bearing walls and bearing walls to create 5 live/work units, four future tenant spaces on the first floor, and accessory office / residential amenidty rooms on the second floor], new plumbing, new electrical, new mechanical, new insulation, new windows, new doors, and interior finishes in compliance with Chapter 8 of the 2012 IBC. NOTE: the tenant spaces on the first floor are not allowed occupancy until a separate permit is pulled to remodel and occupy those spaces. This building will be sprinklered with a fully compliant NFPA 13 system to comply with the 5 story wood construction ordinance. **TLW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 6/16/20186/16/2018 DONE
This permit finaled on the web by Ami Tracy
Third Notice 5/15/20186/11/2018 DONE
Mailed 6-12
Second Notice 4/20/20185/10/2018 DONE
mailed 5-11-18
First Notice 3/17/20184/10/2018 DONE
mailed 4-11-18
BLD-Final3/7/20183/8/20183/7/2018APASS
DetailsDave Hannah
Jason Phone #: ###-####
Permanent Occupancy  3/7/2018 DONE
BLD-Final2/28/20183/1/20183/2/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Final3/1/20183/2/20183/2/2018APASS
DetailsDave Hannah
Jason Phone #: ###-####
Zoning Approval3/2/20183/2/20183/2/2018 PASS
DetailsSarah Schafer
FIRE-Final Inspection2/28/20183/1/20183/1/2018APASS
DetailsJim Page
Final life fire safety inspection for this permit complete.
FIRE-Final Inspection2/22/20182/22/20182/22/2018PFAIL
DetailsJim Page
Provide as-builts for stairwell pressurization activation automatic function/manual function and overide, fire alarm permit will not be finaled until as-builts are submitted and approved.
Temporary Occupancy2/2/20185/3/20182/2/2018 DONE
DetailsChristina Prado
FIRE-Final Inspection1/29/20181/29/20181/29/2018PPART
DetailsJim Page
Fire sprinkler inspection complete for level 1 lobby and level 2 common areas. Fire alarm testing partially complete for parking levels, additional notification required on level 1.5 landing on southside of garage. Fire alarm testing complete for level 1 lobby and level 2 common areas. Fire extinguishers are in place with current inspection tags.
BLD-Final1/25/20181/26/20181/29/2018PPEND
DetailsDave Hannah
Level 1 and 2 not 2nd garage live work units Jason Phone #: ###-####
FIRE-Final Inspection1/25/20181/26/20181/26/2018PCANC
DetailsJim Page
Inspection request for life fire safety TCO will be rescheduled for 29JAN2018.
BLD-Final1/19/20181/23/20181/23/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-####
FIRE-Final Inspection1/22/20181/23/20181/23/2018ACANC
DetailsJim Page
Issues with fire alarm on level 6, more testing needs to be completed before TCO, this request is cancelled.
FIRE-Final Inspection1/19/20181/22/20181/22/2018ACANC
DetailsJim Page
Due to inspection load, this inspection will be rescheduled by Jason Phone #: ###-#### for 9AM, this request is cancelled.
BLD-Conference1/3/20181/3/20181/4/2018PDONE
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Ceiling Grid Inspection1/2/20181/2/20181/2/2018PPASS
DetailsDave Hannah
Inspection request for the ceiling grid at the management office. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
BLD-Final12/20/201712/22/201712/22/2017APART
DetailsDave Hannah
Jason Phone #: ###-####

Dave, requesting partial final for garage only up to mezzanine. Chad has signed off for mechancal on card in my office. Sarah is going out this afternoon to inspect garage interior. Public Works sign off not needed for this phase. Thanks, Angie ok for temp occ obn phase one parking garege only.
Temporary Occupancy12/22/20173/22/201812/22/2017 DONE
DetailsChristina Prado
FIRE-Final Inspection12/18/201712/19/201712/19/2017APART
DetailsJim Page
Life fire safety inspection for phase 1 TCO complete.
Print Occupancy Form  12/18/2017 DONE
DetailsChristina Prado
BLD-Conference12/4/201712/5/201712/5/2017PDONE
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Conference11/17/201711/20/201711/20/2017APASS
DetailsDave Hannah
Conference request for Core ; Shell. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
BLD-Ceiling Grid Inspection11/16/201711/17/201711/17/2017APASS
DetailsDave Hannah
Inspection request for the ceiling grid in the Live Works and Housing lobby. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Ceiling Grid Inspection10/30/201710/30/201710/30/2017APASS
DetailsDave Hannah
Inspection Request for ceiling grids and wall covering. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
BLD-Ceiling Grid Inspection10/24/201710/25/201710/25/2017AFAIL
DetailsDave Hannah
Inspection request for (2) two grid ceilings on the first floor. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus fire stopping above ceiling
BLD-Other10/19/201710/20/201710/20/2017APASS
DetailsDave Hannah
Monte-fire wall in trash room Phone #: ###-####
BLD-Ceiling Grid Inspection10/16/201710/17/201710/17/2017APASS
DetailsDave Hannah
Monty-3A Phone #: ###-####
BLD-Ceiling Grid Inspection9/20/20179/21/20179/21/2017APASS
DetailsDave Hannah
level 5 & 6 // Monte Phone #: ###-####
BLD-Framing/Rough-in9/19/20179/20/20179/20/2017APART
DetailsDave Hannah
Inspection request for 5th floor Drop Ceilings. Phone #: ###-#### Inspection requested via web by Carl Benjamin needs to fix some fire assemblies
BLD-Energy code compliance9/19/20179/20/20179/20/2017APASS
DetailsDave Hannah
Inspection request for Live Works ! thru 5 Insulation and main entry Lobby fire caulking Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Framing/Rough-in9/18/20179/19/20179/19/2017APASS
DetailsDave Hannah
6B roof & ceiling 5A & 5B - Monty Phone #: ###-#### 6B only ok to cover
BLD-Framing/Rough-in9/15/20179/18/20179/18/2017AFAIL
DetailsDave Hannah
Inspection request for framing in the entry lobby walls. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Ceiling Grid Inspection9/11/20179/12/20179/12/2017APASS
DetailsDave Hannah
7th floor // monte Phone #: ###-####
BLD-Framing/Rough-in8/8/20178/9/20178/9/2017APART
DetailsBrandon Shaw
For the Mechanical Soffit Framing at the garage side of the Live work.
BLD-Aging Inspection7/7/20177/7/20177/7/2017 PASS
DetailsDave Hannah
CHANGE STATUS TO (ISS)  6/12/2017 DONE
DetailsChristina Prado
(F) Reprint permit  6/12/2017 DONE
OVERRIDE  6/5/2017  
Plan assigned to (AJS)5/12/20175/12/20176/5/2017 PASS
DetailsAdele J Schaffeld-Griffin
Permit Ready to Issue  6/5/2017 DONE
DetailsChristina Prado
Plan Mod approved, all requirements met

DO NOT RE-ISSUE
Routing - PLAN CHECK6/1/2017 6/2/2017 PASS
DetailsAdele J Schaffeld-Griffin
Plan mod for ASI046 only, removing partition wall in commercial space A/B and D and associated plumbing and mechanical.
BLD-Other5/26/20175/30/20175/30/2017APASS
DetailsDave Hannah
Live work , fire caulking - Carl Phone #: ###-####
Routing - PLAN CHECK5/15/2017 5/24/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental5/15/2017 5/22/2017 PASS
DetailsRick Christenson
Routing - FIRE5/15/20175/15/20175/17/2017 PASS
DetailsKatie Marron
Modifications to include heat pump and electrical panel for future tenant space reviewed. No additional comments required.
Routing - Design Review5/15/2017 5/16/2017 PASS
DetailsSarah Schafer
Routing PW Drainage5/15/2017 5/15/2017 PASS
DetailsBrian Murphy
Routing - MECHANICAL5/15/2017 5/15/2017 PASS
DetailsTroy James
Routing - PLUMBING5/15/2017 5/15/2017 PASS
DetailsDaryl Spivey
Per Plan & ISPC
Routing - Addressing5/15/2017 5/15/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS5/15/2017 5/15/2017 PASS
DetailsRachael Beierle
PREPARING FOR FUTURE DINING. FEES APPLIED WEN TI IS SUBMITTED
Plan Modification Accepted  5/12/2017 DONE
DetailsChristina Prado
Modifications to commercial tenant A/B space to provide MEP rough-in for future tenant use: location of heat pumps noted for future install by tenant; cold water line stubbed in; power for canopy-mounted letter signs revised to stub into tenant space
200A electrical panel added where conduit previously stubbed for future use, to be surface mounted to existing 1-hr rated; demising wall.
BLD-Conference4/5/20174/6/20174/6/2017APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Carl Benjamin ok to use fire details for first floor work live units
BLD-Framing/Rough-in2/22/20172/22/20172/23/2017PPART
DetailsDave Hannah
Chris Phone #: ###-#### ext framing first and second floor ok to cover ext.
BLD-Framing/Rough-in1/18/20171/19/20171/20/2017APART
DetailsDave Hannah
Inspection request for Metal Stud Framing at East Elevation of Floors 1 and 2. Phone #: ###-#### Inspection requested via web by Carl Benjamin ok to cover ext e
wall
Place hold on job2/22/2016 4/12/2016 DONE
DetailsBrittany Hill
Need ACHD, RP, Revised Certificate of Value and GC form for issuance

DO NOT ISSUE WITHOUT BLD15-03423 & BLD15-03424
Issue PAID IN FULL permit  4/12/2016 DONE
Print Occupancy Form  4/12/2016 DONE
Telephone call  4/7/2016 DONE
Left a message with Leslie informing her that this is one of three permits for this address, but that this one is showing it will expire in ten days and if they would like a 180 day extension they would need to email Jason B
Expiration Notice3/22/20164/12/20163/22/2016 DONE
DetailsBrittany Hill
OVERRIDE  2/22/2016  
Routing - PLAN CHECK2/4/2016 2/22/2016 PASS
DetailsTim L. Woodard
Routing - PLUMBING2/4/2016 2/22/2016 PASS
DetailsTim L. Woodard
Approved in E-Plan. TLW
Routing Off Site - STRUCTURAL2/4/2016 2/22/2016 PASS
DetailsTim L. Woodard
Approved in E-Plan Review. TLW
PLANS/APPL TAKEN TO FRONT DESK  2/22/2016 DONE
Routing - Erosion and Sediment2/4/2016 2/22/2016 PASS
DetailsTim L. Woodard
Approved in E-Plan Review. TLW
Routing - MECHANICAL2/4/2016 2/22/2016 PASS
DetailsTim L. Woodard
Approved per E-Plan. TLW
Permit Ready to Issue  2/22/2016 DONE
DetailsChristina Prado
Need ACHD, RP, Revised Certificate of Value and GC form for issuance//All requirements met 4/11/16 CDP


DO NOT ISSUE WITHOUT BLD15-03423 & BLD15-03424
Plan assigned to (TLW)10/19/2015 2/22/2016 PASS
DetailsTim L. Woodard
Plan resubmittals received  2/4/2016  
DetailsTim L. Woodard
Routing - FIRE12/28/201512/28/201512/28/2015 PASS
DetailsKatie Marron
Fire correction items resubmitted under BLD15-03423 (upper apartment bldg permit). Approved per revised report.
Routing Off Site - STRUCTURAL10/19/2015 11/18/2015 FAIL
DetailsTim L. Woodard
1st review completed  11/18/2015 DONE
Routing - PLAN CHECK10/19/2015 11/18/2015 FAIL
DetailsTim L. Woodard
Routing - MECHANICAL10/19/2015 11/18/2015 FAIL
DetailsTroy James
Routing - PLUMBING10/19/2015 11/18/2015 FAIL
DetailsDaryl Spivey
Routing - PUBLIC WORKS10/19/2015 11/18/2015 PASS
DetailsTim L. Woodard
per BLD15-03423 by Beverly Mountain
Routing PW Sewer Design10/23/2015 11/18/2015 PASS
DetailsKyle S. Rosenmeyer
Routing PW Sewer Rating10/23/2015 11/3/2015 PASS
DetailsBarbara Moore
Routing PW Environmental10/23/2015 10/26/2015 PASS
DetailsRick Christenson
Routing PW Solid Waste10/23/2015 10/23/2015 PASS
DetailsMegan Durrell
Routing PW Geothermal10/23/2015 10/23/2015 PASS
DetailsJon R. Gunnerson
Coordinate geothermal connection with Public Works - 208.384.3935
Routing - Addressing10/19/2015 10/23/2015 PASS
DetailsEmily Dixon
Routing - Design Review10/19/2015 10/23/2015 PASS
DetailsSarah Schafer
Approved per DRH15-00152
Routing PW Drainage10/23/2015 10/23/2015 PASS
DetailsBrian Murphy
Routing PW Street Lights10/23/2015 10/23/2015 FAIL
DetailsMike D Hedge
See BLD15-03423 in E Plan.
Routing - FIRE10/19/201510/19/201510/20/2015 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - PLANNING Land Div10/19/2015 10/20/2015 PASS
DetailsDave Abo
Routing - Erosion and Sediment10/19/2015 10/20/2015 FAIL
DetailsEvan Jenkins
Full ESC Narrative or SWPPP (To Meet Federal EPA ESC Requirements for 2012 CGP) Required per BCC 8-17 ESC Requirements, for approval. Evan Jenkins 794.3958
Pending Assignment by TLW10/19/2015 10/19/2015 DONE
DetailsTim L. Woodard
Intake Approval  10/16/2015  
DetailsTim L. Woodard
Application received 10/19/2015   
Routing - MECHANICAL6/1/2017