First Notice | 1/24/2018 | 1/24/2018 | 2/12/2018 | | DONE |
Tony Young
|
|
|
Mailed 2-13-18
|
BLD-Final | 1/24/2018 | 1/24/2018 | 1/24/2018 | P | DONE |
Tony Young
|
|
|
Project complete, last open permit needs to be DOC-FINAL - Christina Phone #: ###-####
|
DOC - Permit Finaled | 1/24/2018 | 1/24/2018 | 1/24/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 7/8/2016 | 7/8/2016 | 7/8/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | PART |
Jim Sly
|
|
|
Ed Phone #: ###-#### C/N. Nail hanger in Laundry, Install Tlitan Bolts in bottom plates, Fireblock at Fireplaces and Bathroom. Install required holddowns at ext walls. Talk to Ed. OK to insulate after Mech rough-in passes or do not cover any areas Mechanical.
|
BLD-Wall Bracing | 1/27/2016 | 1/28/2016 | 1/28/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, exterior ok,,
|
BLD-Wall Bracing | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | PART |
Tony Young
|
|
|
Ed/// Inspection for Clubhouse Phone #: ###-####,, ok after a couple fixes on club house
|
BLD-Other | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | PASS |
Tony Young
|
|
|
Ed/// Inspection for Clubhouse''s roof sheathing Phone #: ###-####,, ok after a couple fixes,, Ed to verify
|
BLD-Footing | 11/16/2015 | 11/18/2015 | 11/18/2015 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-#### (rescheduled 11-17-15),, foundation,, slab,, interior footings ok pending special inspection report,, S. I. on site
|
BLD-Footing | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | PASS |
Phil Shearer
|
|
|
Ed Phone #: ###-####. Exterior footings
|
BLD-Footing | 11/2/2015 | 11/2/2015 | 11/2/2015 | P | CANC |
Tony Young
|
|
|
Barry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/2/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/2/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/30/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 10/26/2015 | 10/26/2015 | 10/30/2015 | | PASS |
Carl Westfall
|
|
|
Clubhouse footing/foundation plan mod (submitted 10-27-15)
|
Routing - PLAN CHECK | 10/27/2015 | | 10/30/2015 | | PASS |
Carl Westfall
|
|
|
Footing, foundation, and slab on grade only
|
Routing Off Site - STRUCTURAL | 10/27/2015 | | 10/30/2015 | | PASS |
Carl Westfall
|
|
|
Jan Welch - footing, foundation, and slab on grade only
|
Plan Reviewer's activity | | | 10/30/2015 | | DONE |
|
|
|
Plan modification approved
|
Permit Ready to Issue | | | 10/30/2015 | | DONE |
|
|
|
requirements met
|
Plan resubmittals received | | | 10/27/2015 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/26/2015 | 10/29/2015 | 10/26/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CJW) | 10/23/2015 | 10/23/2015 | 10/26/2015 | | PASS |
Carl Westfall
|
|
|
Kensington Clubhouse
|
Routing - PLAN CHECK | 10/23/2015 | | 10/26/2015 | | PASS |
Carl Westfall
|
|
|
Footing and foundation permit allowed
|
1st review completed | | | 10/26/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/26/2015 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan Modification Accepted | | | 10/26/2015 | | DONE |
Christina Prado
|
|
|
Plan mod accepted for changes to the foundation details
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2015 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 10/23/2015 | | PASS |
Christina Prado
|
|
|
|
Application received | | 10/22/2015 | | | |
|
|
|
|