Print Statement | | | 8/17/2016 | | DONE |
|
|
|
|
Second Notice | | 7/21/2016 | 8/11/2016 | | DONE |
|
|
|
Mailed 8-11-16
|
First Notice | | 6/20/2016 | 7/11/2016 | | DONE |
|
|
|
Mailed 7-12
|
BLD-Final | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Tony Young
|
|
|
Richard Phone #: ###-####
|
Permanent Occupancy | | | 6/10/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, commercial hood suppression system inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Foundation | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | CANC |
Jim Sly
|
|
|
rebar; Richard Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | PASS |
Jim Sly
|
|
|
rebar; Richard Phone #: ###-####
|
BLD-Framing/Rough-in | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | PASS |
Tony Young
|
|
|
Richard Phone #: ###-####
|
BLD-Framing/Rough-in | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | PART |
Tony Young
|
|
|
Robert Phone #: ###-####,, walls only ok
|
Issue PAID IN FULL permit | | | 3/29/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/29/2016 | | DONE |
|
|
|
|
Expiration Notice | 3/24/2016 | 4/14/2016 | 3/24/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 11/24/2015 | | |
|
|
|
|
Plan assigned to (JG) | 10/30/2015 | 10/30/2015 | 11/24/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/24 Level 3 TI - ePlanReview - Chipotle pending others
|
Routing - Erosion and Sediment | 11/24/2015 | | 11/24/2015 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved - no RP designated at time of application.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2015 | | DONE |
|
|
|
Need RP, All other requirements met 3/9/16 //C_P
GC Form and Revised Cert of Value
|
Routing PW Solid Waste | 11/2/2015 | | 11/23/2015 | | PASS |
Megan Durrell
|
|
|
|
Route to Impact Fee Review | 11/18/2015 | 11/21/2015 | 11/19/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 11/18/2015 | | FAIL |
Javier Guzman
|
|
|
eplan
|
Routing Off Site - C.D.H | 10/30/2015 | | 11/18/2015 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by Natasha Ferney
|
Routing - PLAN CHECK | 10/30/2015 | | 11/18/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 10/30/2015 | | 11/10/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 10/30/2015 | | 11/5/2015 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required
chemical station must have a true air gap
|
Routing - FIRE | 10/30/2015 | 10/30/2015 | 11/3/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - Erosion and Sediment | 10/30/2015 | | 11/2/2015 | | FAIL |
Evan Jenkins
|
|
|
ESC Waiver Letter Request Required per BCC 8-17
Evan Jenkins 794.3958
|
Pending Assignment by JCB | 10/30/2015 | | 10/30/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Design Review | 10/30/2015 | | 10/30/2015 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH15-00302
|
Routing - Addressing | 10/30/2015 | | 10/30/2015 | | PASS |
Emily Dixon
|
|
|
Suite 110 added.
|
Routing - PUBLIC WORKS | 10/30/2015 | | 10/30/2015 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 10/28/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Westfall and plan review fees paid.
|
Intake Approval | | | 10/26/2015 | | FAIL |
|
|
|
1) Please fill out form “#520 – Major Tenant Improvement Submittal Checklist” and upload it into the Documents folder of ePlanReview. Make sure all required documents are uploaded.
2) Provide a completed Food Establishment License application and Food Establishment Plan Review and Approval form. (1 copy of each) Forms are available at: http://www.cdhd.idaho.gov/EH/food/forms.htm. Initial submittal does NOT require a trip to CDHD if submitting electronically, however, CDHD may require a separate meeting for specific cases.
3) Show locations of portable fire extinguishers.
4) Heating and cooling load calculations to justify the proposed HVAC units.
|
Plan Reviewer's activity | | | 10/26/2015 | | PASS |
|
|
|
Plan intake approved
|
Application received | | | 10/21/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 21 2015 4:17PM
|