BLD-Final | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 1/20/2016 | 1/20/2016 | 1/20/2016 | P | PASS |
Dave Hannah
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 1/15/2016 | 1/19/2016 | 1/19/2016 | P | PASS |
Jim Sly
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 1/14/2016 | 1/15/2016 | 1/18/2016 | P | NR |
Dave Hannah
|
|
|
Brett Phone #: ###-####
|
BLD-Wall Bracing | 1/4/2016 | 1/5/2016 | 1/5/2016 | A | PASS |
Dave Hannah
|
|
|
Josh Phone #: ###-####
|
BLD-Foundation | 12/4/2015 | 12/7/2015 | 12/7/2015 | P | CANC |
Dave Hannah
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 12/3/2015 | 12/4/2015 | 12/4/2015 | P | PASS |
Dave Hannah
|
|
|
Manuel Phone #: ###-####
|
BLD-Foundation | 12/2/2015 | 12/3/2015 | 12/4/2015 | P | CANC |
Dave Hannah
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 12/4/2015 | 12/4/2015 | 12/4/2015 | A | PASS |
Dave Hannah
|
|
|
|
Plan assigned to (BJM) | 10/29/2015 | 10/29/2015 | 12/3/2015 | | DONE |
Brian McGowan
|
|
|
due 11/10 ePlan. 1st review complete, Failed. Section and plans do not match. 11-06-15
|
BLD-Footing | 12/1/2015 | 12/2/2015 | 12/2/2015 | P | NR |
Mike Jordan
|
|
|
DAne Phone #: ###-####
|
BLD-Footing | 11/30/2015 | 12/1/2015 | 12/1/2015 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/19/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/19/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/9/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 11/9/2015 | | 11/9/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/9/2015 | | DONE |
|
|
|
All Met
|
Routing - PLAN CHECK | 10/27/2015 | | 11/9/2015 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 11/6/2015 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/6/2015 | | 11/6/2015 | | FAIL |
Brian McGowan
|
|
|
Building section does not match the rest of the plan or the plan dies not match the Building Section
|
Routing - MECHANICAL | 10/27/2015 | | 11/4/2015 | | PASS |
Troy James
|
|
|
|
Plan assigned to (LEG) Tisha | 10/27/2015 | | 10/29/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Application received | | | 10/27/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 27 2015 9:20AM
|
Intake Approval | | | 10/27/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/27/2015 | | DONE |
|
|
|
|
Routing - Addressing | 10/27/2015 | | 10/27/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/27/2015 | | 10/27/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 10/27/2015 | | 10/27/2015 | | PASS |
Colleen T Carroll
|
|
|
|