BLD-Final | 9/9/2016 | 9/12/2016 | 9/12/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 7/17/2016 | 7/19/2016 | 7/19/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 7/19/2016 | 7/19/2016 | 7/19/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 7/12/2016 | 7/15/2016 | 7/15/2016 | A | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall. Point load girder in the liveingroom, Poaint load support 2PLY girder though the floor to foundation, Truss clips above stairs, floor truss hanger in garge missing nails. OK to insulate
|
BLD-Wall cover | 6/9/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Phil Shearer
|
|
|
Shear // Antonio Phone #: ###-####
|
BLD-Foundation | 4/21/2016 | 4/21/2016 | 4/21/2016 | P | PASS |
Phil Shearer
|
|
|
Avaro Phone #: ###-####
|
BLD-Footing | 4/20/2016 | 4/20/2016 | 4/20/2016 | P | PASS |
Phil Shearer
|
|
|
Avarro Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/13/2016 | | DONE |
|
|
|
|
Expiration Notice | 4/1/2016 | 4/22/2016 | 4/1/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 11/18/2015 | | |
|
|
|
|
Telephone call | | | 11/18/2015 | | DONE |
|
|
|
called Tahoe- left message that permit is ready for pick up and fees due
|
Routing - PLAN CHECK | 11/18/2015 | | 11/18/2015 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/18/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/18/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/18/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (LEG) Tisha | 10/27/2015 | | 11/18/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 11/10; need calcs for (2) eng'd shear lines on plan.
|
Plan resubmittals received | | | 11/17/2015 | | DONE |
Tisha Gallop
|
|
|
updated engineering
|
Routing - PLAN CHECK | 11/4/2015 | | 11/10/2015 | | FAIL |
Tisha Gallop
|
|
|
e-mailed Leonard
|
1st review completed | | | 11/10/2015 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 10/29/2015 | | 11/4/2015 | | PASS |
Troy James
|
|
|
|
Routing PW Flood Plain | 10/29/2015 | | 10/29/2015 | | CANC |
Jason C. Taylor
|
|
|
LOMR, no floodplain requirements. JCT
|
Routing - Addressing | 10/27/2015 | | 10/29/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 10/27/2015 | | 10/29/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 10/29/2015 | | 10/29/2015 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/27/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/27/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/27/2015 | | DONE |
|
|
|
|
Application received | | 10/27/2015 | | | |
|
|
|
|