Second Notice | | 4/22/2016 | 5/10/2016 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | | 3/31/2016 | 4/12/2016 | | DONE |
|
|
|
Mailed 4-13-16
|
BLD-Final | 3/18/2016 | 3/21/2016 | 3/21/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landva OK for Perm Occ..
|
FIRE-Final Inspection | 3/18/2016 | 3/21/2016 | 3/21/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 3/21/2016 | | DONE |
|
|
|
|
BLD-Final | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter Need Fire final.
|
FIRE-Final Inspection | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | FAIL |
Troy Cobbley
|
|
|
Need mechanical room ceiling extended or sprinkler modifications provided. The sprinkler permit will then need to be finaled. Need the southeast exit sign repaired.
|
BLD-Ceiling Grid Inspection | 3/2/2016 | 3/3/2016 | 3/3/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Ceiling Grid Inspection | 3/1/2016 | 3/2/2016 | 3/2/2016 | P | NR |
Jim Sly
|
|
|
note: electrical scheduled for PM also. Phone #: ###-#### Inspection requested via web by Todd Landvatter complete firestopping
|
BLD-Wall cover | 2/8/2016 | 2/9/2016 | 2/9/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Wall cover | 2/4/2016 | 2/5/2016 | 2/5/2016 | P | PASS |
Jim Sly
|
|
|
inspection for insulation on 1 hour walls in sleeping area. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Framing/Rough-in | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Conference | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | DONE |
Jim Sly
|
|
|
Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/14/2016 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 1/14/2016 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 10/28/2015 | 10/28/2015 | 11/18/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 11/18/2015 | | 11/18/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/18/2015 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLAN CHECK | 10/28/2015 | | 11/13/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 11/13/2015 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 10/28/2015 | | 11/3/2015 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 10/28/2015 | 10/28/2015 | 11/2/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to case
|
Routing - Design Review | 10/28/2015 | | 10/29/2015 | | PASS |
Josh Wilson
|
|
|
|
Intake Approval | | | 10/28/2015 | | PASS |
|
|
|
|
Application received | | | 10/26/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 26 2015 1:19PM
|